RESOLVED that Cabinet – (a) approve the award of a contract to the preferred contractor via delegated decision by the Chief Executive (in consultation with the Section 151 Officer and Monitoring Officer) at the conclusion of the tender process, providing the Contractors submission is within the affordability envelope for the works. It is expected that the delegated decision will be taken on, or after, 5 May 2022; (b) confirms that it has read, understood and taken account of the Wellbeing Impact Assessment (Appendix 1 to the report) as part of its consideration, and (c) that the delegated decision is implemented immediately due to the time pressure to progress the programme and award a Contract to allow works to commence on Phase 2 on site as soon as possible to maximise the more favourable conditions for construction over the summer and mitigate the risks posed by ongoing market volatility and cost pressures.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Lead Member / Officer Cllr Brian Jones: Lead Member for Waste, Transport and the Environment / Tony Ward: Head of Highways, Facilities & Environmental Services
Report author(s) Peter Clayton, Project Manager and Tony Ward, Head of Highways, Facilities & Environmental Services
Title Phase 2 Waste Transfer Station, Colomendy Contract Award via Delegated Decision
1. What is the report about? 1.1. This report summarises the process undertaken to date in relation to the tender to deliver Phase 2 of the development of the new DCC Waste Transfer Station (WTS) required to support the proposed change to the Waste Collection model.
1.2It also recommends that Cabinet agree to award a contract to the successful tenderer to deliver the Phase 2 of the development of the new DCC WTS via a Delegated Decision on conclusion of the tender process in the absence of Cabinet in May and at least the first part of June 2022. This is necessary in order to keep the project progressing and to avoid delay (and further costs) providing that the preferred contractors’ submission is within the affordability envelope for the works.
2. What is the reason for making this report? 2.1. A Cabinet decision is required to enable the council to award a contract to the successful tenderer to deliver Phase 2 of the development of the new DCC Waste Transfer Station via a Delegated Decision on conclusion of the tender process. This is because there will be no Cabinet in May (when a decision from Cabinet would otherwise be sought) or for at least the first part of June 2022. A delay in awarding the contract would result in a further delay to the project and would almost certainly also result in additional costs to the council. 3. What are the Recommendations? 3.1. That Cabinet approve the award of a Contract to the preferred contractor via Delegated Decision by the Chief Executive (in consultation with the Section 151 Officer and Monitoring Officer) at the conclusion of the tender process, providing the Contractors submission is within the affordability envelope for the works. It is expected that the Delegated Decision will be taken on, or after, 5th May 2022.
3.2That Cabinet confirms that it has read, understood and taken account of the Well- being Impact Assessment (Appendix 1) as part of its consideration.
3.3That the Delegated Decision is implemented immediately due to the time pressure to progress the programme and award a Contract to allow works to commence on Phase 2 on site as soon as possible to maximise the more favourable conditions for construction over the summer and mitigate the risks posed by ongoing market volatility and cost pressures.
4. Report details 4.1. Denbighshire County Council wish to appoint a Contractor to deliver Phase 2 of the development of a new Waste Transfer Station at Colomendy, Denbigh. These works follow on from the Phase 1 Enabling Works that have been delivered in collaboration with 4 businesses on the Colomendy Industrial Estate and were completed in March 2022.
4.2A Report seeking approval from Cabinet to issue an Invitation To Tender (ITT) for Phase 2 was brought to Cabinet on 19th October 2021 and was approved. Since this point, work has been underway to develop the Phase 2 tender package whilst in parallel delivering the live Phase 1 tender on site in collaboration with the 4 businesses.
4.3A contract notice for Phase 2 was published on the Sell2Wales procurement portal on 23rd March 2022 with a deadline for submission of 4th May 2022.
4.4The tender is based on a weighting of 60% Price and 40% Quality, with a pre-tender estimated (PTE) value of £5.25M.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.