RESOLVED that Cabinet – (a) approve the initiation of the project to procure the North Wales Construction Framework Phase 3, and (b) confirms that it has read, understood and taken account of the Wellbeing Impact Assessment (Appendix 1 to the report) as part of its consideration.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Title North Wales Construction Framework (NWCF) Phase 3 – Stage 1- Initiate Project approval
1. What is the report about?
1.1The purpose of this report is to seek approval to begin the process for the procurement of the NWCF Phase 3 to be in place for June 2024. NWCF Phase 2 is due to end May 2024. In order to ensure that all projects in the current programme of works are procured and monitored appropriately. This will allow for a smooth transition by continuing the engagement with stake holders and to secure the commitment of the North Wales Local Authorities (NWLA).
2. What is the reason for making this report?
2.1Following the success of the NWCF and the benefits in procurement time, cost and value added provided by it, it is proposed to initiate a project that allow the NWLA to continue to have a Framework in place for the procurement of regional construction projects. 2.2. It is proposed to update the Framework and to extend its scope to cover all relevant construction projects over £250K threshold, and to incorporate the lessons learned from the current iteration. 2.3. The NWCF phase 1 and 2 have been a catalyst for engagement and upskilling of local contractors operating within the regional supply chain, this will encourage local contractors to be become part of NWCF3. 2.4. Alongside the regional framework, the project will continue to drive improvement in construction procurement practices across the region, to ensure consistency, driving the delivery of community benefits, develop continuous improvement and set new benchmarks for best practice. 2.5. It is proposed that the framework will be set up by the six NWLA and accessible to other public sector agencies (e.g. Higher Education, Police Authority and Fire and Rescue Services, etc.) by June 2024 and be in place for a total of four years (2+1+1 years). 2.6. A condition of the Sustainable Communities for Learning Programme grant funding is that one of the three Welsh Frameworks is used to procure the project. 3. What are the Recommendations?
3.1It is recommended to approve the initiation of the project to procure NWCF3.
3.2That the Committee confirms that it has read, understood and taken account of the Well-being Impact Assessment (Appendix 1) as part of its consideration
4. Report details
4.1The operational board of NWCF, formed by the six NWLA’s, is seeking to continue to have a collaborative construction Framework in place as it is now evident that procuring projects via this route is effective. 4.2. It also consistently aids the delivery of added value in the form of; Targeted Recruitment and Training, supply chain engagement and upskilling, reduced time and cost of the procurement process, Standardised approach and processes that in turn helps reduce risks, continue to have a collaborative relationship with the contractor partners in the Framework minimising confrontation, and engagement with supporting agencies to enable the delivery of KPI targets.
Project Governance
4.3The project has been set up with sound governance and reporting structures. Cabinet approval will be sought to procure NWCF3 and before appointment of successful contractors. Value and scope of Programme
4.4The main driver for the project is to deliver value for money in public procurement and deliver community benefits across the region. This is best achieved through an aggregation of construction projects associated with the Sustainable Communities for Learning Programme and other public sector projects.
Lotting Strategy (the way in which the framework will be divided into value bands)
4.5Proposed lotting structure for framework–
Lot Value Maximum Contractors
Lot 1 £250K – £2m Up to 10
Lot 2 £2m - £5m Up to 6
Lot 3 £5m - £10m Up to 6
Lot 4 £10m - £15m Up to 6
Lot 5 £15m+ Up to 6
Procurement Strategy - Overview
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.