Draft Auditor's Annual Report 2024-25

Noted Finance 1 paper

AI summaryDerbyshire County Council Audit Committee noted a draft auditor's report for 2024-25 that finds significant weaknesses in financial sustainability and governance, and a new risk over the schools grant deficit.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedAudit Committee resolved to note the document
MoneyDSG deficit £44.737m, forecast £83.874mCumulative deficit at 31 March 2025, forecast by 31 March 2026
What happens nextFinal Auditor's Annual Report to followWording still subject to internal consultation
Who it affectsCouncil, residents, service usersParticularly Adult Social Care and Children's Services

What was decided

The Audit Committee resolved to note the draft Auditor's Annual Report for the year ended 31 March 2025.

Why

The auditor expects to report that the Council did not have adequate arrangements to secure economy, efficiency and effectiveness in its use of resources, and is preparing recommendations on significant weaknesses in financial sustainability and governance. Report P7, P18, P19

The auditor identified a new significant weakness around preparation for the end of the statutory override on the Dedicated Schools Grant deficit, on top of weaknesses carried forward from 2023/24 on financial sustainability and governance. Report P18, P41, P44, P69

What happens next

The auditor will issue its final Auditor's Annual Report and audit opinion on the financial statements once internal consultation and remaining work are complete. Report P7, P11, P67

The Council is expected to develop a robust management plan to fund the DSG deficit before the statutory override ends in March 2028. Report P40, P69

The Council is to maintain transparent governance arrangements for local government reorganisation, with the Audit Committee to seek specific assurance once plans are finalised. Report P59, P62

The money

  • £44.737m Cumulative DSG deficit at 31 March 2025 Report P24, P39
  • £39.027m Forecast in-year DSG deficit for 2025-26 Report P24, P39
  • £83.874m Forecast cumulative DSG deficit by 31 March 2026 Report P24, P39
  • £39.519m Forecast High Needs Block overspend 2025-26 Report P39
  • £0.582m Overall Council underspend for 2024/25 Report P27
  • £18.879m Earmarked reserves used in 2024/25 outturn Report P27
  • £10.977m Planned use of reserves in 2024/25 budget Report P27
  • £7.902m Additional Earmarked and General Reserves drawn down Report P27
  • £11.7m Underspend on Minimum Revenue Provision in 2024/25 Report P27
  • £10.7m MRP saving from policy change to annuity method Report P27
  • £21.127m Adult Social Care directorate overspend 2024/25 Report P27
  • £27.333m Children's Services directorate overspend 2024/25 Report P27
  • £39.556m General Fund Reserve at 31 March 2025 Report P27
  • £192.814m Earmarked Reserves at 31 March 2025 Report P27
  • £4.347m Budget Management Reserve at 31 March 2025 Report P27
  • £31.940m 2024/25 savings target Report P30
  • £29.185m 2024/25 savings achieved (93% of target) Report P30
  • £96.385m Further savings required in MTFP to 2029/30 Report P30
  • £50.097m Unidentified savings gap in MTFP to 2029/30 Report P30
  • £37.499m Identified savings to be delivered in 2025/26 Report P30
  • £723.706m Closing Capital Financing Requirement at 31 March 2025 Report P35
  • £13.822m MRP charge for 2024/25 Report P35
  • £147m Capital additions spend in 2024/25 Report P35
  • £6.9m Maximum qualifying transformation expenditure from capital receipts in 2025/26 Report P35
  • £38m Annual guaranteed funding stream from East Midlands Devolution Deal Report P58

Options considered

  • Chosen: Note the draft Auditor's Annual Report 2024-25

Implications

  • Financial: Auditor concludes a significant weakness remains in financial sustainability: a 2024/25 underspend depended on £18.879m of earmarked reserves and a one-off £11.7m MRP accounting adjustment. Report P27, P43
  • Financial: Auditor identifies a new significant weakness over the Dedicated Schools Grant deficit, forecast to reach £83.874m by 31 March 2026 before the statutory override ends in March 2028. Report P24, P39, P40, P44
  • Financial: Council is planning to use flexible capital receipts of up to £6.9m to fund transformation in 2025/26; the auditor notes this is not a long-term solution to the funding gap. Report P35
  • Risk: Auditor concludes the significant weakness in governance remains, citing another limited Head of Internal Audit opinion and 29 internal audit recommendations over 12 months overdue at March 2025. Report P47, P52, P77
  • Legal: Two elector objections on 2023/24 accounts remain open and await information from the Council; no objections have been received on 2024/25 accounts. Report P9, P79
  • Other: Auditor makes an 'other' recommendation that the Council maintain effective governance over local government reorganisation and that the Audit Committee seek specific assurance once plans are finalised. Report P59, P62
  • Equalities: An area SEND inspection of the Derbyshire Local Area Partnership in November 2024 identified widespread failings; a priority action plan was developed in January 2025. Report P56
  • Climate: East Midlands Combined County Authority, formed March 2024, will focus on transport, housing, skills, net zero, economic development and visitor economy; Derbyshire is part of a £38m per annum devolution deal. Report P58

Who and where

  • Adult Social Care service users and Children's Services users (including SEND) Report P27, P56
  • Council tax payers and Derbyshire residents Report P27, P35
  • Schools (DSG High Needs Block providers) Report P39
  • Council staff (workforce implications of reorganisation) Report P62
  • Internal audit and council officers implementing overdue recommendations Report P47

Timeline

  • 31 March 2025: Year-end for the 2024-25 accounts covered by the report Report P1, P6
  • July 2025: Cabinet considered the 2024/25 financial outturn Report P27
  • November 2025: Draft Auditor's Annual Report issued Report P1
  • 2 December 2025: Audit Committee noted the draft report
  • 31 March 2026: Forecast date for cumulative DSG deficit of £83.874m Report P24, P39
  • March 2028: Expiry of extended statutory override for DSG deficits Report P24, P40

Plain English for the jargon

  • AAR: Auditor's Annual Report
  • DSG: Dedicated Schools Grant, the ring-fenced funding for schools
  • MRP: Minimum Revenue Provision, the amount a council sets aside each year to repay capital borrowing
  • MTFP: Medium Term Financial Plan, the council's forward budget strategy
  • VFM: Value for Money, the auditor's assessment of economy, efficiency and effectiveness
  • WGA: Whole of Government Accounts, the consolidated national accounts the NAO prepares
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item68/25

Resolved

RESOLVED to note the report.
Word for word from the decision Derbyshire published for this meeting. Source: democracy.derbyshire.gov.uk

Follow this further

Built from Derbyshire's papers

What the report saysPro

Report to Audit Committee

DRAFT Auditor’s Annual Report Derbyshire County Council– year ended 31 March 2025

November 2025 Contents

01 Introduction 02 Audit of the financial statements 03 Commentary on VFM arrangements 04 Other reporting responsibilities

Our reports are prepared in the context of the ‘PSAA Statement of Responsibilities of Auditors and of Audited Bodies’ and the ‘Appointing Person Terms of Appointment’ issued by Public Sector Audit Appointments Limited. This document is to be regarded as confidential to Derbyshire County Council. It has been prepared for the sole use of the Audit Committee as the appropriate sub- committee charged with governance. We do not accept any liability or responsibility to any other person in respect of the whole or part of its contents.

2 Introduction 01 Introduction

Purpose of the Auditor’s Annual Report Our Auditor’s Annual Report (AAR) summarises the work we have undertaken as the auditor for Derbyshire County Councill (‘the Council’) for the year ended 31 March 2025. Although this report is addressed to the Council, it is designed to be read by a wider audience including members of the public and other external stakeholders. Our responsibilities are defined by the Local Audit and Accountability Act 2014 and the Code of Audit Practice (‘the Code’) issued by the National Audit Office (‘the NAO’). The remaining sections of the AAR outline how we have discharged these responsibilities and the findings from our work. These are summarised below.

Value for Money arrangements Opinion on the financial statements We expect to state in our audit report that we are not satisfied arrangements were in place for the Council to secure economy, efficiency and effectiveness in its use of resources. We have not yet issued our audit report. We will provide an update on our opinion on the This is because we are expecting to issue recommendations in relation to significant financial statements in our final Auditor’s Annual Report. weaknesses in those arrangements that are relevant to the 2024/25 financial year. Section 3 provides our commentary on the Council’s arrangements and a summary of our draft recommendations, and the weaknesses identified. Please note these recommendations are being reviewed through our internal consultation process. The final approved wording will be reported in our final Auditor’s Annual Report.

Reporting to the group auditor At the date of reporting our work on the Council’s Whole of Government Accounts return remains incomplete whilst we wait for final instructions from the National Audit Office

Wider reporting responsibilities We are still working on our response to two objections raised by electors on the 2023/24 financial statements and await information from the Council to enable us to conclude. We have not currently received any objections on the 2024/25 financial statements.

4 Audit of the financial statements 02 Audit of the financial statements

Our audit of the financial statements Our audit is conducted in accordance with the requirements of the Code, and International Standards on Auditing (UK) (ISAs). The purpose of our audit is to provide reasonable assurance to users that the financial statements are free from material error. We do this by expressing an opinion on whether the statements are prepared, in all material respects, in line with the financial reporting framework applicable to the Council and whether they give a true and fair view of the Council’s financial position as at 31 March 2025 and of its financial performance for the year then ended. Our audit is ongoing, and we have not yet issued our audit report. We are not yet at a stage to share our conclusions. Once our audit is finalised, we will provide detail of our findings in our final Auditor’s Annual Report.

6 Our work on Value for Money arrangements 03 VFM arrangements

Overall Summary VFM arrangements – Overall summary

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Draft Auditor's Annual Report 2024-25Report 775 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 23 attended
PO
Councillor Paul OxberryChairman, present
MB
Councillor Matthew BenfieldCommittee Member, present
MC
Councillor Mark CliffCommittee Member, present
DG
Councillor Damien GreenhalghCommittee Member, present
RH
Councillor Rachael HatchettCommittee Member, present
AH
Councillor Adrian HunterCommittee Member, present
PP
Councillor Paul ParkinCommittee Member, apologies
JH
Councillor Jamie HodgsonCommittee Member, expected
NG
Councillor Nigel GourlayCommittee Member, apologies
JG
Julia GaleCouncil Staff, expected
MK
Mark KenyonOfficer, in attendance
DS
Danny SunderlandClerk, expected

All 23 on the meeting page

On this subject at Derbyshire

Search all
  1. Draft Auditor's Annual Report 2024-25This decision
  2. Report of the External Auditor - Audit Strategy Memorandum - year ending 31 March 2026Noted
  3. External Auditor progress reportDecided
  4. External Auditor reportsNoted
  5. To consider the reports of the External AuditorDecided
  6. To consider the reports of the External AuditorDecided

More from Derbyshire Audit Committee

All decisions
MeetingDecisionOutcome
14 Jul 2026 Place Department Risk ManagementIt was agreed that the Chairman take a request to Cabinet to open the project to scrutiny by the Committee bearing in... Agreed Open
14 Jul 2026 Performance Monitoring and Budget Monitoring Outturn 2025-26 as at Quarter 4 (31 March 2026)RESOLVED that the Committee notes: a) The Council Plan performance and Revenue outturn position for 2025-26; b) The c... Decided Open
14 Jul 2026 Internal Audit Charter UpdateRESOLVED that the Committee approve the Council’s Internal Audit Charter. Approved Open
14 Jul 2026 Counter Fraud Strategy UpdateRESOLVED to approve the Counter Fraud Strategy 2026-27 as appended at Appendix 2 to the report. Approved Open
14 Jul 2026 National Fraud Initiative UpdateRESOLVED that the Committee note the outcomes to date of the Council’s participation in the NFI 2024-25 exercise and ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies