RESOLVED that Cabinet – (a) acknowledge the latest cost and budget position (Appendix 1 to the report); (b) approves the updated Business Case (Appendix 2 to the report); (c) delegates authority to the Chief Executive, in consultation with the Section 151 Officer and Monitoring Officer to call upon capital plan unhypothecated funding if required due to uncontrollable increases in costs as a result of inflation or supply chain issues. Any call on this funding will subsequently be reported to the next meeting of Cabinet, and (d) confirms that it was read, understood and taken account of the Wellbeing Impact Assessment as part of its consideration (Appendix 3 to the report).
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Lead Member / Officer Cllr Brian Jones: Lead Member for Waste, Transport and the Environment / Tony Ward: Head of Highways, Facilities & Environmental Services
Report author(s) Tony Ward, Head of Highways, Facilities & Environmental Services / Peter Clayton, Project Manager
Title Waste Service Remodelling – Update on financial position including updated business case
1. What is the report about? 1.1. This report updates Cabinet on the latest cost and budget position on the Waste Service Remodelling project and seeks approval of an updated Business Case.
2. What is the reason for making this report? 2.1. To update Cabinet on the latest cost and budget position on the Waste Service Remodelling project, and to seek approval of an updated Business Case.
3. What are the Recommendations? 3.1. That Cabinet acknowledge the latest cost and budget position (Appendix 1).
3.2The Cabinet approves the updated Business Case (Appendix 2).
3.3That Cabinet delegates authority to the Chief Executive, in consultation with the Section 151 Officer and Monitoring Officer to call upon capital plan unhypothecated funding if required due to uncontrollable increases in costs as a result of inflation or supply chain issues. Any call on this funding will subsequently be reported to the next meeting of Cabinet.
3.4That Cabinet confirms that it has read, understood and taken account of the Well- being Impact Assessment as part of its consideration (Appendix 3). 4. Report details 4.1. The Business Case for moving to a new Waste Service Model based on the Welsh Government (WG) collections blueprint and supported from a new central Depot was approved by Cabinet in December 2018. Since then, work has been underway to take forward the development of the new central depot required to support the service change, along with other key activities, including: routing the new collection rounds; specifying the new Resource Recovery Vehicles (RRV’s) required to support the proposed rounds; and finalising the service design and containers required.
4.2Since December 2018, a site was selected in Denbigh for the new central Depot on land allocated in the LDP adjacent to the current Colomendy Industrial Estate. The Council has been working in collaboration with 4 local businesses who were also looking to acquire land on this site to enable them to expand their operations. The Council has worked together with the businesses to secure the purchase of the land (as the landowner wanted to sell the whole site in one transaction rather than in plots); go through the Planning process; and to deliver the Phase 1 enabling works given the need to drain, service, access and amend levels across the site. As a result, the development of the new central depot to support the service change has taken longer than initially anticipated, with progress also in part affected by the impact of Covid-19. Although the decision to work with the 4 local businesses has resulted in the project taking longer than expected to deliver, it was absolutely the correct thing to do. These businesses had outgrown their premises and were unable to expand. By working with them, we have enabled these businesses to remain in the county, which has protected many existing local jobs as well as created new jobs for local people.
4.3To deal with the risks and unknowns on the project, the contingency sum within the overall budget was increased to £2M in July 2019. At the time it was reasonably felt this was sufficient to cover cost increases across the key work streams.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.