Decision (a) That the acquisition of the land and the drainage works on the east side of Dinah's Hollow, Melbury Abbas be progressed immediately at a total cost of £130k. (b) That Cabinet notes the scale of additional resource required to stabilise slopes throughout the hollow and that the affordability of the scheme should be considered alongside other priorities as part of the 2021/22 budget setting process and MTFP. Reason for Decision The impact of a major slope failure would be high in respect of health and safety and financial implications. Possible consequences are loss of life or major injury and legal action. There would also be reputational damage, impact on service delivery and disruption to the highway network affecting a key north-south route.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
The impact of a major slope failure would be high in respect of health and safety and financial implications. Possible consequences are loss of life or major injury and legal action. There would also be reputational damage, impact on service delivery and disruption to the highway network affecting a key north-south route. 1. Executive Summary
1.1On 02 December 2015 the predecessor County Council’s Cabinet suspended the proposed Dinah's Hollow Slope Stabilisation scheme. The decision was made pending the outcome of bids for the funding of a north/south strategic link between the M4 and Poole Port following the collaborative work with Bath and North East Somerset and Wiltshire Councils and the respective LEPs. In the Budget 2020, delivered on 11 March 2020, the government announced that it would provide over £27 billion between 2020 and 2025 to boost regional connectivity through the Second Road Investment Strategy (RIS2). Exploring the case for improvements to the links between the M4 and the Dorset Coast was in included in the list of named schemes. Meanwhile, the risk of a major landslip causing injury and closing the C13 remains. The Capital Strategy and Asset Management Group (CSAM) reviewed the risk on 1 June 2020 and confirmed the bid for corporate capital funds should progress.
1.2Dorset Council now has the opportunity to acquire the land on the east side of Dinah's Hollow by agreement. Acquisition would enable one possible trigger for a landslip to be mitigated through drainage works. (Recommendation 1).
1.3For full mitigation of the risk of landslip throughout the hollow, the suspension of the stabilisation scheme needs to be lifted and work completed on both east and west sides. This would require an additional easement over, or acquisition of, land on the west side. Negotiation with the current owner on the west side made no progress before the suspension and compulsory purchase may be necessary.
1.4The cost of completing the full scheme to mitigate the risk on both sides, maintaining the existing traffic management arrangements of alternate single lane working, is estimated to be £4.5 million. (Recommendation 2).
Financial implications
2.1A budget of £520k, allocated prior to the suspension of the scheme, has been carried forward and is sufficient to allow drainage and land acquisition on the east side but not stabilisation (Recommendation 1).
2.2A further capital investment of £3.98m is needed to fund the full slope stabilisation of Dinahs Hollow (Recommendation 2). 3. Climate implications
3.1The projected increase in storms and periods of prolonged wet weather will be detrimental to slope stability and increase the risk of slippage.
4. Other Implications
4.1The slopes either side of the C13 are in private ownership. Acquiring the slopes, by agreement or using compulsory powers, will allow the Council to have full control of the slopes and thus be in a position to undertake any appropriate works. It would though mean the Council, as landowner, would take on potential liability for any future landslip.
5. Risk Assessment
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Dorset Council Annual Report 2025 - 2026That the Dorset Council Annual Report for 2025-2026 be received and noted. Reason for the decision The annual report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.