Decision (a) That the scale of additional resource requirements to deliver the climate emergency strategy 2040 and 2050 targets be noted, and that affordability should be considered as part of the 2021/22 budget setting process and MTFP. (b) That the Summary Climate Action Plan (set out at appendix A) be approved for public consultation along with the Climate and Ecological Emergency Strategy (c) That the Portfolio Holder in conjunction with the Executive Director of Place to agree the final wording of the final document.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
1. Cabinet notes the scale of additional resource requirements to deliver the climate emergency strategy 2040 and 2050 targets, and that affordability should be considered as part of the 2021/22 budget setting process and MTFP.
2. Cabinet approves the Summary Climate Action Plan (Appendix A) for public consultation along with the Climate and Ecological Emergency Strategy
Reason for recommendation
Executive summary
Dorset Council declared a Climate and Ecological Emergency in 2019 and established an Executive Advisory Panel to strategically guide the Councils response. A draft Climate and Ecological Emergency Strategy was produced in July 2020 which presented 8 key areas for action to ensure that Dorset Council becomes Carbon Neutral by 2040 and the Dorset Council Area by 2050. The draft Strategy was approved by the EAP, Scrutiny Committee and Cabinet 28th July 20.
The pathway to carbon neutrality is critical and is presented in the draft strategy as a carbon budget detailing the necessary reductions in carbon emissions against key target dates to meet the 2040 target. Cabinet asked for a costed delivery plan to be developed for consideration in October 2020. This was to set out detailed actions required to deliver against the strategy targets with associated costs and budget requirements for consideration within the short and medium-term financial planning processes.
This paper sets out the findings of this work and budget considerations, providing an indication of working costs to feed into the budget setting process. It is recommended to incorporate the delivery plan within the public consultation process for the draft strategy, to take place from the end of October 2020.
Financial implications
Draft costs have been identified for all 187 actions within the delivery plan. Of these 100 have been identified as achievable through ‘Business as Usual’ (BAU) within existing budgets. However, alone these will not achieve the significant shift required to deliver on the strategy commitments and additional funding will be required. Overall this figure is estimated in the region of £127million.
The delivery plan highlights an additional revenue requirement in the region of £2.6 Million for 2021/22. These costs principally relate to strengthening BAU existing work areas, undertaking further detailed studies to develop targeted programmes of work, and additional resource to enable delivery of the strategy and wider engagement with public and communities.
Eight capital projects have also been identified to start in 2021/22 principally related to Dorset Council moving towards a carbon neutral estate, shifting to electric vehicles and generating renewable energy. Bids will need further consideration as part of 2021/22 capital programme. Many of the Capital actions will not only achieve carbon savings but have the potential to deliver significant revenue savings. Significant further work will be required to develop actions into detailed business cases and programmes of work.
The delivery of the strategy is a long-term commitment over a 20 to 30 year period and current costs assigned within the delivery plan are best estimates at this time. In many areas further detailed work is required to refine the figures.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Dorset Council Annual Report 2025 - 2026That the Dorset Council Annual Report for 2025-2026 be received and noted. Reason for the decision The annual report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.