What was decided
The committee noted the progress made in delivering the 2024/25 annual business plan.
The committee noted the status of mitigation measures and explanations given for delays and revised completion dates.
Why
Staffing capacity was strengthened during 2025, with the Devon Loves Dogs post expanded and new coordinator roles filled. Report P5, P6
Survey work advanced, with a large visitor survey initiated and a petalwort monitoring contract awarded. Report P8, P16
On site works progressed, including protective fencing at Dawlish Warren and a redesign of site signage. Report P14, P18
What happens next
The South East Devon Visitor Survey continues online and face to face until April 2026. Report P8
The petalwort translocation survey is rescheduled for November 2025 when conditions should be wetter. Report P16
Installation of new signage at Dawlish Warren is expected by the end of 2025. Report P14
Options considered
- Chosen: Use the Exeter Port Authority RIB vessel for the Exe Estuary patrol boat pilot. Approved by the committee in July 2025 as a revised approach Report P10
- Rejected: Proceed with the original patrol boat proposal. Approach was amended to use the RIB vessel instead Report P10
Implications
- Staffing: The Devon Loves Dogs Coordinator post rose from 0.5 FTE to 0.8 FTE in January 2025, and a two year fixed term Assistant Coordinator joined in August. Report P5
- Risk: Full deployment of the patrol boat is on hold until insurance cover is confirmed. Report P10
- Environment: Hedge planting at the Imperial Recreation Ground, Exmouth, remains on hold until revetment repairs are completed. Report P12
- Financial: A grant funding application will be needed to cover more extensive revetment repairs at Exmouth. Report P12
Who and where
- Habitats at Dawlish Warren, where new fencing directs visitors away from sensitive zones Report P18
- Visitors to South East Devon, who will see new signage and may be surveyed Report P8, P14
- Users of the Imperial Recreation Ground, Exmouth, awaiting hedge planting Report P12
- The Devon Loves Dogs team, with expanded coordinator capacity Report P5
Timeline
- January 2025: Devon Loves Dogs post expanded from 0.5 FTE to 0.8 FTE Report P5
- March 2025: South East Devon Visitor Survey programme initiated Report P8
- March 2025: Signage redesign tender concluded; contract awarded to The Way Design Report P14
- May 2025: Visitor survey launched online and face to face Report P8
- May 2025: First petalwort translocation survey cancelled due to dry weather Report P16
- July 2025: New SANGs and Infrastructure Projects Coordination Officer began work Report P6
- July 2025: Use of Exeter Port Authority RIB vessel approved by the committee Report P10
- August 2025: Assistant Project Coordinator took up post on a two year fixed term contract Report P5
- November 2025: Petalwort translocation survey rescheduled Report P16
- End of 2025: New signage installation at Dawlish Warren expected Report P14
- April 2026: South East Devon Visitor Survey expected to conclude Report P8
Plain English for the jargon
- SANGs: Suitable Alternative Natural Greenspaces, green areas provided to draw visitors away from sensitive habitats
- FTE: Full Time Equivalent, a measure of staff capacity
- HREC: Habitat Regulations Executive Committee, the joint committee overseeing the work
- RIB: Rigid Inflatable Boat, the type of vessel now proposed for the estuary patrol
- Petalwort: A small plant species whose translocation site is being monitored