Provisional Capital Out-turn 2023/24 & Revised Capital Programme 2024/25 to 2028/29

Approved Committee 4 papers

Council approved this item on Thursday 25 July 2024. Below is the council's own wording, with the papers it was decided on.

Item91/24

Resolved

RESOLVED (unanimously) 1. That the provisional Capital Out-turn of £9,427,189 as detailed in Appendix A, is approved. 2. That the explanations regarding significant variances in planned and actual capital expenditure for 2023/24 are noted. 3. That an overall reduction of £68,745 is applied to the capital programme for 2024/25 consisting of a carried forward underspend of £253,454 at 31 March 2024 and other revisions totalling £-322,199, set out in paragraphs 3.1 and 3.2 and Appendix A be approved for inclusion into the capital programme. 4. That an additional amount of £240,000 is added to 2025/26 capital programme as set out in paragraph 3.2 and appendix A. 5. That the updated capital programme for 2024/25 to 2028/29 set out in Appendix B to the report totalling £28,917,955 be approved. 6. That financing of the Capital Programme from sources summarised at paragraph 3.21 and shown in Appendix C be approved. 7. That the balance of funds available over the 5-year programme, shown at Appendix C, is noted. The Chair declared the motion CARRIED. 21:07pm - Councillor Dermot Murphy left the meeting.
Word for word from the decision Derbyshire Dales published for this meeting. Source: democracy.derbyshiredales.gov.uk

Follow this further

Built from Derbyshire Dales's papers

What the report saysPro

Report to Council

Recommendations

1. That the provisional Capital Out-turn of £9,427,189 as detailed in Appendix A, is approved.

2. That the explanations regarding significant variances in planned and actual capital expenditure for 2023/24 are noted.

3. That an overall reduction of £68,745 is applied to the capital programme for 2024/25 consisting of a carried forward underspend of £253,454 at 31 March 2024 and other revisions totalling £-322,199, set out in paragraphs 3.1 and 3.2 and Appendix A be approved for inclusion into the capital programme.

4. That an additional amount of £240,000 is added to 2025/26 capital programme as set out in paragraph 3.2 and appendix A.

5. That the updated capital programme for 2024/25 to 2028/29 set out in Appendix B to the report totalling £28,917,955 be approved.

6. That financing of the Capital Programme from sources summarised at paragraph 3.21 and shown in Appendix C be approved. 7. That the balance of funds available over the 5-year programme, shown at Appendix C, is noted.

List of Appendices Appendix A Capital Out-turn 2023/24 Appendix B Revised Capital Programme 2024/25 – 2028/29 Appendix C Proposed financing of the Capital Programme 2023/24 to 2028/29

Background Papers None

Consideration of report by Council or other committee Not applicable

Council Approval Required Yes

Exempt from Press or Public No Provisional Capital Out-turn 2023/24 and Revised Capital Programme 2024/25 to 2028/29

Background

1.1At Council on 4th April Members approved a revised capital programme totalling £39,501,864, covering the financial years 2023/24 to 2028/29, as summarised in table 1 below:

Table 1: Capital Programme approved 4th April 2024

Financial year £ 2023/24 10,755,164 2024/25 21,818,043 2025/26 4,142,449 2026/27 1,077,736 2027/28 806,736 2028/29 901,736 Total 39,501,864

1.2This report provides information relating to the provisional outturn (subject to audit) for 2023/24 and seeks approval for a revised capital programme for 2024/25 to 2028/29, taking account of slippage from 2023/24. 2. Provisional Out-turn for 2023/24

2.1At Council on 4th April a revised capital budget of £10,755,164 was approved for 2023/24.

2.2The actual total capital expenditure for 2023/24 was £9,427,189. Therefore, there was an overall underspend of £1,327,975 The Programme has been financed as shown in table 2 below:-

Table 2: Capital financing arrangements for 2023/24

Sources of Financing £ Capital Receipts 398,989 Capital Programme Reserve 604,180 S106 Contributions 3,008,724 Grants 4,621,019 Economic Development Reserve 5,701 IT Reserve 51,291 Vehicle Reserve 489,251 Revenue Grants 248,034 Total 9,427,189

2.3The expenditure incurred against each project is outlined at Appendix A, which provides explanations for under- and over-spends and whether each project has concluded. Where projects are continuing beyond the end of 2023/24, budget underspends have been carried forward and added to the budget for 2024/25. It is proposed to carry forward £253,454 of the provisional underspend from 2023/24 into 2024/25.

2.4Material project under- and over-spends of £10,000 or more in 2023/24 are explained below.

• Project 270 – Disabled Facilities Grants : £270,308 underspend. (Funded by the Better Care Fund). Spending of this grant is demand led. The underspend in 2023/24 is earmarked in reserves for future expenditure.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Outturn: Appendix A /24Appendix 156 KB Download
PDF
Capital Outturn: Appendix B /24Appendix 135 KB Download
PDF
Capital Outturn: Appendix C /24Appendix 44 KB Download
PDF
Provisional Capital Out-turn 2023/24 & Revised Capital Programme 2024/25 to 2028/29Report 164 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

27 of 41 attended
RA
Robert Archer LIBDEMCommittee Member, apologies
AB
Anthony Bates CONCommittee Member, present
JB
John Bointon CONCommittee Member, present
GB
Geoff Bond CONCommittee Member, apologies
KB
Kelda Boothroyd GREENCommittee Member, present
MB
Matt Buckler GREENCommittee Member, present
SB
Sue Bull CONCommittee Member, present
MB
Martin Burfoot LIBDEMCommittee Member, present
SB
Sue Burfoot LIBDEMCommittee Member, present
DB
David Burton LIBDEMCommittee Member, apologies
BB
Bob Butcher LABCommittee Member, present
NB
Neil Buttle GREENCommittee Member, present

All 41 on the meeting page

On this subject at Derbyshire Dales

Search all
  1. Provisional Capital Out-turn 2023/24 & Revised Capital Programme 2024/25 to 2028/29This decision
  2. Provisional Capital Out-Turn 2025/26 and Revised Capital Programme 2026/27 to 2030/31Approved
  3. Provisional Capital Outturn 2024/25 and Revised Capital Programme 2025/26 to 2029/30Approved
  4. Provisional Capital Out-Turn 2022/23 and Revised Capital Programme 2023/24 to 2027/28Approved

More from Derbyshire Dales Council

All decisions
MeetingDecisionOutcome
23 Jul 2026 CommitteesRESOLVED (unanimously) That the non-exempt minutes of the listed in the Minute Book for the period 14 May 2026 to 02 ... Decided Open
23 Jul 2026 Approval of Minutes of Previous MeetingRESOLVED (unanimously) That the minutes of a meeting of Council held on 28 May 2026 and 18 June 2026 be approved as a... Approved Open
23 Jul 2026 Provisional Capital Out-Turn 2025/26 and Revised Capital Programme 2026/27 to 2030/31RESOLVED (unanimously) 1. That the provisional Capital Out-Turn of £15,075,300 as detailed in Appendix 1 be approved.... Approved Open
23 Jul 2026 Provisional Revenue Outturn 2025/26RESOLVED (unanimously) That in accordance with Procedure Rule 13 the meeting continue until 9.00pm. The substantive m... Noted Open
22 Jul 2026 Questions (rule of procedure 15)Decision making on planning applications is informed by the Local Plan, but each application for planning permission ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies