Capital budget monitoring and forecast as at Quarter 1 2025-26

Noted Executive 1 paper

AI summaryDerbyshire County Council Cabinet noted the Quarter 1 2025-26 capital programme position, showing a forecast overall underspend of £12.926m against a total programme of £774.133m to 2028-29.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted the capital programme position
Money£12.926m underspendagainst £774.133m programme to 2028-29
What happens nextNo call-inDecision not subject to call-in
Who it affectsCouncil departments and capital projectsAdult Social Care, Children's Services, Place, Corporate Services

What was decided

Cabinet noted the current position on the monitoring of capital schemes, including the forecast underspend and the top ten projects by value. Report 10.1

Why

To ensure the council complies with best practice in providing regular capital reports to key stakeholders on estimates and expenditure. Report 11.1

The council's Financial Regulations require regular reporting of projected capital expenditure and resources compared with approved estimates. Report 6.1

What happens next

No further action arises; the position is reported rather than approved, and there is no call-in period for this decision. Report P12, 10.1

The money

  • £774.133m Total current capital programme to 2028-29 Report 1.1, P30
  • £12.926m Forecast overall underspend on the capital programme Report 1.1, P30

Options considered

  • Rejected: Do Nothing (no report submitted). Council's Financial Regulations require regular capital monitoring reports to Cabinet Report 6.1

Implications

  • Financial: Forecast overall underspend means no expectation that borrowing costs will exceed the revenue budget estimates; any capital spend above approved budgets would need financing and could create revenue pressures.
  • Legal: None directly arising out of this report. Report 2.1
  • Equalities: Not directly arising out of this report. Report 5.1, P22
  • Staffing: None directly arising out of this report. Report 3.1
  • Risk: None directly arising out of this report on risk management. Report 7.1, P26

Who and where

  • Adult Social Care and Health department (capital projects) Report P30
  • Children's Services department (capital projects) Report P30
  • Corporate Services and Transformation department (capital projects) Report P30
  • Place department (capital projects including transport, waste, regeneration) Report P30
  • Council taxpayers and residents (through funded services and borrowing costs)

Timeline

  • 30.06.2025: Forecast position reported as at this date Report P30
  • 16 October 2025: Cabinet meeting date when position was noted
  • 31 March 2026: End of 2025-26 financial year, planned spend to this date Report P30
  • 2026-27: Next planned capital spending year Report P30
  • 2027-28: Planned capital spending year Report P30
  • 2028-29: End date of the life of the current capital programme Report 1.1

Plain English for the jargon

  • Capital programme: The council's multi-year plan for spending on assets such as buildings, roads and equipment, funded from grants, receipts, borrowing, reserves or revenue contributions.
  • Underspend: Spending expected to come in below the approved budget, here shown in brackets as a negative figure.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item117/25

Resolved

To note the current position on the monitoring of Capital Schemes. To note the current position on the monitoring of Capital Schemes.
Word for word from the decision Derbyshire published for this meeting. Source: democracy.derbyshire.gov.uk

Follow this further

Built from Derbyshire's papers

What the report saysPro

Report to Cabinet

FOR PUBLICATION

DERBYSHIRE COUNTY COUNCIL

CABINET

16 October 2025

Report of the Director of Finance

Capital budget monitoring and forecast as at Quarter 1 2025-26

(Cabinet Member for Council Efficiency (DOGE))

1. Divisions Affected

1.1County-wide

2. Key Decision

2.1This is report informs Cabinet on the current position and forecast outturn of the Capital budget.

3. Purpose

3.1To inform Cabinet of the latest Capital budget monitoring position as at 30 June 2025.

4. Information and Analysis

4.1The report includes Cabinet approved schemes that have been active during this financial year, including schemes which are to be closed in year. All schemes have a nominated budget holder who is responsible for ensuring the scheme stays within budget, and who provides the projected spend figures. The schemes have been approved over several previous years in addition to the current year.

4.2The 2025-26 new capital programme approved by Full Council in February 2025 was £94.456m. The project budget for schemes being monitored this year (which includes schemes from prior years which

CONTROLLED date back to 2012, apart from Markham Vale which dates back to 1998) total £777.785m, of these, £774.133m are currently open schemes. There is a forecast underspend of £12.926m over the life of these projects (see Appendix 2).

4.3Adult Social Care & Health - projected underspend of £3.656m

Adult Care has a budget of £88.950m and comprises 24 schemes. The 7 largest schemes account for 81.6% of the budget. These are summarised in the table and narrative below. £2.491m of the underspends are shown below.

Scheme Spend Forecast (Under) Project to /Over Major Schemes Budget Date spend £m £m £m £m Belper Integrated Specialist 15.613 14.872 14.874 (0.739) Facilities Centre Bennerley Avenue - Care Home 15.000 13.951 15.000 0.000 Darley Dale Specialist Community 10.520 10.439 10.520 0.000 Care Centre Heanor Specialist Community Care 9.750 8.968 8.968 (0.782) Centre DFG Major Adaptations 2024-25 6.463 5.509 6.274 (0.190) DFG Major Adaptations 2023-24 5.730 5.825 5.919 0.190 Briar Close House refurbishment 5.008 4.478 4.478 (0.530) Bassett House Refurbishment 4.579 4.139 4.139 (0.440) Total of 7 largest schemes 72.663 68.181 70.172 (2.491)

The Belper Integrated Specialist Facilities Centre This major care home scheme (operational since 2020) is almost finalised and retention to the main contractor has been released. There is a requirement to improve car park security, and various options continue to be assessed. These range from barriers to signage. More recently we have had security issues i.e. people using our car park for the shops that are around our building.

Bennerley Avenue - Care Home This major care home scheme (operational since 2022) is almost finalised. There will be no further expenditure in the current year.

CONTROLLED Darley Dale Specialist Care Centre This care centre scheme is substantially complete (operational since 2016). There are latent defects due to leaks in the flat roof. The negotiation for the work is still being finalised by Legal and will commence once a way forward is agreed with the contractor.

Heanor Specialist Care Centre This care centre (operational since 2015) is now complete, and the final certificate has been issued. The project finished with an underspend of £0.782m.

Disabled Adaptations The Disabled Adaptations scheme relate to aids and adaptations installed in residents’ own homes so they may remain as independent as possible. The funding is made up of borrowing and contributions from clients and district councils (Disabled Facilities Grant up to £30,000 per application). Currently the projected spend is in line with the budget.

4.4Children’s Services - projected underspend of £2.434m

This underspend is across multiple projects with the highest being £0.414m on Harrington Junior School replacement, Alfreton Park School £0.0.015m and Glossopdale School Replacement £0.214m, Hunloke Park classroom block £0.161m.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital budget monitoring and forecast as at Quarter 1 2025-26Report 178 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 19 attended
AG
Councillor Alan GravesChairman, present
RR
Councillor Robert ReaneyVice-Chairman, present
DA
Councillor Dawn AbbottCommittee Member, present
JB
Councillor Joss BarnesCommittee Member, present
JB
Councillor Jack BradleyCommittee Member, apologies
CH
Councillor Charlotte HillCommittee Member, present
JL
Councillor John LawsonCommittee Member, present
SR
Councillor Sam RedfernCommittee Member, present
SR
Councillor Stephen ReedCommittee Member, present
CW
Councillor Carol WoodCommittee Member, present
EA
Emma AlexanderOfficer, in attendance
HB
Helen BarringtonOfficer, in attendance

All 19 on the meeting page

On this subject at Derbyshire

Search all
  1. Capital budget monitoring and forecast as at Quarter 1 2025-26This decision
  2. Capital Budget Monitoring and Forecast 2026/27 Quarter 1 (30 June 2026)Noted
  3. Allocations from the Children’s Services Capital BudgetApproved
  4. Capital budget monitoring and forecast as at Quarter 3Noted
  5. Children's Services SEND Capital Budget (High Needs Provision Capital) AllocationsApproved
  6. Children's Services SEND Capital Budget (High Needs Provision Capital) AllocationsApproved

More from Derbyshire Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Outcome of Rapid Options Assessment into Future Use of The Derby and Derbyshire Waste Treatment Centre (DDWTC)1) To note the content of the report and its appendices including the financial implications of the recommendations; ... Noted Open
10 Sep 2026 To approve, as a correct record, the non-exempt minutes of the meeting held on 30 July 2026To approve, as a correct record, the minutes of the above meeting. Approved Open
10 Sep 2026 Delivery of Quarter One of the 2026-27 Highways Capital ProgrammeRESOLVED to: 1) Note the £17.500m delivery of the annual Highways Capital Programme in Quarter 1 of 2026-27; and 2) N... Noted Open
10 Sep 2026 Derbyshire Employment and Skills Strategy 2026-2030RESOLVED to: a) Approve the formal adoption of the Derbyshire Employment and Skills Strategy 2026-30; b) Support the ... Approved Open
10 Sep 2026 Collaboration Agreement between Derbyshire County Council and Elvaston Castle and Gardens TrustRESOLVED to: 1) Approve the Council entering into the proposed Collaboration Agreement with Elvaston Castle and Garde... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies