Capital Programme Update

Noted Committee 1 paper

Council noted this item on Thursday 29 February 2024. Below is the council's own wording, with the papers it was decided on.

Item339/23

Resolved

RESOLVED (unanimously) 1. That the Capital Programme expenditure to 31 st January 2024 is noted. 2. That re-phasing of existing projects for completion over the next 5 years is approved. 3. That two new projects totalling £165,959, set out in paragraphs 2.13 to 2.21 of the report, are approved for inclusion in the programme. 4. That the revised capital programme for 2023/24 to 2028/29, as shown in Appendix A, totalling £39,629,590 is approved. 5. That financing of the Capital Programme from sources summarised at paragraph 2.24 and shown in Appendix C is approved. 6. That the balance of funds available over the 5-year programme, shown at Appendix C, is noted. 7. That project 652 Matlock Bath Lovers Walk Shelter Rebuild is amended to be Matlock Bath Lovers Walk and Derwent Gardens general improvements project. The Chair declared the motion CARRIED .
Word for word from the decision Derbyshire Dales published for this meeting. Source: democracy.derbyshiredales.gov.uk

Follow this further

Built from Derbyshire Dales's papers

What the report saysPro

Report to Council

Recommendations

1. That the Capital Programme expenditure to 31st January 2024 is noted.

2. That re-phasing of existing projects for completion over the next 5 years is approved.

3. That two new projects totalling £165,959, set out in paragraphs 2.13 to 2.21 of the report, are approved for inclusion in the programme.

4. That the revised capital programme for 2023/24 to 2028/29, as shown in Appendix A, totalling £39,629,590 is approved.

5. That financing of the Capital Programme from sources summarised at paragraph 2.24 and shown in Appendix C is approved.

6. That the balance of funds available over the 5-year programme, shown at Appendix C, is noted. List of Appendices

Appendix A Revised Capital Programme 2023/24 to 2028/29 Appendix B Comments on Schemes and Financing Appendix C Proposed financing of the Capital Programme 2023/24 to 2027/28

Background Papers None

Consideration of report by Council or other committee Not applicable

Council Approval Required Yes

Exempt from Press or Public No Capital Programme Update

Background

1.1At the Council meeting on 14th December 2023 Members approved a revised capital programme totalling £37,770,410 covering the financial years 2023/24 to 2027/28, as summarised in table 1 below:

Table 1: Capital Programme approved 14th December 2023

Financial year £ 2023/24 12,855,250 2024/25 20,688,422 2025/26 3,099,002 2026/27 1,077,736 2027/28 50,000 Total 37,770,410

2. Capital Expenditure for 2023/24

2.1At Council on 14th December a revised capital budget of £37,770,410 was approved for 2023/24. As at 31st January 2023/24 expenditure against the budget was £7,495,047 as shown in Appendix A.

2.2The forecast out turn for the 2023/24 capital programme determines that the amount in 2023/24 should be revised downwards to £10,755,164, to reflect forecasted expenditure which is a difference of £2,100,086 from the budget approved in December 2023 as shown in Appendix A.

2.3A summary of the changes to the programme are summarised in the table 2 below and explained in paragraphs 2.14 to 2.20.

Table 2: Changes to the 2023-24 Programme

Approved Capital Programme – December 2023 12,855,250 Project 360 – Vehicle Slippage reincorporated – as 166,133 Approved by Council in January 2024 Additional Capacity Funding Ashbourne Reborn 35,000 Expected Overspends 39,247 Slippage / reprofiling into 2024-25 (2,335,231) Funds no longer required (25,408) Forecast Underspends not required (4,827) New Bids – Profiled into 2023-24 25,000 Total Proposed Programme 2023-24 10,755,164

Table 3: Revised Capital financing arrangements for 2023/24

Sources of Financing £ Capital Receipts 574,450 Capital Programme Reserve 632,739 S106 Contributions 3,833,228 Grants 4,795,381 Economic Development Reserve 9,896 IT Reserve 155,737 Vehicle Reserve 495,133 Revenue Grants Unapplied 258,600 Total 10,755,164

2.4The expenditure and forecast out turn forecasted for each project is outlined at Appendix A, which provides explanations for under and over-spends and whether each project has concluded. Where projects are continuing beyond the end of 2023/24, budget underspends have been carried forward and added to the budget for 2024/25.

2.5As noted in table 2 above, Slippage/Reprofiling against schemes that are to be moved into 2024/25 total £2,335,231 these are explained below:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme UpdateReport 348 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

29 of 42 attended
SW
Steve Wain LIBDEMChair, present
DG
Dawn Greatorex LABVice-Chair, present
RA
Robert Archer LIBDEMCommittee Member, present
MB
Matt Buckler GREENCommittee Member, apologies
SB
Sue Bull CONCommittee Member, present
MB
Martin Burfoot LIBDEMCommittee Member, present
SB
Sue Burfoot LIBDEMCommittee Member, present
BB
Bob Butcher LABCommittee Member, present
NB
Neil Buttle GREENCommittee Member, present
DC
David Chapman CONCommittee Member, present
SH
Susan Hobson CONCommittee Member, present
DH
David Hughes LIBDEMCommittee Member, present

All 42 on the meeting page

On this subject at Derbyshire Dales

Search all
  1. Capital Programme UpdateThis decision
  2. Provisional Capital Out-Turn 2025/26 and Revised Capital Programme 2026/27 to 2030/31Approved
  3. Capital programme updateNoted
  4. Capital Programme UpdateNoted
  5. Capital Programme updateNoted
  6. Provisional Capital Outturn 2024/25 and Revised Capital Programme 2025/26 to 2029/30Approved

More from Derbyshire Dales Council

All decisions
MeetingDecisionOutcome
23 Jul 2026 CommitteesRESOLVED (unanimously) That the non-exempt minutes of the listed in the Minute Book for the period 14 May 2026 to 02 ... Decided Open
23 Jul 2026 Approval of Minutes of Previous MeetingRESOLVED (unanimously) That the minutes of a meeting of Council held on 28 May 2026 and 18 June 2026 be approved as a... Approved Open
23 Jul 2026 Provisional Capital Out-Turn 2025/26 and Revised Capital Programme 2026/27 to 2030/31RESOLVED (unanimously) 1. That the provisional Capital Out-Turn of £15,075,300 as detailed in Appendix 1 be approved.... Approved Open
23 Jul 2026 Provisional Revenue Outturn 2025/26RESOLVED (unanimously) That in accordance with Procedure Rule 13 the meeting continue until 9.00pm. The substantive m... Noted Open
22 Jul 2026 Questions (rule of procedure 15)Decision making on planning applications is informed by the Local Plan, but each application for planning permission ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies