Dorset Council Climate and Ecological Emergency Strategy Delivery plan

Noted Executive 3 papers

Cabinet noted this item on Tuesday 6 October 2020. Below is the council's own wording, with the papers it was decided on.

Item27

Resolved

Decision (a) That the scale of additional resource requirements to deliver the climate emergency strategy 2040 and 2050 targets be noted, and that affordability should be considered as part of the 2021/22 budget setting process and MTFP. (b) That the Summary Climate Action Plan (set out at appendix A) be approved for public consultation along with the Climate and Ecological Emergency Strategy (c) That the Portfolio Holder in conjunction with the Executive Director of Place to agree the final wording of the final document.
Word for word from the decision Dorset published for this meeting. Source: moderngov.dorsetcouncil.gov.uk

Follow this further

Built from Dorset's papers

What the report saysPro

Report to Cabinet

Recommendation

It is recommended that:

1. Cabinet notes the scale of additional resource requirements to deliver the climate emergency strategy 2040 and 2050 targets, and that affordability should be considered as part of the 2021/22 budget setting process and MTFP.

2. Cabinet approves the Summary Climate Action Plan (Appendix A) for public consultation along with the Climate and Ecological Emergency Strategy

Reason for recommendation

Executive summary

Dorset Council declared a Climate and Ecological Emergency in 2019 and established an Executive Advisory Panel to strategically guide the Councils response. A draft Climate and Ecological Emergency Strategy was produced in July 2020 which presented 8 key areas for action to ensure that Dorset Council becomes Carbon Neutral by 2040 and the Dorset Council Area by 2050. The draft Strategy was approved by the EAP, Scrutiny Committee and Cabinet 28th July 20.

The pathway to carbon neutrality is critical and is presented in the draft strategy as a carbon budget detailing the necessary reductions in carbon emissions against key target dates to meet the 2040 target. Cabinet asked for a costed delivery plan to be developed for consideration in October 2020. This was to set out detailed actions required to deliver against the strategy targets with associated costs and budget requirements for consideration within the short and medium-term financial planning processes.

This paper sets out the findings of this work and budget considerations, providing an indication of working costs to feed into the budget setting process. It is recommended to incorporate the delivery plan within the public consultation process for the draft strategy, to take place from the end of October 2020.

Financial implications

Draft costs have been identified for all 187 actions within the delivery plan. Of these 100 have been identified as achievable through ‘Business as Usual’ (BAU) within existing budgets. However, alone these will not achieve the significant shift required to deliver on the strategy commitments and additional funding will be required. Overall this figure is estimated in the region of £127million.

The delivery plan highlights an additional revenue requirement in the region of £2.6 Million for 2021/22. These costs principally relate to strengthening BAU existing work areas, undertaking further detailed studies to develop targeted programmes of work, and additional resource to enable delivery of the strategy and wider engagement with public and communities.

Eight capital projects have also been identified to start in 2021/22 principally related to Dorset Council moving towards a carbon neutral estate, shifting to electric vehicles and generating renewable energy. Bids will need further consideration as part of 2021/22 capital programme. Many of the Capital actions will not only achieve carbon savings but have the potential to deliver significant revenue savings. Significant further work will be required to develop actions into detailed business cases and programmes of work.

The delivery of the strategy is a long-term commitment over a 20 to 30 year period and current costs assigned within the delivery plan are best estimates at this time. In many areas further detailed work is required to refine the figures.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Climate Plan: 110920 pdfAppendix A 272 KB Download
PDF
ACTION-PLAN_Buildings(p)Appendix B 508 KB Download
PDF
Dorset Council Climate and Ecological Emergency Strategy Delivery planReport 77 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 65 attended
SF
Councillor Spencer FlowerChairman, present
PW
Councillor Peter WharfVice-Chair, present
RB
Councillor Ray BryanCommittee Member, present
GC
Councillor Graham Carr-JonesCommittee Member, present
TF
Councillor Tony FerrariCommittee Member, present
LM
Councillor Laura MillerCommittee Member, present
AP
Councillor Andrew ParryCommittee Member, present
GS
Councillor Gary SuttleCommittee Member, present
JH
Councillor Jill HaynesCommittee Member, present
DW
Councillor David WalshCommittee Member, present
MP
Matt ProsserOfficer, in attendance
AD
Aidan DunnOfficer, in attendance

All 65 on the meeting page

On this subject at Dorset

Search all
  1. Dorset Council Climate and Ecological Emergency Strategy Delivery planThis decision
  2. Dorset Council Climate and Ecological Emergency StrategyDeferred
  3. Draft Dorset Council Climate and Ecological Emergency Strategy for Public ConsultationApproved

More from Dorset Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 July 2026 (period 4) financial management report 26/27Decision (a) That the Senior Leadership Team’s forecast as of July 2026 including progress in addressing demand for s... Noted Open
8 Sep 2026 Additional Procurement Pipeline Report - over £500k (2026 - 27) and Modern Slavery Transparency Statement 2025 - 2026Decision (a) Cabinet considered the contents of the report (of 8 September 2026) in respect of proposed additional mo... Approved Open
8 Sep 2026 Exempt BusinessDecision That the press and the public be excluded for the following item(s) in view of the likely disclosure of exem... Decided Open
28 Jul 2026 Dorset Council Annual Report 2025 - 2026That the Dorset Council Annual Report for 2025-2026 be received and noted. Reason for the decision The annual report ... Noted Open
28 Jul 2026 Dorset Local Visitor Economy Partnership Destination Management Plan(a) That the Dorset Local Visitor Economy Partnership Destination Management Plan (DLVEPDM) be adopted and (b) That a... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies