DENBIGH HIGH SCHOOL REFURBISHMENT - DRAFT STRATEGIC OUTLINE CASE AND APPROVAL TO PROGRESS DESIGN AND BUILD TENDER
ApprovedExecutive5 papers
AI summaryDenbighshire Cabinet approves £19.8million Denbigh High School refurbishment commitment, Strategic Outline Case submission, and design and build procurement start.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedMatch funding, case and procurement
Money£19.8million totalIncluding DCC and Welsh Government shares
What happens nextWelsh Government January 2026Strategic Outline Case to investment panel
Who it affectsDenbigh High School communityLearners, staff, and council services
What was decided
Cabinet approved the capital match funding commitment of £6,171,379 from Denbighshire County Council via prudential borrowing, with associated revenue costs to be built into future Medium Term Financial Plans once the capital works are completed. Report 3.1, 6.2
Cabinet approved submission of the Strategic Outline Case to the Welsh Government's Sustainable Communities for Learning investment panel in January 2026. Report 3.2, 1.2
Cabinet approved parallel commencement of procurement above £2million excluding VAT to appoint a design and build contractor via Lot 5 of the North Wales Construction Partnership. Report 3.3, 4.5, 4.6
Why
The refurbishment of Denbigh High School is part of the Band B school modernisation projects and a priority in the Sustainable Communities for Learning Programme, with a need to enhance teaching and learning environments. Report 4.1, P15
The revised Order of Cost Estimate is £24.1million against the £19.8million agreed envelope, a £4.3million pressure that includes fire suppression and temporary accommodation not in the 2018 estimate. Report 4.3, 6.2
Delay risks further cost increases from global market uncertainty on goods and services. Report P41
What happens next
Procurement process will run from January 2026 to March 2026, with contract award expected in April 2026 alongside Welsh Government approval of the Strategic Outline Case. Report 4.6
Following appointment of a lead contractor in late Spring 2026, costs will be reviewed and a revised budget submitted in the Outline Business Case in late 2026. Report 4.4
A revised Strategic Outline Programme for 2027 to 2030 will be submitted in 2027, with main construction work between 2028 and 2030. Report 4.4, 6.3
£24.1million Revised Order of Cost Estimate Report 4.3
£4.3million Cost pressure against the 2024 envelope Report 4.3
£11,461,132 Welsh Government proposed funding Report P28, 6.2
£6,171,379 Denbighshire County Council proposed funding Report P29, 6.2
£19,836,575 Total project funding including Net Zero Carbon Report P32, 6.2
£426k per annum Indicative revenue pressure from prudential borrowing Report 6.2
£15.2million Construction investment supporting economic and social value Report P23
Options considered
Chosen: Commence procurement in parallel with Strategic Outline Case submission. Reduces risk of further cost increases from market uncertainty and aligns contractor appointment with Welsh Government approval process Report 4.6, P41
Chosen: Fund Denbighshire's contribution via prudential borrowing. Creates a revenue pressure of about £426k per annum that will be refined in future iterations of the Medium Term Financial Plan Report 3.1, 6.2
Implications
Financial: Prudential borrowing creates a revenue pressure of about £426k per annum, with costs to be built into future Medium Term Financial Plans once the capital works are completed. Report 3.1, 6.2, P40
Financial: Further contributions from Denbighshire and the Welsh Government may be required once the realistic budget is reviewed after contractor appointment. Report 4.4, 6.2
Climate: The project aims to enhance energy efficiency and support the Council's Net Zero Carbon and Ecologically Positive target by 2030, with carbon reduction elements still to be detailed. Report 5.3
Risk: Key active risks are affordability and cost, planning conditions, SAB conditions, delay in delivery, and changes to scope. Report P41
Other: The Well-being Impact Assessment identified a period of disruption during construction, to be managed through a phasing plan and temporary accommodation provision. Report 7.2, P36
January 2026: Strategic Outline Case to be submitted to Welsh Government investment panel Report 3.2, 4.6
January 2026: Procurement process commences Report 4.6
April 2026: Award of design and build contract expected Report 4.6
late 2026: Outline Business Case with revised budget to be submitted Report 4.4
2027: Revised Strategic Outline Programme for 2027 to 2030 to be submitted Report 4.4, 6.3
2028 to 2030: Main construction work scheduled Report 6.3
Plain English for the jargon
Strategic Outline Case (SOC): An early stage business case document submitted to the Welsh Government to seek approval for a project.
Strategic Outline Programme (SOP): The longer term programme of school modernisation projects approved in 2019 and reaffirmed in April 2024.
Order of Cost Estimate (OCE): An estimate of construction costs prepared at concept design stage.
Employer's Agent (EA): A consultant appointed to act on behalf of the Council to manage the design and build contractor.
Sustainable Communities for Learning: The Welsh Government's programme for school and college capital investment.
Net Zero Carbon (NZC): A target of balancing carbon emissions produced with those removed from the atmosphere.
Band B: The current phase of the Welsh Government's school modernisation investment programme.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9
Resolved
RESOLVED that Cabinet approves – (a) the capital match funding commitment of Denbighshire County Council to the Denbigh High School Project as set out within paragraph 6.2 of the report funded by prudential borrowing, and the revenue costs associated with the borrowing and the project which will need to be refined over time and built into future iterations of the Council’s Medium Term Financial Plan once the capital works are completed; (b) the submission of the Strategic Outline Case (Appendix 1 to the report) for consideration by the Welsh Government’s Sustainable Communities for Learning investment panel in January 2026; (c) proceeding in parallel with the above the commencement of procurement (above £2m excluding VAT threshold) to appoint a contractor for design and build of the scheme, and (d) confirms that it has read, understood and taken account of the Well-being Impact Assessment (Appendix 1a to the report) as part of its consideration.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Title Denbigh High School Refurbishment – Draft Strategic Outline Case and Approval to Progress Design and Build Tender
1. What is the report about? 1.1. This report is to seek approval from Cabinet to commit financially to the Denbigh High Project and submit the Strategic Outline Case (SOC) to the Welsh Government’s Sustainable Communities for Learning investment panel in January 2026 for the proposed refurbishment of Denbigh High School.
1.2This report also seeks approval from Cabinet to commence the procurement process to appoint a contractor to lead on the detailed design and build for the refurbishment of the current Denbigh High School site and the associated financial commitment.
2. What is the reason for making this report? 2.1. The reason for this report is to seek approvals for the submission of the Strategic Outline Case and to proceed in parallel with the commencement of the procurement process for a design and build contract to develop the scheme.
3. What are the Recommendations?
3.1To approve the capital match funding commitment of Denbighshire to the Denbigh High Project as set out within paragraph 6.2 funded by prudential borrowing, and the revenue costs associated with the borrowing and the project which will need to refined over time and built into future iterations of the Council’s Medium Term Financial Plan once the capital works are completed.
3.2That the Committee approves the submission of the Strategic Outline Case (Appendix 1) for consideration by the Welsh Government’s Sustainable Communities for Learning investment panel in January 2026.
3.3To approve proceeding in parallel with the above the commencement of procurement (above £2million exc VAT threshold) to appoint a contractor for design and build of the scheme.
3.4That the Committee confirms that is has read, understood and taken account of the Well-being Impact Assessment (Appendix 1a) as part of its consideration.
4. Report details Strategic Outline Case
4.1The proposal to refurbish the current Denbigh High School site was part of the ‘Band B’ suite of school modernisation projects. This remains a priority within the authority’s Sustainable Communities for Learning Programme. As part of the Strategic Outline Programme, approved initially in 2019 and reaffirmed by Cabinet in April 2024, there is a need to enhance the teaching and learning environments of the school.
4.2In September 2025 an employer’s agent (EA) was appointed to undertake further feasibility works to ascertain a concept design and inform an outline scope of works for addressing the major site issues. The EA has developed a proposed scheme of works that has been developed in consultation with the school’s Senior Leadership Team who support the current scope of works identified.
4.3The EA has consequently issued an updated order of cost estimate (OCE) for the scheme. The agreed funding envelope as part of the 2024 Strategic Outline Programme (SOP) is £19.8million. (see Section 6) The revised OCE is £24.1million. This pressure of £4.3million includes a contingency for a fire suppression system and also for some temporary accommodation for the construction period. These elements were not included in the initial estimate for the scheme in 2018.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.