Resolved
To note the current position on the monitoring of Capital schemes. To note the current position on the monitoring of Capital schemes.
Cabinet noted this item on Thursday 7 December 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
To note the current position on the monitoring of Capital schemes. To note the current position on the monitoring of Capital schemes.
FOR PUBLICATION
DERBYSHIRE COUNTY COUNCIL
CABINET
7 December 2023
Report of the Director of Finance & ICT
Capital budget monitoring and forecast as at Quarter 2 2023-24 (Corporate Services and Budget)
1. Divisions Affected
1.1County-wide
2. Key Decision
2.1This is a Key Decision because it is likely to result in the Council incurring expenditure which is, or savings which are, significant, having regard to the budget for the service or function concerned (this is currently defined as £0.500m).
3. Purpose
3.1To inform Cabinet of the latest Capital budget monitoring position as at 30 September 2023.
4. Information and Analysis
4.1The report includes Cabinet approved schemes that have been active during this financial year, including schemes closed in year. All schemes have a nominated budget holder who is responsible for ensuring the scheme stays within budget, and who provides the projected spend figures. The schemes have been approved over several previous years in addition to the current year. 4.2 The 2023-24 capital programme is £313.436m, approved adjustments to this figure have increased this to £316.881m. The main reason for this increase is additional funding sources, including an additional grant of £4.213m for Pothole works. This is offset by some minor reductions in other funding. The budget for schemes being monitored this year (which includes schemes from prior years programmes) total £719.283m, of these, £663.611m are currently open schemes. There is a forecast underspend of £13.638m over the life of these projects (see Appendix 2).
4.3Adult Social Care & Health - projected underspend of £1.248m
Adult Care has a budget of £91.854m comprised of 19 schemes. Five schemes account for 78.08% of the budget. These are summarised in the table and narrative below. £1.000m of the underspends are on Belper and Heanor Integrated Specialist Facilities with more detail being included below.
(Under) Spend Budget Forecast /Over Major Schemes to Date £m £m spend £m £m Disabled Adaptations 20.833 17.552 20.833 0.000 2020 - 2023 Belper Integrated Specialist Facilities 15.613 14.841 15.113 (0.500) Centre Bennerley Avenue – Care 15.000 13.669 15.000 0.000 Home Darley Dale Specialist 10.520 10.423 10.518 (0.002) Community Care Centre Heanor Specialist 9.750 8.968 9.250 (0.500) Community Care Centre
Disabled Adaptations The Disabled Adaptations schemes are the currently open programmes which relate to aids and adaptations installed in resident’s own homes so they may remain as independent as possible. They will be fully financed from borrowing together with contributions from clients and district councils. Currently the projected spend is in line with the budget. Previously reported underspends on prior years programmes have been allocated to new adaptation projects. This had initially been intended to fund a new scheme to replace Telecare equipment but the demand for adaptations is utilising the budget. A separate budget of £1.250m was approved by Full Council in February 2023 for a project to provide the Telecare equipment and is being funded from borrowing.
The Belper Integrated Specialist Facilities Centre This major care home scheme (operational since 2020) is almost finalised and retention to the main contractor has been released. There is a requirement to improve car park security, and options are currently being explored. An underspend of £0.500m is anticipated after the security works are complete.
Bennerley Avenue - Care Home This major care home scheme (operational since 2022) is almost finalised, and the defects period ended in August 2023. The final certificate is due shortly. The business case specification is being prepared for phase 2 of the development and potential third-party investors will be invited to submit expressions of interest on the site.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Budget Monitoring and Forecast as at Quarter 2 2023-2024Report | 180 KB | DownloadRead as text |
Follow Cabinet at Derbyshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | Outcome of Rapid Options Assessment into Future Use of The Derby and Derbyshire Waste Treatment Centre (DDWTC)1) To note the content of the report and its appendices including the financial implications of the recommendations; ... | Noted | Open |
| 10 Sep 2026 | To approve, as a correct record, the non-exempt minutes of the meeting held on 30 July 2026To approve, as a correct record, the minutes of the above meeting. | Approved | Open |
| 10 Sep 2026 | Delivery of Quarter One of the 2026-27 Highways Capital ProgrammeRESOLVED to: 1) Note the £17.500m delivery of the annual Highways Capital Programme in Quarter 1 of 2026-27; and 2) N... | Noted | Open |
| 10 Sep 2026 | Derbyshire Employment and Skills Strategy 2026-2030RESOLVED to: a) Approve the formal adoption of the Derbyshire Employment and Skills Strategy 2026-30; b) Support the ... | Approved | Open |
| 10 Sep 2026 | Collaboration Agreement between Derbyshire County Council and Elvaston Castle and Gardens TrustRESOLVED to: 1) Approve the Council entering into the proposed Collaboration Agreement with Elvaston Castle and Garde... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.