RESOLVED that Cabinet – (a) confirms that it has read, understood and taken account of the Wellbeing Impact Assessment (Appendix 2 to the report) as part of its consideration; (b) supports the preferred way forward to complete the Phase 2 works at the new Waste Transfer Station on the Colomendy Industrial Estate, Denbigh, and (c) acknowledge the latest budget pressure and agree to continue working at risk while discussions on potential sources of funding for the pressure were concluded with the Welsh Government. This was necessary to mitigate the risk of further delays that would further impact on cost and programme , including affecting wider programme of service change for which completion of the Waste Transfer Station was critical.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Lead Member / Officer Cllr Barry Mellor, Lead Member for Environment & Transport / Tony Ward, Corporate Director: Environment & Economy
Head of Service Andy Clark, Interim Head of Highways & Environment
Report author Peter Clayton, Corporate Project Manager
Title Phase 2 Works Contract new DCC Waste Transfer Station (WTS), Colomendy Industrial Estate Expansion - Update
1. What is the report about? 1.1. This report provides an update on the latest position with respect to Phase 2 works to complete the new Waste Transfer Station (WTS) on the Colomendy Industrial Estate, Denbigh. It also seeks a decision to support the proposed way forward to complete the project following the main contractor entering administration, and it provides an update on a budget pressure as result of that situation.
2. What is the reason for making this report? 2.1. To seek support for the preferred way forward to complete Phase 2 works at the new WTS in Denbigh, following the main contractor entering administration, and to update on a budget pressure resulting from that situation.
3. What are the Recommendations? 3.1. That Cabinet confirm that it has read, understood and taken account of the Well- being Impact Assessment (Appendix 2) as part of its consideration.
3.2That Cabinet support the preferred way forward to complete the Phase 2 works at the new WTS on the Colomendy Industrial Estate, Denbigh.
Mae'r ddogfen hon ar gael yn Gymraeg. This document is available in Welsh. 3.3. That Cabinet acknowledge the latest budget pressure and agree to continue working at risk while discussions on potential sources of funding for the pressure are concluded with Welsh Government (WG). This is necessary to mitigate the risk of further delays that would further impact on cost and programme, including affecting wider programme of service change for which completion of the WTS is critical.
4. Report details 4.1. An NEC4 ECC Design & Build Contract was awarded to RL Davies & Son Ltd (RLD) in June 2022 to deliver Phase 2 of the works to complete the WTS at Colomendy, Denbigh. This new WTS is required to support the change in the waste collection model proposed to occur from March 2024 whereby the Council will move to the preferred Welsh Government collections blueprint.
4.2RLD commenced works on site on Phase 2 in August 2022 but unfortunately on February 16th 2023 they were placed into Administration. At the time of Administration the anticipated Final Account cost of Phase 2 was estimated at £6.9M against a budget including Contingency of £7.022M. A Report on the original appointment of RLD and subsequent termination of the contract following their administration was taken to Cabinet on 25th March 2023.
4.3Since February 16th, in order to keep works progressing on the site and to mitigate delays, it was agreed an Exception Report be prepared to allow the Council to raise orders and make payments direct to key subcontractors who were working for RLD whilst a decision was made on the longer term way forward. This has allowed work to continue to progress on site to mitigate impact on programme.
4.4As part of the short term Exception standard NEC4 ECC Short Subcontracts have been set up with subcontractors pending the decision on the longer term way forward.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.