APPROVAL FROM CABINET TO SUBMIT THE STRATEGIC OUTLINE CASE (SOC) TO THE WELSH GOVERNMENT'S SUSTAINABLE COMMUNITIES FOR LEARNING INVESTMENT PANEL IN JANUARY 2026
ApprovedExecutive3 papers
AI summaryDenbighshire Cabinet approved submitting the Strategic Outline Case for the £13.2m extension and refurbishment of Ysgol Pendref to the Welsh Government in January 2026, committing £4,110,417 in match funding through prudential borrowing.
What happens nextSubmit to Welsh Government in January 2026To move project to next stage and develop detailed design
Who it affectsNot stated
What was decided
Cabinet approved the council's £4,110,417 capital match funding commitment to the Ysgol Pendref project, funded by prudential borrowing, with related revenue costs to be built into future Medium Term Financial Plans. Report 3.1, 6.4
Cabinet approved submission of the Strategic Outline Case to the Welsh Government's Sustainable Communities for Learning investment panel in January 2026. Report P7, P8
Cabinet confirmed it had read, understood and taken account of the Well-being Impact Assessment.
Why
The school has operated from two separate buildings on one site since 2012, and the project will consolidate all teaching and learning into a single building. Report 4.2
The project supports the Community Focused Schools agenda, contributes to the council becoming net carbon zero by 2030, and brings construction employment to Upper Denbigh. Report 5.1, 5.5
Section 14 of the Education Act places a duty on local authorities to secure sufficient primary schools. Report P35
What happens next
Submit the Strategic Outline Case to the Welsh Government investment panel in January 2026. Report P7, P8, 4.4
Appoint a main contractor in spring 2026 via the North Wales Construction Partnership. Report 4.4
Construction could commence by summer 2028 with project completion estimated at summer 2030, subject to approvals. Report 4.4, 6.5
The money
£13,212,056 Total project pre-tender estimate Report P23
£7,633,632 Welsh Government 65% contribution Report P19, 6.2
£4,110,417 Denbighshire County Council 35% match funding via prudential borrowing Report P20, 6.2, 6.4
£11,744,050 Subtotal excluding net zero carbon element Report P21, 6.2
£1,468,006 Net Zero Carbon element, 100% Welsh Government funded Report P22, 6.2
£1,874,040 Expression of interest to Welsh Government Childcare and Early Years Programme Report 6.3
£284k per annum Indicative revenue pressure from prudential borrowing identified in Strategic Outline Programme Report 6.4
Implications
Financial: Council match funding will be met through prudential borrowing, creating an indicative £284k per annum revenue pressure and longer-term interest and debt repayment costs to be built into future Medium Term Financial Plans. Report 6.4, P33
Climate: Project will incorporate an air source heat pump, PV panels and low U-value components, with biodiversity and habitat creation to offset construction carbon. Report 7.2
Risk: Key risks are affordability and cost increases, planning and SuDS Approving Body conditions, delay in delivery and changes to scope, with delays likely to raise costs further. Report 10.2
Financial: Any cost variation will be reflected in the revised Strategic Outline Programme in 2027, with main council spend falling between 2027 and 2030. Report 6.5
Other: Project cuts across Education, Planning and Public Protection, Corporate Support, Finance and Audit, and Highways and Environmental Services.
SOC: Strategic Outline Case, the first step in seeking Welsh Government approval
SOP: Strategic Outline Programme covering the council's wider school investment plans
DCC: Denbighshire County Council
NZC: Net Zero Carbon, the separately funded element of the project
MTFP: Medium Term Financial Plan
SAB: SuDS Approving Body, dealing with sustainable drainage approvals
NNDR: National Non-Domestic Rates, the business rates paid on school premises
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
RESOLVED that Cabinet approves – (a) the capital match funding commitment of Denbighshire County Council to the Ysgol Pendref Project as set out within paragraph 6.2 of the report funded by prudential borrowing, and the revenue costs associated with the borrowing and the project which will need to be refined over time and built into future iterations of the Council’s Medium Term Financial Plan once the capital works are completed; (b) the submission of the Strategic Outline Case for consideration by the Welsh Government’s Sustainable Communities for Learning investment panel in January 2026, and (c) confirms that it has read, understood and taken account of the Well-being Impact Assessment (Appendix 1 to the report) as part of its consideration.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Lead Member / Officer Cllr Diane King, Lead Member for Education, Children and Families
Head of Service Geraint Davies. Head of Education Services
Report author Alice Thelwell, Modernising Education Officer
Title Approval from Cabinet to submit the Strategic Outline Case (SOC) to the Welsh Government’s Sustainable Communities for Learning investment panel in January 2026
1. What is the report about? 1.1. The report seeks approval from Cabinet to submit the Strategic Outline Case (SOC) to be considered by Welsh Government’s Sustainable Communities for Learning investment panel in January 2026
2. What is the reason for making this report? 2.1. By submitting the SOC to Welsh Government’s Sustainable Communities for Learning investment panel in January 2026 we will be able to move to the next stage of the Ysgol Pendref project and develop the detailed design.
3. What are the Recommendations?
3.1To approve the capital match funding commitment of Denbighshire to the Ysgol Pendref Project as set out within paragraph 6.2 funded by prudential borrowing, and the revenue costs associated with the borrowing and the project which will need to refined over time and built into future iterations of the Council’s Medium Term Financial Plan once the capital works are completed. 3.2. That the Committee approves the submission of the Strategic Outline Case to the Welsh Government’s Sustainable Communities for Learning investment panel in January 2026. 3.3. That the Committee confirms that it has read, understood and taken account of the Well-being Impact Assessment (Appendix 1) as part of its consideration.
4. Report details 4.1. Denbighshire County Council propose to extend and refurbish Ysgol Pendref as part of the Welsh Government’s Sustainable Communities for Learning Programme. Approval was granted in 2024 by Cabinet and the Welsh Government for Denbighshire’s Strategic Outline Programme which includes this project.
4.2Ysgol Pendref was established in 2012 following the amalgamation of the neighbouring schools of Ysgol Gwaenynog and Ysgol Heulfre. The new school Ysgol Pendref has operated since 2012 from two separate buildings on one site. This has created issues and challenges for the school. This project seeks to consolidate all teaching and learning into a single building. The proposal will also seek provision for dedicated childcare provision, subject to approval for a separate Child Care Capital Grant scheme to Welsh Government, and the development of community facilities to support the Upper Denbigh area.
4.3In the summer of 2025, a Design and Construction Agent was appointed to support the development of the project and manage the procurement of a contractor to lead on the design and build for the extension and refurbishment of the current Ysgol Pendref site. Approval to progress the procurement was provided by Cabinet in September 2025.
4.4The submission of the Strategic Outline Case to Welsh Government represents the first step in the process of obtaining approval for the project. Subject to approvals for the Strategic Outline Case a main contractor will be appointed in the spring of 2026 via the North Wales Construction Partnership. The indicative timescales suggest that the construction stage of the project could commence by Summer 2028 with project completion estimated at Summer 2030. 5. How does the decision contribute to the Corporate Plan 2022 to 2027: The Denbighshire We Want?
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
APPROVAL FROM CABINET TO SUBMIT THE STRATEGIC OUTLINE CASE (SOC) TO THE WELSH GOVERNMENT'S SUSTAINABLE COMMUNITIES FOR LEARNING INVESTMENT PANEL IN JANUARY 2026Report
10APPROVAL FROM CABINET TO SUBMIT THE STRATEGIC OUTLINE CASE (SOC) TO THE WELSH GOVERNMENT'S SUSTAINABLE COMMUNITIES FOR LEARNING INVESTMENT PANEL IN JANUARY 2026This decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.