East Devon District Council

2025-26 Annual Business Plan and 5 Year Delivery Plan

Approved Executive 2 papers

AI summarySouth and East Devon Habitat Regulations Executive Committee approved the 2025-26 Annual Business Plan and updated 5 Year Delivery Plan, with £100,000 for Dawlish Warren visitor centre interpretation, new warden posts, and other mitigation works.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved2025-26 Annual Business Plan and updated 5 Year Delivery Plan approved
Money£100,000 largest itemDawlish Warren visitor centre and gateway interpretation
What happens nextProgress report in October 2026Further report on delivery of 2025-26 ABP to come back to committee
Who it affectsSouth East Devon wildlife mitigation areaExe Estuary, Pebblebed Heaths, Dawlish Warren and visitors

What was decided

The Executive Committee approved the 2025-26 Annual Business Plan, including the commitments and actions set out in Appendix A. Report 1.1, 1.2

The Committee noted the updated 5 Year Delivery Plan also contained in Appendix A. Report 1.2, 1.3

A further progress report on the 2025-26 Annual Business Plan will be received in October 2026.

Why

The plan follows the updated South East Devon Wildlife Joint Habitats Mitigation Strategy approved by all partner authorities, with measures prioritised by the Habitat Regulations Delivery Manager and Officer Working Group. Report 1.4, 1.5

The recommendations target investment in staffing, vehicles, operational budgets, site-based management and monitoring to strengthen mitigation delivery across the region. Report 1.6, P7

Staffing is recommended to be expanded because warden cover of around 27km of Exe Estuary shoreline and 1,600ha of heaths and Dawlish Warren is currently stretched, especially when only one warden is in post. Report 2.1, 2.2, 2.3, 2.4

What happens next

A progress report on delivery of the 2025-26 Annual Business Plan will come back to the Executive Committee in October 2026.

Two new fixed-term posts (Team Leader Wildlife Wardens and Wildlife Warden) and a hybrid vehicle are to be taken forward as part of the plan. Report 2.5, 2.6, 3.2, 3.3

A monitoring strategy, refresh of Exe Codes of Conduct, No BBQ banner redesign, schools resource review, buoy repairs, signage, dog bins and dog walking review are all to be progressed in 2025-26. Report 4.1, 5.3, 6.2, 7.3, 9.2, 10.1, 14.3, 15.4

The money

  • £49,000 Team Leader Wildlife Wardens, 1 FT 2-year fixed term (includes base salary, NI, superannuation and support costs) Report 2.5, P17, P29
  • £45,000 Wildlife Warden, 1 FTE 2-year fixed term (includes base salary, NI, superannuation and support costs) Report 2.6, P17, P29
  • £26,000 Additional warden vehicle (purchase, livery, insurance, fuel) Report P24, P25
  • £7,500 Devon Loves Dogs operations and development Report P24, P25
  • £3,000 Wildlife Wardens operations and development Report P24, P25
  • £7,000 Production of monitoring strategy Report P31
  • £3,000 Exe Codes of Conduct updates, reprints and distribution Report 5.3, P36
  • £4,000 Redesign and print of No BBQ campaign banners for Dawlish Warren Report 6.2, P41
  • £5,000 Review of existing education work and production of new educational materials Report 7.3, P46
  • £7,500 Shared use of the Exeter Port Authority RIB (approved at July 2025 meeting) Report 8.1, P49
  • £10,000 Repair, realignment and replacement of Exe wildlife refuge buoys Report 9.2, P53
  • £5,000 New or redesigned banners for campaigns on the Exe Estuary Report 10.2, P57
  • £250 Vantage point count resources Report 11.3, P63
  • £100,000 Visitor centre and gateway interpretation at Dawlish Warren Report 12.5, P70
  • £3,500 Chestnut paling fencing at Dawlish Warren to protect habitat from trampling Report 10.1, P74
  • £4,000 Additional dog bins on the Pebblebed Heaths Report 14.3, P79
  • £15,000 Review of dog walking management on the Pebblebed Heaths Report 15.4, P86
  • £15,000 Fire Strategy work for the Pebblebed Heaths Report 16.2, P90
  • £250 Monitoring support (e.g. mileage for volunteers) on the Pebblebed Heaths Report 17.2, P94

Options considered

  • Chosen: Approve the 2025-26 Annual Business Plan and 5 Year Delivery Plan. The plan follows the updated South East Devon Wildlife Joint Habitats Mitigation Strategy and was agreed by the Officer Working Group. Report 1.1, 1.4
  • Chosen: Purchase the new warden vehicle outright as a hybrid. Replacing vehicles every 10 to 15 years offers better long-term value than leasing and allows future resale. Report 3.2, 3.3
  • Chosen: Use consultancy support to design an integrated monitoring programme. Embeds efficient monitoring within the mitigation strategy to support evidence-based decision-making. Report 4.2

Implications

  • Staffing: Two new fixed-term posts are recommended: a Team Leader for Wildlife Wardens at £49,000 and a Wildlife Warden at £45,000, each for 2 years. Report 2.5, 2.6, P17
  • Financial: The plan proposes a new vehicle purchase, additional dog bins, fencing, banners, signage, refuge buoy repairs, and a £100,000 investment in Dawlish Warren visitor centre interpretation. Report 3.2, 12.5, P70, P79
  • Climate: Fire is identified as an increasing threat to the Pebblebed Heaths in the context of climate change, prompting £15,000 of consultancy work on fire strategy. Report 16.1, 16.2, P90
  • Risk: The plan flags reputational and ecological risks around dog management on the Pebblebed Heaths and proposes a £15,000 evidence-based review. Report 15.1, 15.4, P86
  • Equalities: Visitor centre redesign, gateway signage and educational materials are intended to make information available without always requiring staff present and to reach wider audiences including schools. Report 7.1, 12.4, P46, P70
  • Other: The plan aims to shift perceptions of Dawlish Warren from a recreation or dog walking area to a recognised nature reserve, supporting Special Area of Conservation protection. Report 12.3, 12.5

Who and where

  • Visitors to the Exe Estuary, Pebblebed Heaths and Dawlish Warren Report 1.6, 12.3, P70
  • Dog walkers on the Pebblebed Heaths and Dawlish Warren Report 14.3, 15.1, P86
  • Water users on the Exe Estuary, including canoeists, paddleboarders and walkers Report 9.1, 10.1
  • Schools and young people receiving new educational materials on the Exe Estuary Report 7.1, 7.3, P46
  • Partner authorities in the South East Devon Wildlife Joint Habitats Mitigation Strategy, including East Devon District Council, Teignbridge District Council, Exeter City Council and Devon County Council Report 1.4, P96
  • Wildlife wardens and Devon Loves Dogs staff, including new Team Leader and Wildlife Warden posts Report 2.5, 2.6, P9
  • The Exe Estuary Management Partnership, Pebblebed Heaths Conservation Trust, RSPB, DWT and Natural England Report 5.1, 14.3, 16.3, P98

Timeline

  • 2018: Exe Estuary Codes of Conduct originally developed by EEMP on behalf of SEDW Report 5.1
  • 2021: Three-year Exe Estuary Wildlife Refuge Monitoring Programme began, including vantage point counts Report 11.1, P58
  • July 2025: Executive Committee approved £7,500 for trial shared use of the EPA RIB Report 8.1, P49
  • Summer 2025: Warmest summer on record for the UK, increasing fire threat to the Pebblebed Heaths Report 16.1
  • September 2025: Interactive review of Exe Codes of Conduct held at EEMP winter forum Report 5.2
  • 30 October 2025: Executive Committee approved the 2025-26 Annual Business Plan and noted the updated 5 Year Delivery Plan Report P95
  • 2026-31: Later years of the 5 Year Delivery Plan depend on the success of existing projects such as the Exe Estuary wildlife refuges and are indicative Report 1.3
  • October 2026: Further report on progress with the 2025-26 Annual Business Plan to be received

Plain English for the jargon

  • ABP: Annual Business Plan, the list of key projects for delivery over the next 12 months.
  • OWG: Officer Working Group, the group that agreed the recommended projects.
  • SEDW: South East Devon Wildlife, the partnership running the Joint Habitats Mitigation Strategy.
  • EEMP: Exe Estuary Management Partnership.
  • DLD: Devon Loves Dogs, a scheme promoting responsible dog walking on the heaths.
  • EPA: Exeter Port Authority, whose RIB is to be shared with the Wildlife Warden team.
  • RIB: Rigid Inflatable Boat.
  • SAC: Special Area of Conservation, a European wildlife protection designation.
  • VPC: Vantage Point Count, a snapshot bird and activity monitoring method on the Exe Estuary.
  • SANG: Suitable Alternative Natural Greenspace, used to reduce pressure on protected sites.
  • NNR: National Nature Reserve, the designation for the Pebblebed Heaths.
  • FTE: Full Time Equivalent, used to describe warden staffing levels.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item18

Resolved

RESOLVED that the Executive Committee: 1. Approves the 2025 – 26 Annual Business Plan (Appendix A in the report) and the commitments and actions set out therein; 2. Notes the updated 5 Year Delivery Plan also shown in Appendix A; 3. Received a further report detailing progress with the 2025 – 26 Annual Business Plan in October 2026.
Word for word from the decision East Devon published for this meeting. Source: democracy.eastdevon.gov.uk

Follow this further

Built from East Devon's papers

What the report saysPro

Report to South and East Devon Habitat Regulations Executive Committee

Summary

1.1This paper outlines key projects recommended for delivery over the next 12 months by the Habitat Regulations Delivery Manager, agreed by the Officer Working Group (OWG). These are listed in Appendix A as the 2025-26 Annual Business Plan (ABP).

1.2The ABP is part of an updated 5-year delivery plan, also in Appendix A, which provides a budget and project timeline for the short and medium term.

1.3Some measures in the 5-year plan, especially those for 2026-31, depend on the success of existing projects, such as the Exe Estuary wildlife refuges, and should be viewed as an indicative guide.

1.4The South East Devon Wildlife – Joint Habitats Mitigation Strategy has been approved by all partner authorities. As such, the measures recommended for delivery in the 2025-26 ABP follow the direction laid out in the updated mitigation strategy and as prioritised by the Habitat Regulations Delivery Manager and OWG.

1.5Analysis has been undertaken to assess the partnership’s financial position, allocate funds in line with the updated strategy, and identify the implications for setting appropriate planning obligations across the region. The findings are reported separately.1

1 2025 Financial report.

2025/26 Annual Business Plan / 5Yr Delivery Plan 1.6 In line with the approved Strategy, this report recommends targeted investment in staffing, vehicles, operational budgets, site-based management measures, and monitoring to strengthen the delivery of mitigation across the region. The proposals build on recent progress by ensuring sufficient staff capacity, supporting operational effectiveness, and enhancing visitor engagement and habitat protection.

1.6A balance of investment in people, infrastructure, and site-specific interventions will enable the partnership to deliver measurable outcomes and adapt to ongoing pressures.

2. Wildlife Wardens staff resource.

2.1Wildlife wardens play a vital dual role, combining on -the-ground ranger duties with awareness-raising and community engagement. They patrol in pairs for health and safety, which ensures effective coverage, though this does limit the overall area they can cover at any one time. In recent years there have been lengthy periods of time where only one wildlife warden has been in post and this has required other staff (e.g. delivery manager) to join them on patrols at least 1 day per week, taking time away from other duties.

2.2The wardens need to cover around 27km of shoreline along the Exe Estuary plus an area of around 1,600ha (the combined area of the East Devon Heaths and Dawlish Warren). There is clear scope to expand the warden team to provide better coverage.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2025-26 Annual Business Plan and 5 Year Delivery PlanReport 209 KB DownloadRead as text
PDF
HREC: 2025-26 Annual Business Plan and 5Yr Delivery Plan: Appendix AAppendix 162 KB Download

At this meeting

Whole meeting

Who was there

3 of 10 attended
GJ
Councillor Geoff JungChair, present
RW
Councillor Ruth WilliamsCommittee Member, present
GT
Councillor Gary TaylorCommittee Member, present
SE
Sama EuridgeOfficer, apologies
CS
Claire SpenceOfficer, apologies
MD
Matthew DiamondOfficer, in attendance
NH
Neil HarrisOfficer, in attendance
RH
Rebecca HealOfficer, in attendance
DM
Debbie MeakinOfficer, in attendance
PO
Paul OsborneOfficer, in attendance

On this subject at East Devon

Search all
  1. 2025-26 Annual Business Plan and 5 Year Delivery PlanThis decision
  2. Recommendation from Strata Joint Executive Committee - Strata Business Plan 2026/2027Approved
  3. Adoption of Exmouth Placemaking Plan and Strategic Outline Business CaseApproved
  4. 2024-25 Annual Business Plan - Annual reportDecided
  5. Housing Revenue Account Business Plan updateNoted
  6. Strata Business Plan 2025/2026Approved

More from East Devon South and East Devon Habitat Regulations Executive Committee

All decisions
MeetingDecisionOutcome
30 Oct 2025 2024-25 Annual Business Plan - Annual reportRESOLVED that the Executive Committee: Notes the progress made in delivering the 2024/25 annual business plan . Notes... Decided Open
30 Oct 2025 Habitat Mitigation Team updateRESOLVED that the Executive Committee note the update. Noted Open
30 Oct 2025 Communications reportRESOLVED that the Executive Committee note the results of the communications report for the period of September 2024 ... Noted Open
30 Oct 2025 Finance reportRESOLVED that the Executive Committee: 1. Notes the update on the overall financial position including contributions ... Decided Open
30 Oct 2025 Risk Register reportRESOLVED that the Executive Committee: 1. Notes the identification, categorisation and prioritisation of risks as rec... Decided Open