RESOLVED (unanimously) 1. That activity and progress to date be received and agreed. 2. That the proposed governance structure and Terms of Reference for the Programme Board are received and approved. 3. That Councillors Peter Dobbs, Steve Flitter, David Hughes and Stuart Lees be appointed to the Ashbourne Reborn Programme Board to represent the District Council. 4. That Councillor David Hughes be nominated as Chair of the Ashbourne Reborn Programme Board. 5. That relevant partners be invited to nominate representatives to enable representation on the Board to be finalised. 6. That delivery partner Project Boards’ Terms of Reference are in accordance with paragraphs 2.5 to 2.8 of this report and that they be submitted to the proposed Programme Board for approval. 7. That the highlighted risks and associated mitigation measures be received and noted. The Chair declared the motion CARRIED .
Word for word from the decision Derbyshire Dales published for this meeting.Source: democracy.derbyshiredales.gov.uk
1. That activity and progress to date be received and agreed.
2. That the proposed governance structure and Terms of Reference for the Programme Board are received and approved.
3. That Council nominates Members to represent Derbyshire Dales District Council on the Programme Board, including the proposed Chair of the Board, and proposes that equivalent processes are undertaken by relevant partners to enable representation on the Board to be finalised.
4. That delivery partner Project Boards’ Terms of Reference are in accordance with paragraphs 2.5 to 2.8 of this report and that they are submitted to the proposed Programme Board for approval.
5. That the highlighted risks and associated mitigation measures are received and noted. List of Appendices Appendix 1 Activity to date Appendix 2 Proposed Governance Structure Appendix 3 Ashbourne Reborn Programme Board Draft Terms of Reference Appendix 4 Strategic Risk Register (top ten risks)
Background Papers Community and Environment Committee reports: • 1 November 2022 • 29 June 2022 • 6 April 2022 • 23 February 2022
Consideration of report by Council or other committee No
Council Approval Required Yes
Exempt from Press or Public No ASHBOURNE REBORN GOVERNANCE AND DELIVERY
Background
1.1Ashbourne Reborn is a £15.22m programme aimed at transforming Ashbourne town centre through significant improvements to highways and public realm and the development of the Link Community Hub. The programme is principally funded by the UK Government through the Levelling Up Fund. The initial Levelling Up Fund capital grant award in January 2023 was £13,373,509. A further grant of £70,000 was awarded in July 2023 to provide revenue capacity support.
1.2As a reminder, the programme comprises the following projects:
Project 1: Public Realm & Highways Improvements - £8.804m This project will deliver a series of transformed public spaces including the Market Place, Victoria Square, Millennium Square and Shrovetide Walk. Connections between these spaces will also be improved. Highways improvements will be undertaken along Compton, Dig Street and St John Street to create a better pedestrian experience, reducing the impact of vehicles and improving safety. This project is led by Derbyshire County Council.
Project 2: Link Community Hub - £6.418m The project aims to transform the Methodist Church into a multi-purpose community space, enhancing the town centre offer, and providing a venue that will help drive greater footfall. This project is led by Ashbourne Methodist Church.
1.3Derbyshire Dales District Council is the Accountable Body for Ashbourne Reborn. This means that, although projects are being delivered by other delivery partners the Council has full and sole responsibility for, inter alia:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Approval of Minutes of Previous MeetingRESOLVED (unanimously) That the minutes of a meeting of Council held on 28 May 2026 and 18 June 2026 be approved as a...
Provisional Revenue Outturn 2025/26RESOLVED (unanimously) That in accordance with Procedure Rule 13 the meeting continue until 9.00pm. The substantive m...
Questions (rule of procedure 15)Decision making on planning applications is informed by the Local Plan, but each application for planning permission ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.