Resolved
Decision To respond to a request to review the timing of meetings prior to the Dorset Council elections in May 2024 and to put into place proper arrangements for council committee meetings .
Audit and Governance Committee decided this item on Monday 13 November 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision To respond to a request to review the timing of meetings prior to the Dorset Council elections in May 2024 and to put into place proper arrangements for council committee meetings .
That committee considers the recommendations of the Task & Finish Group, taking into account the results of the members survey, and makes recommendations to Full Council in respect of the following timings in preparation for the Calendar of Meetings 2024/25:
(a) During the period of British Summer Time, Full Council meetings will be held at 6.30pm. (April, May, July & October) (b) During the period of Greenwich Mean Time, Full Council meetings will be held at 2pm. (December & February)
(c) During the period of British Summer Time, Cabinet will be held at 6.30pm. (April, May, June, July, September, October)
(d) During the period of Greenwich Mean Time Cabinet will be held at 2pm. (November, December, January, March)
(e) That all meetings of Audit & Governance Committee will be held at 6.30pm.
To respond to a request to review the timing of meetings prior to the Dorset Council elections in May 2024 and to put into place proper arrangements for council committee meetings.
1. Report
1.1The calendar of meetings is approved by Full Council each year to establish the date and time of each committee for the following municipal year. 1.2 Since the establishment of Dorset Council in 2019, most committee meetings are held at 10am at County Hall, Dorchester, except for Full Council which starts at 6.30pm. 1.3 At Full Council on 14 February 2023, councillors agreed to welcome a review and discussed the impact to the public and councillors when there were limited options to attend or take part at a committee meeting if they were working during the day. Equally, there were also concerns expressed at the meeting, that many councillors already had other commitments in the evenings, such as attendance at town and parish council meetings. 1.4 An informal Task and Finish Group was created with the following councillors:
Cllr Richard Biggs (Chairman of Audit and Governance Committee) Cllr Belinda Bawden (member of Audit and Governance Committee) Cllr Simon Christopher (member of Audit and Governance Committee) Cllr Barry Goringe (member of Audit and Governance Committee) Cllr Ryan Hope (member of Place and Resources Overview Committee) Cllr Robin Legg (member of Audit and Governance Committee) Cllr Valerie Pothecary (Chairman of the Council) Cllr Spencer Flower (Leader of the Council) Cllr William Trite (Vice-Chairman of the Council) 1.5 The Task and Finish Group met on 16 June 2023 and asked for a wide range of data to be collated to conduct and inform their review. This included information on the average attendance at meetings and the average duration of committee meetings, data from other “shire councils” and the results of the 2022/23 councillor survey on this topic.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Review of Timing of Committee MeetingsReport | 215 KB | DownloadRead as text |
Follow Audit and Governance Committee at Dorset and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Aug 2026 | Recruitment to the Independent Remuneration Panel Report- That support was sought from South-West Councils to fulfil the role of chair of the panel; - That an open recruitme... | Decided | Open |
| 3 Aug 2026 | Exempt BusinessThat the press and the public be excluded for the following item(s) in view of the likely disclosure of exempt inform... | Decided | Open |
| 27 Apr 2026 | Risk Management UpdateDecision - That the selected Strategic Risks and their associated risk appetites, as context for the committee’s cons... | Noted | Open |
| 27 Apr 2026 | Audit Actions Update ReportDecision - That the SWAP audit update provided in the report, including the detailed progress report at Appendix 1 be... | Noted | Open |
| 27 Apr 2026 | Corporate Complaints PolicyIt was agreed that a report would be brought back in six months to review the revised policy. Decision That the Audit... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.