Resolved
Decision That the report be noted.
Audit and Governance Committee noted this item on Monday 18 January 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision That the report be noted.
Dorset Council Report of Internal Audit Activity Progress Report 20/21 – December 2020
Internal Audit ▪ Risk ▪ Special Investigations ▪ Consultancy Unrestricted Executive Summary As part of our update reports, we will Audit Opinion, Summary of Significant Risks and Follow up work provide an ongoing opinion to support the end of year annual opinion. Introduction: Since our last update, England has had a further four-week period of lockdown, followed by a return to a much We will also provide details of any stricter tier system of restrictions. Whilst this second lockdown and stricter tier system has not impacted on our significant risks that we have audit work in the same way as the first national lockdown, the two audit staff that were redeployed to assist the identified in our work, along with the Council with payment of business grants have been seconded to the Revenues and Benefits team again for the progress of mitigating previously second round of business grant payments. This has impacted on the resources available to the team. identified significant risks by audit. Audit Opinion: This is our third quarterly update for 2020/21 and reviews completed have highlighted that whilst generally risks The contacts at SWAP in are well managed, we have identified some gaps, weaknesses and areas of non-compliance. However, we have connection with this report are: reasonable levels of confidence that the agreed actions will be implemented and thus strengthen internal control.
Since our last report in September 2020, we have issued five Limited opinions on the areas and activities we have Rupert Bamberger been auditing but none have been classified as a significant risk. Senior Management are now increasingly Assistant Director directing internal audit to areas of likely risk, or known issues, which is a positive. This will naturally result in an Tel: [phone removed] increased number of Limited assurance opinions. In Appendix A on pages 6-11, we provide a summary of the [email removed] Limited opinion work, to provide the committee with further insight. Sally White Significant Risks: Principal Auditor In our September update we highlighted the significant corporate risk around the reasons for a largely unpredicted Tel: [phone removed] budget overspend in 2019-20 for both SEN and Mainstream Home to School Transport. We are currently [email removed] undertaking follow up work and will provide an update to the March committee around progress to mitigate this risk.
As part of our September update on the use of Pupil Premium Plus (PPP) Grant by the Virtual School (VS) for Looked After Children (LAC) we reported that it was not possible to assure members that the corporate risk had been effectively mitigated. We have further follow up work planned for the new year and hope to able to provide an update in our next report.
SWAP work is completed to comply with the International Professional Practices Framework of the Institute of Internal Auditors, further Page 1 of 17 guided by interpretation provided by the Public Sector Internal Audit Standards (PSIAS) and the CIPFA Local Government Application Note.
Unrestricted Executive Summary Follow up Following the report to the Committee by the Senior Manager for Assurance we are currently undertaking a further review of Whistleblowing along with an audit review of Fraud Reporting. We are working with the Service Manager in order to be able to report a satisfactory position. In respect of the follow up work with Portesham School, we are currently working with the school to obtain an updated position to ensure satisfactory progress. Additionally, we have also undertaken a further follow up of Financial Reconciliations and the details of this can be found on page 12.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit 2020/21 Plan Progress ReportReport | 609 KB | DownloadRead as text |
Follow Audit and Governance Committee at Dorset and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Aug 2026 | Recruitment to the Independent Remuneration Panel Report- That support was sought from South-West Councils to fulfil the role of chair of the panel; - That an open recruitme... | Decided | Open |
| 3 Aug 2026 | Exempt BusinessThat the press and the public be excluded for the following item(s) in view of the likely disclosure of exempt inform... | Decided | Open |
| 27 Apr 2026 | Risk Management UpdateDecision - That the selected Strategic Risks and their associated risk appetites, as context for the committee’s cons... | Noted | Open |
| 27 Apr 2026 | Audit Actions Update ReportDecision - That the SWAP audit update provided in the report, including the detailed progress report at Appendix 1 be... | Noted | Open |
| 27 Apr 2026 | Corporate Complaints PolicyIt was agreed that a report would be brought back in six months to review the revised policy. Decision That the Audit... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.