Provisional Capital Outturn 2024/25 and Revised Capital Programme 2025/26 to 2029/30

Approved Committee 4 papers

Council approved this item on Thursday 24 July 2025. Below is the council's own wording, with the papers it was decided on.

Item90/25

Resolved

RESOLVED (unanimously) 1. That the provisional Capital Out-turn of £9,687,256 as detailed in Appendix A, is approved. 2. That the explanations regarding significant variances in planned and actual capital expenditure for 2024/25 are noted. 3. That an overall increase of £857,787 is applied to the capital programme for 2025/26 – 2029/30 consisting of a carried forward spend of £314,977 at 31 March 2025 and other revisions totalling £542,810 set out in paragraphs 3.1 to 3.7 and Appendix A be approved for inclusion into the capital programme. 4. That the funding for Matlock Bath Lovers Walk is retained in the capital programme in 2025/26 5. That the updated capital programme for 2025/26 to 2029/30 set out in Appendix B to the report totalling £28,180,995 be approved. 6. That financing of the Capital Programme from sources summarised at paragraph 3.11 and shown in Appendix C be approved. 7. That the balance of funds available over the 5-year programme, shown at Appendix C, is noted. The Chair declared the motion CARRIED. 21.58 Councillor Nick Whitehead and Councillor Nick Wilton left the meeting 22.00 Councillor David Chapman, Councillor Susan Hobson and Councillor Peter Slack left the meeting
Word for word from the decision Derbyshire Dales published for this meeting. Source: democracy.derbyshiredales.gov.uk

Follow this further

Built from Derbyshire Dales's papers

What the report saysPro

Report to Council

Recommendations

1. That the provisional Capital Out-turn of £9,687,256 as detailed in Appendix A, is approved.

2. That the explanations regarding significant variances in planned and actual capital expenditure for 2024/25 are noted.

3. That an overall increase of £857,787 is applied to the capital programme for 2025/26 – 2029/30 consisting of a carried forward spend of £314,977 at 31 March 2025 and other revisions totalling £542,810 set out in paragraphs 3.1 to 3.7 and Appendix A be approved for inclusion into the capital programme.

4. That the scheme at Matlock Bath Lovers Walk is retained in the capital programme in 2025/26 to rebuild the shelter for the reasons given in paragraphs 3.8 and 3.9 of this report.

5. That the updated capital programme for 2025/26 to 2029/30 set out in Appendix B to the report totalling £28,180,995 be approved.

6. That financing of the Capital Programme from sources summarised at paragraph 3.11 and shown in Appendix C be approved.

7. That the balance of funds available over the 5-year programme, shown at Appendix C, is noted. List of Appendices Appendix A Capital Out-turn 2024/25 Appendix B Revised Capital Programme 2025/26 – 2029/30 Appendix C Proposed financing of the Capital Programme 2024/25 to 2029/30

Background Papers None

Consideration of report by Council or other committee Not applicable

Council Approval Required Yes

Exempt from Press or Public No Provisional Capital Out-turn 2024/25 and Revised Capital Programme 2025/26 to 2028/29

Background

1.1At Council on 3rd March Members approved a revised capital programme totalling £37,397,415 covering the financial years 2024/25 to 2029/30, as summarised in table 1 below:

Table 1: Capital Programme approved 3rd March 2025

Financial year £ 2024/25 10,074,207 2025/26 20,931,994 2026/27 3,175,196 2027/28 993,696 2028/29 1,167,826 2029/30 1,054,496 Total 37,397,415

1.2This report provides information relating to the provisional outturn (subject to audit) for 2024/25 and seeks approval for a revised capital programme for 2025/26 to 2029/30, taking account of slippage from 2024/25. 2. Provisional Out-turn for 2024/25

2.1At Council on 3rd March a revised capital budget of £10,074,207 was approved for 2024/25.

2.2The actual total capital expenditure for 2024/25 was £9,687,256. Therefore, there was an overall underspend of £386,951. The Programme has been financed as shown in table 2 below:-

Table 2: Capital financing arrangements for 2024/25

Sources of Financing £ Capital Receipts 710,258 Capital Programme Reserve 71,847 S106 Contributions 1,383,675 Grants 7,246,441 Economic Development Reserve 42,299 IT Reserve 51,025 Corporate Plan Priority Reserve 30,910 Vehicle Reserve 70,483 Revenue Grants 69,272 Carsington Fund (STWA) 11,048 Total 9,687,256

2.3The expenditure incurred against each project is outlined at Appendix A, which provides explanations for under- and over-spends and whether each project has concluded. Where projects are continuing beyond the end of 2024/25, budget underspends have been carried forward and added to the budget for 2024/25. It is proposed to carry forward £314,977 of the provisional underspend from 2024/25 into 2025/26.

2.4Material project under- and over-spends of £10,000 or more in 2024/25 are explained below.

• Project 270 – Disabled Facilities Grants: (£65,405) Spending of this grant is demand led. The underspend in 2024/25 is earmarked in reserves for future schemes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
8a. Appendix A: Capital Out turn /25Appendix 214 KB Download
PDF
8b. Appendix B: 5 Year Programme 2025-26: 2029-30 /25Appendix 196 KB Download
PDF
8c: Appendix C: Capital Financing /25Appendix 380 KB Download
PDF
Provisional Capital Outturn 2024/25 and Revised Capital Programme 2025/26 to 2029/30Report 250 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

27 of 45 attended
RS
Roger Shelley LIBDEMChair, present
LP
Lucy Peacock LABVice-Chair, apologies
DG
Dawn Greatorex LABCommittee Member, apologies
RA
Robert Archer LIBDEMCommittee Member, apologies
AB
Anthony Bates CONCommittee Member, present
JB
John Bointon CONCommittee Member, present
GB
Geoff Bond CONCommittee Member, apologies
MB
Matt Buckler GREENCommittee Member, present
SB
Sue Bull CONCommittee Member, present
MB
Martin Burfoot LIBDEMCommittee Member, present
SB
Sue Burfoot LIBDEMCommittee Member, present
DB
David Burton LIBDEMCommittee Member, apologies

All 45 on the meeting page

On this subject at Derbyshire Dales

Search all
  1. Provisional Capital Outturn 2024/25 and Revised Capital Programme 2025/26 to 2029/30This decision
  2. Provisional Capital Out-Turn 2025/26 and Revised Capital Programme 2026/27 to 2030/31Approved
  3. Provisional Capital Out-turn 2023/24 & Revised Capital Programme 2024/25 to 2028/29Approved
  4. Provisional Capital Out-Turn 2022/23 and Revised Capital Programme 2023/24 to 2027/28Approved

More from Derbyshire Dales Council

All decisions
MeetingDecisionOutcome
23 Jul 2026 CommitteesRESOLVED (unanimously) That the non-exempt minutes of the listed in the Minute Book for the period 14 May 2026 to 02 ... Decided Open
23 Jul 2026 Approval of Minutes of Previous MeetingRESOLVED (unanimously) That the minutes of a meeting of Council held on 28 May 2026 and 18 June 2026 be approved as a... Approved Open
23 Jul 2026 Provisional Capital Out-Turn 2025/26 and Revised Capital Programme 2026/27 to 2030/31RESOLVED (unanimously) 1. That the provisional Capital Out-Turn of £15,075,300 as detailed in Appendix 1 be approved.... Approved Open
23 Jul 2026 Provisional Revenue Outturn 2025/26RESOLVED (unanimously) That in accordance with Procedure Rule 13 the meeting continue until 9.00pm. The substantive m... Noted Open
22 Jul 2026 Questions (rule of procedure 15)Decision making on planning applications is informed by the Local Plan, but each application for planning permission ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies