Decision Executive Decision Notice - Weymouth Harbour & Esplanade Flood and Coastal Risk Management Strategic Outline Case - Dorset Council Reason for the decision At its Annual Meeting, Council decided to continue to meet virtually for all non-executive committees. The Leader of the Council also decided that Cabinet should continue to meet virtually until social distancing requirements had been removed. Therefore, the Portfolio Holder for Customer and Community Services has made this decision taking into account the views expressed by the wider cabinet membership. Weymouth Town Centre and parts of the surrounding area are at risk of flooding and coastal erosion. With a projected acceleration in sea level rise and more intense weather events because of climate change, the problems facing Weymouth will increase significantly .
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
Cabinet 22 June 2021 Weymouth Harbour & Esplanade Flood and Coastal Risk Management Strategic Outline Case For Decision Portfolio Holder: Cllr R Bryan, Highways, Travel and Environment Cllr T Ferrari, Economic Growth, Assets & Property
Local Councillor(s): Cllr Jon Orrell
Executive Director: J Sellgren, Executive Director of Place
Report Author: Sarah Cairns Title: Service Manager – Major Projects Tel: 01305 252398 Email: [email protected]
Report Status: Public
Recommendation: That Cabinet: 1. Agrees the Weymouth Harbour and Esplanade Flood and Coastal Risk Management Strategic Outline Case (Appendix 1) for submission to the Environment Agency’s Large Project Review Group. 2. Authorises officers to develop the Outline Business Case towards deliverable schemes for inclusion in Dorset Council’s future capital programme. 3. Authorises use of existing capital budget to deliver Outline Business Case.
Reason for Recommendation: Weymouth Town Centre and parts of the surrounding area are at risk of flooding and coastal erosion. With a projected acceleration in sea level rise and more intense weather events because of climate change, the problems facing Weymouth will increase significantly.
Without investment in managing this flood and erosion risk, Weymouth faces increasing direct losses through flooded assets and infrastructure and indirect impacts such as a failing property market due to blight and increasing social deprivation.
It is estimated that there are 400 businesses (based upon ONS figures) within the areas that are directly affected by future flood risk. The council are yet to develop a permanent solution to the objection in principle that the Environment Agency (EA) have to development in the flood zones around Weymouth Town Centre. Future development could create jobs within Weymouth and previous estimates have suggested this could be over 1000.
Dorset Council as: (i) The principal asset owner of harbour and seafront infrastructure, (ii) The Local Planning Authority, (iii) The defined Lead Local Flood Authority, and (iv) The Coast Protection Authority; needs to adopt a coherent plan for the long-term sustainable flood and coastal erosion risk management of Weymouth Harbour and the Esplanade.
1. Executive Summary The Weymouth Harbour & Esplanade Flood and Coastal Risk Management (FCRM) Strategic Outline Case (SOC) document (Appendix 1) sets out the five business cases: strategic, economic, commercial, financial and management at a strategic level. They are based upon the Weymouth Harbour and Esplanade FCRM Strategy document (Appendix 2) which was approved by Cabinet in October 2020. The SOC sets out a holistic way of tackling all sources of flooding in Weymouth including fluvial, coastal (tidal inundation and wave overtopping), surface water and groundwater. The approach is to undertake a comprehensive programme of wall replacement and wall raising around both the Harbour and Esplanade frontages. This will both reduce flood risk and replace deteriorating walls, some of which are already at the end of their design life. It is a phased and adaptive approach which provides the opportunity to keep under review several factors including rates of climate change, asset deterioration and changes in spatial planning needs and requirements.
The project team are hoping to gain approval to submit the SOC to the EA’s Large Project Review Group (LPRG), which looks at all projects which are projected to cost in excess of £10million, and to agree the funding process of the Outline Business Case (OBC) production. Table 1 below states the current programme to progress to OBC and then phase 1 of construction.
Activity Date
Strategic Outline Case – Submit to LPRG August 2021
Strategic Outline Case – LPRG Approval September 2021
Outline Business Case development 2021 – 2023
Outline Business Case – Submit to LPRG February 2023
Outline Business Case – Approval March 2023 Activity Date
Detailed Design & Consents Spring 2023 – Summer 2024
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Dorset Council Annual Report 2025 - 2026That the Dorset Council Annual Report for 2025-2026 be received and noted. Reason for the decision The annual report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.