RESOLVED (unanimously) 1. That the provisional Capital Out-turn of £4,233,274, as detailed in Appendix A, be approved. 2. That the explanations regarding significant variances in planned and actual capital expenditure for 2022/23 be noted. 3. That an underspend of £1,814,037 be carried forward at 31 March 2023 and other revisions totalling £96,000 set out in paragraphs 3.1 and 3.2 and Appendix A be approved for inclusion into the capital programme. 4. That new projects totalling £4,652,400 set out in paragraphs 3.5 to 3.18 of the report be approved for inclusion in the programme. 5. That the updated capital programme for 2023/24 to 2027/28 set out in Appendix B to the report totalling £38,450,376 be approved. 6. That financing of the Capital Programme from sources summarised at paragraph 3.21 and shown in Appendix C be approved. 7. That the balance of funds available over the 5-year programme, shown at Appendix C, be noted. The Chair declared the motion CARRIED .
Word for word from the decision Derbyshire Dales published for this meeting.Source: democracy.derbyshiredales.gov.uk
1. That the provisional Capital Out-turn of £4,233,274, as detailed in Appendix A, is approved.
2. That the explanations regarding significant variances in planned and actual capital expenditure for 2022/23 are noted.
3. That an underspend of £1,814,037 be carried forward at 31 March 2023 and other revisions totalling £96,000 set out in paragraphs 3.1 and 3.2 and Appendix A be approved for inclusion into the capital programme.
4. That new projects totalling £4,652,400 set out in paragraphs 3.5 to 3.18 of the report are approved for inclusion in the programme.
5. That the updated capital programme for 2023/24 to 2027/28 set out in Appendix B to the report totalling £38,450,376 be approved.
6. That financing of the Capital Programme from sources summarised at paragraph 3.21 and shown in Appendix C be approved. 7. That the balance of funds available over the 5-year programme, shown at Appendix C, is noted.
List of Appendices Appendix A Capital Out-turn 2022/23 Appendix B Revised Capital Programme 2023/24 – 2027/28 Appendix C Proposed financing of the Capital Programme 2022/23 to 2027/28 Appendix D Details of bids for Inclusion into the Capital Programme 2023/24 to 2027/28
Background Papers None
Consideration of report by Council or other committee Not applicable
Council Approval Required Yes
Exempt from Press or Public No Provisional Capital Out-turn 2022/23 and Revised Capital Programme 2023/24 to 2027/28
Background
1.1At Council on 2nd March 2023 Members approved a revised capital programme totalling £35,858,944, covering the financial years 2022/23 to 2026/27, as summarised in table 1 below:
Table 1: Capital Programme approved 2nd March 2023
Financial year £ 2022/23 6,160,505 2023/24 14,843,110 2024/25 13,027,857 2025/26 799,736 2026/27 1,027,736 Total 35,858,944
1.2This report provides information relating to the provisional outturn (subject to audit) for 2022/23 and seeks approval for a revised capital programme for 2023/24 to 2027/28, taking account of slippage from 2022/23 and including bids for 13 new projects and other changes. 2. Provisional Out-turn for 2023/23
2.1At Council on 2nd March a revised capital budget of £6,160,505 was approved for 2022/23.
2.2The actual total capital expenditure for 2022/23 was £4,233,274. Therefore, there was an overall underspend of £1,927,231. The Programme has been financed as shown in table 2 below:-
Table 2: Capital financing arrangements for 2022/23
Sources of Financing £ Capital Receipts 420,511 Capital Programme Reserve £354,467 S106 Contributions 1,014,563 Grants 1,940,965 Economic Development Reserve 10,000 IT Reserve 18,700 Vehicle Reserve 474,077 Total 4,233,274
2.3The expenditure incurred against each project is outlined at Appendix A, which provides explanations for under- and over-spends and whether each project has concluded. Where projects are continuing beyond the end of 2022/23, budget underspends have been carried forward and added to the budget for 2023/24. It is proposed to carry forward £1,814,037 of the provisional underspend from 2022/23 into 2023/24. 2.4 Material project under- and over-spends in 2022/23 are explained below.
• Project 270 – Disabled Facilities Grants (funded by the Better Care Fund): overspent by £24,739
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Approval of Minutes of Previous MeetingRESOLVED (unanimously) That the minutes of a meeting of Council held on 28 May 2026 and 18 June 2026 be approved as a...
Provisional Revenue Outturn 2025/26RESOLVED (unanimously) That in accordance with Procedure Rule 13 the meeting continue until 9.00pm. The substantive m...
Questions (rule of procedure 15)Decision making on planning applications is informed by the Local Plan, but each application for planning permission ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.