Approved Planning

Planning Committee (CleS) approved this item on Monday 8 December 2008. Below is the council's own wording, with the papers it was decided on.

Item41

Resolved

“That the recommendation of the Development and Building Control Manager for approval in respect of the deferred application be agreed, subject to the following conditions: Extra 1. The development must be begun not later than the expiration of two years from the final approval of the reserved matters. In accordance with Section 92 of the Town and Country Planning Act 1990 (as amended by the Planning and Compulsory Purchase Act 2004). Extra 2. The development hereby approved shall be carried out wholly in accordance with the details contained in the application as submitted to the Council on the date specified in Part 1 of this decision notice and as amended on drawings received 19th August 2008; unless otherwise firstly approved in writing with the Local Planning Authority; in order to ensure the development is carried out in complete accordance with the approved plans. Extra 3. Notwithstanding any description of the materials in the application, no development shall be commenced until samples or precise details of the materials to be used in the construction of the external hard standings, walls and / or roofs of the buildings have been submitted to, and approved in writing by, the Local Planning Authority in order to ensure the satisfactory appearance of the development upon completion, in the interests of visual amenity and in accordance with Policy HP9 of the Chester-le-Street District Local Plan and Policy 8 of the Regional Spatial Strategy. Extra 4. The hereby approved development shall be carried out in accordance with a scheme of landscaping to be submitted to, and approved in writing by, the Local Planning Authority prior to the commencement of any development on site, and which scheme may provide for the planting of trees and / or shrubs (including species, sizes, numbers and densities), the provision of screen fences or walls, the movement of earth, the formation of banks or slopes, the seeding of land with grass, or other works for improving the appearance of the development. The works agreed to shall be carried out within the first planting season following completion of development of the site (or of that phase of development in the case of phased development) and shall thereafter be maintained for a period of 5 yrs following planting; in the interests of visual amenity, the satisfactory appearance of the development upon completion and in accordance with the provisions of Policy HP 9 and HP 17; of the Chester-le-Street District Local Plan. Extra 5. Notwithstanding the information submitted with the application for the duration of all construction works access shall be taken from Waldridge Lane only unless otherwise agreed in writing with the Local Planning Authority in the interests of highway safety and residential amenity in accordance with policies HP9 and T15 of the Chester-le-Street District Local Plan. Extra 6. Prior to development commencing a scheme for the management of construction traffic (to include an existing highway condition survey) on Waldridge Lane shall be submitted to and approved in writing by the Local Planning Authority and then implemented in accordance with the approved scheme unless otherwise agreed in writing, in the interests of highway safety and residential amenity in accordance with policies HP9 and T15 of the Chester-le-Street District Local Plan. Extra 7. No development approved by this permission shall be commenced until: a) the application site has been subjected to a detailed site investigation scheme for the investigation and recording of contamination and a report has been submitted to and approved by the LPA; b) should contamination be found, detailed proposals for the removal, containment or otherwise rendering harmless such contamination (the ‘contamination proposals’) have been submitted to and approved by the LPA; c) for each part of the development, contamination proposals relevant to that part (or any part that would be affected by the development) shall be carried out either before or during such development; d) if during development works any contamination should be encountered which was not previously identified and is derived from a different source and/or of a different type to those included in the contamination proposals then revised contamination proposals shall be submitted to the LPA; and e) if during development work, site contaminants are found in areas previously expected to be clean, then their remediation shall be carried out in line with the agreed contamination proposals. In accordance with Planning Policy Statement 23: 2004. Extra 8. The works to trees indicated on site plan (p)14 received 2nd June 2008 for retention and pruning shall be undertaken prior to works commencing in accordance with the recommendations of the Arboricultural Report dated March 2008 pages 10 and 11 section 5.0, Appendix 2A, 4 and 5 unless otherwise agreed in writing with the Local Planning Authority, in the interests of avoiding compaction of the roots for the long term health and well-being of the tree and in the interests of visual amenity to accord with the aims of Policy HP9 of the Chester-le-Street Local Plan. Extra 9. Post development but prior to occupation Schwegler woodcrete bat boxes shall be installed around the site in accordance with the recommendations in section 4.4 of the White Young Green Bat Survey unless otherwise agreed in writing with the Local Planning Authority in the interests of enhancing biodiversity and conservation interests in accordance with Planning Policy Statement 9 and policy 33 of the Regional Spatial Strategy. (4) Proposal: Proposed erection of 14 no houses with associated access road, driveways and landscaping Location: West Farm, Waldridge Lane, Waldridge, Chester-le-Street, Durham, DH2 2NQ Applicant: [name removed] - Holmside Construction Reference: 08/00227/FUL Councillor Ebbatson requested an additional condition be added to the approval restricting the hours of construction within the site, in the interests of sustainable development and existing residential properties in the area. The Development and Building Control Manager was in agreement and stated that similar conditions had been applied to similar forms of development in residential areas. He suggested that two extra conditions be added, with one condition to control the hours of construction and the other to require the developer to submit a methodology as how the site will be constructed. Councillor Davidson requested that a vote takes place to show whether Members were in agreement with the proposed extra condition. Members voted in favour of the additional conditions and the proposal was carried. In relation to the concerns raised by Councillor Westrip on the Health and Safety aspects of the site, the Development and Building Control Manager advised that the Health and Safety Executive were responsible for ensuring safety on a construction site and as the relevant statutory body they would deal with any breaches of Health and Safety law. Councillor Davidson advised that he was in support of the application as he felt the comments raised were not material planning considerations and proposed to move the Officers recommendation for approval. Councillor Nathan raised comments and expressed concern in relation to the following issues: The increase in traffic the proposal will bring along Waldridge Lane during the construction stage, which will be damaging for existing residents and local amenities. The increase in traffic the proposal will bring through the Meadow Drive/Poppyfields estate as the proposed access to the residential development. The applicants decision to build 14 houses rather than 15, which would lead to a requirement for social housing. The Development and Building Control Manager advised that Officers felt the existing Meadow Drive/Poppyfields estate would not be suitable for accommodating construction traffic, resulting in the use of Waldridge Lane during the construction stage and the future access for the development being proposed through the existing residential estate. In relation to Councillor Nathan’s comments on the alignment of the roads and footpaths of the Meadow Drive/Poppyfields estate, he stated that Highway Officers were of the opinion that the road and pavement capacity already in place would be perfectly adequate to accommodate the extra dwellings proposed and the Planning Matters report provided details of a number of existing estates within the Chester West and Chester South wards with similar estate layouts. In relation to a comment made by Councillor P May on the possibility of an access road between the two developments, the Development and Building Control Manager advised that any planning permission given by this planning authority would be based on the detailed plans submitted by the developer and in this case the plans show only a pedestrian link between the two sites. He stated that if the developer intended providing an access road through the estate, he would be required to submit a new planning application to the authority, as the plans would no longer correspond to the permission. Councillor Ebbatson queried whether an additional condition should be included in the approval stating that the proposed radii at the access to Whitehill Way must be altered to accommodate to the construction traffic. The Highways Officer advised that there would be cost attached to creating and removing the proposed road alterations to Waldridge Lane, which the developer would be required to fund. He stated that if the alterations were carried out to a robust permanent standard, then it would be their intention to leave the alterations in place rather than ask the developer to remove them once construction of the proposal had taken place. The Development and Building Control Manager suggested re-wording extra condition 16 of the approval to state that a scheme for the management of construction traffic is to include an existing highway condition report and realignment of the radii on Whitehill Way and that unless the County Council were willing to fund the improvements, then it would be for the developer to finance. Discussion ensued in relation to the specific inclusion of the road alterations scheme as part of extra condition 16. The Highway Officer advised that the current phrasing of extra condition 5 and 6 allow for any yet unspecified improvement measures along Waldridge Lane as well as the previously identified radii improvement, however if Planning Officers felt the alterations should be specifically included as part of the recommended conditions then he would support their decision. Councillors M May and Nathan were of the opinion that the surface improvement of Waldridge Lane would detract from the character and the beauty of the area. Councillor Nathan raised further concerns in relation to suitability of Waldridge Lane for construction traffic, the security of local residents, the pedestrian link between the two developments and the suitability of Heathfields as the access road for the development, and because of this he did not support this application. Councillor Gollan spoke in relation to extra condition 13 in the recommendations and queried whether this condition could be reinforced to prevent a scheme being submitted which was less than the target of 10 percent decentralised and renewable energy or low carbon sources in the development. The Development and Building Control Manager advised that the Regional Spatial Strategy (RSS) specifies that a local authority must set a target of at least 10 percent when securing schemes to minimise energy consumption within a development, which would be non negotiable. He stated that since the RSS had been put in force by the authority, a number of schemes, which met the 10 percent requirement, had been secured and he felt optimistic that a similar scheme could be secured with this development. Further to Councillor Davidson proposal to accept the Officers’ recommendation for approval, Councillor Westrip stated that as the police and highways authority had not raised any objections in relation to the proposal he felt it would be difficult to refuse the application and seconded the Officers’ recommendation for approval. This proposal was carried. “That the recommendation of the Development and Building Control Manager for approval in respect of the deferred application be agreed, subject to the following conditions: Extra 1. The development must be begun not later than the expiration of three years from the date of this permission, in order to prevent the accumulation of unused planning permissions as required by Section 91 of the Town and Country Planning Act 1990 (as amended). Extra 2. The development hereby approved shall be carried out wholly in accordance with the details contained in the application as submitted to the Council on the date specified in Part 1 of this decision notice and as amended on 19th August 2008; unless otherwise firstly approved in writing with the Local Planning Authority; in order to ensure the development is carried out in complete accordance with the approved plans. Extra 3. Notwithstanding any description of the materials in the application, no development shall be commenced until samples or precise details of the materials to be used in the construction of the external hard standings, walls and / or roofs of the buildings have been submitted to, and approved in writing by, the Local Planning Authority in order to ensure the satisfactory appearance of the development upon completion, in the interests of visual amenity and in accordance with the provisions of Policy HP9 of the Chester-le-Street District Local Plan. Extra 4. Notwithstanding the details shown on the hereby approved plans and elevations, full details of all means of enclosure of the site (including any internal means of enclosure to sub-divide individual plots) shall be submitted to, and approved in writing by, the Local Planning Authority prior to the commencement of any development on site in order to ensure the satisfactory appearance of the development upon completion, in the interests of visual and residential amenity and in accordance with the provisions of Policy HP9 of the Chester-le-Street District Local Plan. Extra 5. The hereby approved development shall be carried out in accordance with a scheme of landscaping to be submitted to, and approved in writing by, the Local Planning Authority prior to the commencement of any development on site, and which scheme may provide for the planting of trees and / or shrubs (including species, sizes, numbers and densities), the provision of screen fences or walls, the movement of earth, the formation of banks or slopes, the seeding of land with grass, or other works for improving the appearance of the development. The works agreed to shall be carried out within the first planting season following completion of development of the site (or of that phase of development in the case of phased development) and shall thereafter be maintained for a period of 5 yrs following planting; in the interests of visual amenity, the satisfactory appearance of the development upon completion and in accordance with the provisions of Policy HP 9 and HP 17; of the Chester-le-Street District Local Plan. Extra 6. Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (or any Order revoking and / or re-enacting that Order with or without modification), no walls, fences, palisades or other means of enclosure shall be erected forward of the main front (or side in the case of corner sites) walls of dwellings, in order to ensure the satisfactory appearance of the development upon completion in the interests of visual amenity and the preservation of the open-plan character and appearance of the development in accordance with Policy HP9 of the Chester-le-Street District Local Plan and Policy 8 of the Regional Spatial Strategy (NE). Extra 7. No development approved by this permission shall be commenced until: a) the application site has been subjected to a detailed site investigation report for the investigation and recording of contamination and has been submitted to and approved by the LPA; b) should contamination be found, detailed proposals for the removal, containment or otherwise rendering harmless such contamination (the ‘contamination proposals’) have been submitted to and approved by the LPA; c) for each part of the development, contamination proposals relevant to that part (or any part that would be affected by the development) shall be carried out either before or during such development; d) if during development works any contamination should be encountered which was not previously identified and is derived from a different source and/or of a different type to those included in the contamination proposals then revised contamination proposals shall be submitted to the LPA; and e) if during development work, site contaminants are found in areas previously expected to be clean, then their remediation shall be carried out in line with the agreed contamination proposals. In accordance with Planning Policy Statement 23: 2004. Extra 8. The works to trees indicated on site plan (p)09 received 2nd June 2008 for retention and pruning shall be undertaken prior to works commencing in accordance with the recommendations of the Arboricultural Report dated March 2008 pages 10 and 11 section 5.0, Appendix 2A, 4 and 5 unless otherwise agreed in writing with the Local Planning Authority, in the interests of avoiding compaction of the roots for the long term health and well-being of the trees and in the interests of visual amenity to accord with the aims of Policy HP9 of the Chester-le-Street Local Plan. Extra 9. Prior to occupation of the dwellings hereby approved, Schwegler woodcrete bat boxes shall be installed around the site in accordance with the recommendations in section 4.4 of the White Young Green Bat Survey unless otherwise agreed in writing with the Local Planning Authority in the interests of enhancing biodiversity and conservation interests in accordance with Planning Policy Statement 9 and policy 33 of the Regional Spatial Strategy. Extra 10. The development hereby permitted by this planning permission shall not be initiated by the undertaking of a material operation as defined in Section 56(4)(a)-(d) of the Town and Country Planning Act 1990 until arrangements have been made to secure the provision of adequate open space for sporting use within the locality in accordance with a detailed scheme, which has first been submitted to and approved in writing by the Local Planning Authority. In order to ensure the development makes adequate provision for recreational and open space facilities and to comply with the aims of Policies HP 9 and RL 5 of the Local Plan 2003. Extra 11. The development hereby permitted by this planning permission shall not be initiated by the undertaking of a material operation as defined in Section 56(4)(a)-(d) of the Town and Country Planning Act 1990 until arrangements have been made to secure the provision of adequate public artwork provision within the locality in accordance with a detailed scheme, which has first been submitted to and approved in writing by the Local Planning Authority. In order to ensure the development makes adequate provision for public artwork provision to comply with the aims of Policy BE 2 of the Local Plan 2003. Extra 12. Prior to development commencing a scheme to provide an anti motorcycle access facility and associated fencing/railings along the central foo
Word for word from the decision Durham published for this meeting. Source: democracy.durham.gov.uk

Follow this further

Built from Durham's papers

Papers for this item

Kept in our archive, download once signed in

No papers were published with this item. The decision above is the council's full record of it.

At this meeting

Whole meeting

On this subject at Durham

Search all
  1. Planning MattersThis decision
  2. Planning MattersApproved
  3. Planning MattersApproved
  4. Planning applications - county mattersApproved
  5. Planning MattersApproved
  6. Planning MattersApproved

More from Durham Planning Committee (CleS)

All decisions
MeetingDecisionOutcome
30 Mar 2009 Planning Matters“That the recommendations of the Development and Building Control Manager for approval in respect of the application ... Approved Open
9 Mar 2009 Minutes of Previous Meeting held 9 February 2009“That the Minutes of the proceedings of the Meeting of the Committee held 9 February 2009, copies of which had previo... Decided Open
9 Mar 2009 Planning Matters“That the recommendations of the Development and Building Control Manager for approval in respect of the application ... Approved Open
9 Feb 2009 Minutes of Previous Meeting held 19 January 2009“That the Minutes of the proceedings of the Meeting of the Committee held 19 January 2009, copies of which had previo... Decided Open
9 Feb 2009 Planning Matters“That notwithstanding the Officer’s recommendation of conditional approval, the application be refused for the follow... Approved Open