FOR PUBLICATION
DERBYSHIRE COUNTY COUNCIL
CABINET
5 December 2024
Report of the Director of Finance
Capital budget monitoring and forecast as at Quarter 2 2024-25 (Corporate Services and Budget)
1. Divisions Affected
1.1County-wide
2. Key Decision
2.1This is a Key Decision because it is likely to result in the Council incurring expenditure which is, or savings which are, significant, having regard to the budget for the service or function concerned (this is currently defined as £0.500m).
3. Purpose
3.1To inform Cabinet of the latest Capital budget monitoring position as at 30 September 2024.
4. Information and Analysis
4.1The report includes Cabinet approved schemes that have been active during this financial year, including schemes closed in year. All schemes have a nominated budget holder who is responsible for ensuring the scheme stays within budget, and who provides the projected spend figures. The schemes have been approved over several previous years in addition to the current year.
4.2The 2024-25 new capital programme approved by Full Council in February 2024 was £100.569m, approved adjustments to this figure
CONTROLLED have increased this to £111.33m at 30 September 2024. The project budget for schemes being monitored this year (which includes schemes from prior years programmes) total £779.455m, of these, £718.359m are currently open schemes. There is a forecast underspend of £10.353m over the life of these projects (see Appendix 2).
4.3Adult Social Care & Health - projected underspend of £1.025m
Adult Care has a budget of £98.676m comprised of 20 schemes. 5 schemes account for 61.21% of the budget. These are summarised in the table and narrative below. £ 0.782m of the underspends are on Heanor Specialist Community Care Centre.
Scheme/ Project Spend Forecast (Under) Budget to /Over Major Schemes Date spend £m £m £m £m Belper Integrated Specialist Facilities 15.613 14.870 15.613 0.000 Centre Bennerley Avenue – Care 15.000 13.950 15.000 0.000 Home Darley Dale Specialist 10.520 10.437 10.520 0.000 Community Care Centre Heanor Specialist 9.750 8.968 9.250 (0.500) Community Care Centre Disabled Adaptations 9.518 7.191 9.518 0.000 (Open years) 2023 - 2024
Disabled Adaptations The Disabled Adaptations schemes are the currently open programmes for aids and adaptations installed in resident’s own homes to enable independent living for as long as possible. They are fully financed by borrowing and contributions from clients and district councils. Currently the projected spend is in line with the budget, despite inflationary pressures and demand led pressures. This is being closely monitored.
The Belper Integrated Specialist Facilities Centre This major care home scheme (operational since 2020) is almost finalised and retention to the main contractor has been released. There is a requirement to improve car park security, and various options are currently being explored. These range from barriers to signage.
CONTROLLED Bennerley Avenue - Care Home This major care home scheme (operational since 2022) is almost finalised, and the defects period ended in August 2023. The final certificate was issued in October 2023. The scheme spend is currently £13.950m with the project expecting to spend to budget. An adjacent piece of land is currently with the Property Disposal team with an aim to sell with a covenant to build another extra care centre.
Darley Dale Specialist Care Centre This care centre scheme is substantially complete (operational since 2016) with some minor works and retention fees outstanding. The final certificate has not yet been issued. The work on the turf roof commenced in January 2024. This work proved problematical. The negotiation for the quantum of remediation is being finalised with the contractor. Work will recommence when this is established.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital budget monitoring and forecast as at Quarter 2 2024-25Report | 177 KB | DownloadRead as text |
Follow Cabinet at Derbyshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | Outcome of Rapid Options Assessment into Future Use of The Derby and Derbyshire Waste Treatment Centre (DDWTC)1) To note the content of the report and its appendices including the financial implications of the recommendations; ... | Noted | Open |
| 10 Sep 2026 | To approve, as a correct record, the non-exempt minutes of the meeting held on 30 July 2026To approve, as a correct record, the minutes of the above meeting. | Approved | Open |
| 10 Sep 2026 | Delivery of Quarter One of the 2026-27 Highways Capital ProgrammeRESOLVED to: 1) Note the £17.500m delivery of the annual Highways Capital Programme in Quarter 1 of 2026-27; and 2) N... | Noted | Open |
| 10 Sep 2026 | Derbyshire Employment and Skills Strategy 2026-2030RESOLVED to: a) Approve the formal adoption of the Derbyshire Employment and Skills Strategy 2026-30; b) Support the ... | Approved | Open |
| 10 Sep 2026 | Collaboration Agreement between Derbyshire County Council and Elvaston Castle and Gardens TrustRESOLVED to: 1) Approve the Council entering into the proposed Collaboration Agreement with Elvaston Castle and Garde... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.