that the application be delegated to the Development Management Manager to grant subject to t he successful completion of a S106 Legal Agreement to secure ; 1. All the dwellings to be affordable in perpetuity and to meet the NPPF’s definitions of social-rented and low-cost housing 2. Strategic Access Management and Monitoring contribution in relation to mitigation for the proposal’s impact on Heathland Sites of Special Scientific Interest. And the conditions outlined in the appendix to these minutes. Or If a Section 106 Legal agreement and other information set out below are not secured by 30 th July 2019, Refuse planning permission as the proposal would: Fail to secure the appropriate affordable housing provision in accordance with Core Strategy affordable housing ... view the full minutes text for item 3.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
£$REFERENCE NO. 3/18/0996/OUT Development of 9 affordable dwellings and associated £$APPLICATION access onto Pardys Hill. Outline application with all PROPOSAL matters reserved. As amended by plans received 7/11/2018 Land to the north of Pardy's Hill, West of Sleight Lane £$ADDRESS Corfe Mullen BH21 3HW £$RECOMMENDATION - Grant, subject to conditions: (see Section 11 of the report for the full recommendation) REASON FOR REFERRAL TO COMMITTEE The application has been called to Committee at the request of the Development Management Manager in accordance with the provision of the Constitution. SUMMARY OF REASONS FOR RECOMMENDATION Proposal would comply with Core Strategy affordable housing exceptions site Policy LN4 providing 9 new affordable dwellings Proposed dwellings would not be at risk from surface water flooding d there would be no worsening of surface water flooding at the site or downstream with an acceptable surface water drainage scheme in place The traffic movements generated by the development can be accommodated without detriment to highway safety or the character of the area and adequate parking provision can be secured The Proposal would not adversely impact upon protected trees, appropriate biodiversity mitigation and enhancement can be secured to ensure no harm to European protected heathlands There is not considered to be any significant harm to neighbouring residential amenity from loss of privacy, overshadowing or dominance. INFORMATION ABOUT FINANCIAL BENEFITS OF THE PROPOSAL
The following are considered to be material to the application: Contributions to be secured through Section 106 legal agreement: £2367 for Heathland Strategic Access Management and Monitoring (SAMM) Contributions to be secured through CIL: Unknown at this stage
The following are not considered to be material to the application: Estimated annual council tax benefit for District: £207.32 per property. Total: £1865.88 Estimated annual council tax benefit total: £1933.95 per property. Total: £17,405.55 Estimated annual new homes bonus per residential unit, per year (for first 4 years): £1,200 approx. (NB. based on current payment scheme, the assumption that the 0.4% housing growth baseline is exceeded and assuming this baseline is reached through the delivery of other new homes) Eastern Planning Committee 29th May 2019
Henshaw Planning Services APPLICANT [name removed] Ltd PARISH/ WARD Corfe Mullen TOWN Corfe Mullen COUNCIL PUBLICITY OFFICER EXPIRY 13 March 2019 SITE VISIT 21/05/2018 DATE DATE DECISION EXT. OF 2 August 2018 15 August 2018 DUE DATE TIME RELEVANT PLANNING HISTORY App No Proposal Decision Date 3/16/0614/OUT 12 affordable dwellings with associated Refused. 14/2/17 access Appeal dismissed 18/10/17. Reasons for refusal: insufficient justification for an affordable housing exception site, not small scale no mechanism to secure affordable housing in perpetuity therefore development fails to accord with Local Plan Policy LN4) and represents inappropriate development within the Green Belt.
fails to demonstrate that flood risk would not increase as a result of the development proposed, or that post-development surface water runoff would not exceed pre-development levels ( Local Plan policy ME6)
fails to demonstrate that the proposed quantum of development can be achieved on the site without harm to the landscape character by reason of its likely impact on protected trees, visual amenity and tranquillity contrary to policies HE2 and HE3 of the Local Plan
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.