RESOLVED (unanimously) 1. That the Capital Programme expenditure to 31 st July 2024 be noted. 2. That re-phasing of existing projects for completion over the next 5 years be approved. 3. That new projects totalling £5,486,041 set out in paragraphs 2.12 to 2.29 of the report, be approved for inclusion in the programme. 4. That the revised capital programme for 2024/25 to 2028/29, as shown in Appendix A, totalling £33,466,045 be approved. 5. That financing of the Capital Programme from sources summarised at paragraph 3.21 and shown in Appendix B be approved. 6. That the balance of funds available over the 5-year programme, shown at Appendix B, be noted. The Chair declared the motion CARRIED .
Word for word from the decision Derbyshire Dales published for this meeting.Source: democracy.derbyshiredales.gov.uk
1. That the Capital Programme expenditure to 31st July 2024 is noted.
2. That re-phasing of existing projects for completion over the next 5 years is approved.
3. That new projects totalling £5,486,041 set out in paragraphs 2.12 to 2.29 of the report, are approved for inclusion in the programme.
4. That the revised capital programme for 2024/25 to 2028/29, as shown in Appendix A, totalling £33,466,045 is approved.
5. That financing of the Capital Programme from sources summarised at paragraph 3.21 and shown in Appendix B is approved.
6. That the balance of funds available over the 5-year programme, shown at Appendix B, is noted. List of Appendices
Appendix A Revised Capital Programme 2024/25 to 2028/29 Appendix B Proposed financing of the Capital Programme 2024/25 to 2028/29
Background Papers None
Consideration of report by Council or other committee Not applicable
Council Approval Required Yes
Exempt from Press or Public No Capital Programme Update
Background
1.1At the Council meeting on 25th July 2024 Members approved a revised capital programme totalling £28,917,905, covering the financial years 2024/25 to 2028/29, as summarised in table 1 below:
Table 1: Capital Programme approved 25th July 2024
Financial year £ 2024/25 21,749,298 2025/26 4,382,449 2026/27 1,077,736 2027/28 806,736 2028/29 901,736 Total 28,917,905
1.2This report provides information on the current financial position of spend against the 2024/25 Capital Programme as at 30th July 2024 and seeks approval for a revised capital programme for 2024/25 to 2028/98, taking account of the expected slippage into 2025/26 and including bids for 3 new projects and other changes.
2. Proposed revisions to the Capital Programme
Capital Expenditure for 2024/25
2.1At Council on 25th July a revised capital budget of £21,749,298 was approved for 2024/25.
2.2As at 31st July expenditure including commitments against the budget was £1,594,577.44 as shown in Appendix A.
2.3The forecast out turn for the 2024/25 capital programme determines that the amount in 2024/25 should be revised to £23,500,785, which is a difference of £1,751,487 from the budget approved in July 2024 as shown in Appendix A.
Table 2: Revised Capital financing arrangements for 2024/25
Sources of Financing £ Capital Receipts 1,551,776 Capital Programme Reserve 139,040 S106 Contributions 2,904,587 Grants 17,881,728 Economic Development Reserve 42,299 IT Reserve 135,000 Vehicle Reserve 391,882 Revenue Grants Unapplied 423,425 Carsington Grant Fund 11,048 Revenue Financing (virement) 20,000 Total 23,500,785
2.4Reprofiling of schemes into 2025/26 total £53,577 these are explained below:
• Project 625 – Bakewell Road scheme £27,104 funded by Capital Reserves. The revised allocation to phase 1 bus station refurbishment forecast is expected to be £127,000. The profiling has been amended to reflect this.
• Project 695 – Cemetery Paths: £30,000 funded by Capital Receipts The revised expenditure in 2024/25 is expected to be £40,000. The profiling has been amended and the slippage on this scheme is expected to take place in 2025/26. Other works funded from the UKSPF project have taken priority over this scheme due to the funding commitment to spend the awarded grant in 2024/25.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Approval of Minutes of Previous MeetingRESOLVED (unanimously) That the minutes of a meeting of Council held on 28 May 2026 and 18 June 2026 be approved as a...
Provisional Revenue Outturn 2025/26RESOLVED (unanimously) That in accordance with Procedure Rule 13 the meeting continue until 9.00pm. The substantive m...
Questions (rule of procedure 15)Decision making on planning applications is informed by the Local Plan, but each application for planning permission ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.