AI summaryHabitat mitigation partnership agrees revised per-dwelling developer contribution rates and updates partner authorities on five-year finances, with partner councils asked to match new index-linked tariffs.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecided
Money£4,867,164 balance to 31/03/25Of £10,284,268 received and £5,417,104 spent on mitigation
What happens nextPartner authorities to update planning obligationsNew SANG Delivery Plan to come to a future Executive Committee meeting
Who it affectsNot stated

What was decided

The Executive Committee noted the overall financial position of developer contributions received, spent and anticipated under signed Section 106 and CIL agreements. Report P2

The Committee noted the assessment apportioning funds under the updated Strategy and agreed the revised planning obligation contribution rates in Table 2 of the report. Report P2

Partner authorities were asked to revise planning obligations for habitat regulations mitigation contributions to the rates in Table 2, index-linked each year. Report P2

Why

Officers said appropriate and sufficient funding is needed to ensure sustainable delivery of habitat mitigation in the short, medium and long term, and a new Strategy has set revised costs. Report P5, 1.3

Because the 'All sites' category represents 93% of total costs, allocating existing funds to match it directly could have compromised on-site mitigation, so a phased approach was recommended instead. Report 2.2, 2.3

Tariffs are reviewed annually to account for inflation, administrative costs, and changes in housing delivery or mitigation costs. Report 1.3

What happens next

Partner authorities will be asked to revise their planning obligation tariffs to match the updated per-dwelling figures and apply annual index-linking. Report P2

A new SANG Delivery Plan, being developed by the partner authorities, will be presented at a future Executive Committee meeting. Report P10

The five-year strategy review will provide a further opportunity to revisit planning obligations and funding allocations.

The money

  • £10,284,268 Total developer contributions received to 31/03/25 across SANGS, Dawlish Warren, Exe Estuary, Pebblebed Heaths and EDDC CIL Report P22
  • -£5,417,104 Total mitigation expenditure to 31/03/25 across all categories Report P22
  • £4,867,164 Balance remaining on account to 31/03/25 Report P22
  • £769.64 Updated per-dwelling SAMM contribution for the 'All sites' cost category Report P32
  • £20.77 Updated per-dwelling SAMM contribution for the Exe Estuary category Report P32
  • £35.00 Updated per-dwelling SAMM contribution for the Pebblebed Heaths category Report P32
  • £50.26 Updated per-dwelling SAMM contribution for the Dawlish Warren category Report P32
  • £3,078,008 Forecast total SAMM income 2025-30 across all categories Report P35
  • £3,341,127 Recommended total SAMM expenditure 2025-30 across all categories Report P44
  • £1,909,428 Projected remaining balance of funds at end of 2029-30 across all categories Report P45

Options considered

  • Rejected: Map all existing funds directly to the four new Strategy cost categories in proportion to their share of total costs. Would risk compromising delivery of on-site mitigation because the 'All sites' category represents 93% of total costs Report 2.2
  • Chosen: Reserve existing site-specific funds first to cover five-year business plan costs (plus 15% contingency) for each protected site, then allocate any remainder to 'All sites'. Ensures delivery of on-site mitigation over the plan period, with 'All sites' already sufficiently funded for at least five years Report 2.3
  • Rejected: Continue the previous practice of including a proportionate 'All sites' allocation within each site-specific contribution. New funding allocation method provides transparent continuity while letting site-specific funds be used first on those sites Report P30

Implications

  • Financial: Developer contribution tariffs across the partner authorities will change, with new per-dwelling rates index-linked annually to cover inflation and cost changes. Report P2, 1.3, P32
  • Financial: Forecast income of £3,078,008 over five years is expected to fall short of recommended expenditure of £3,341,127, leaving a projected £1,909,428 balance at end of 2029-30. Report P35, P44, P45
  • Risk: Officers rated the risk of this report as high, mainly because of the risk that some approved applications will be withdrawn or expire before contributions are paid. Report P4, 1.8
  • Legal: Planning obligations must continue to be worded so that funds can be shifted between cost categories and later rebalanced, provided their terms are honoured. Report 2.7, 2.8
  • Equalities: The equalities impact of the report is assessed as low. Report P3
  • Other: SANG costs and income are not included in the current forecast because the new SANG Delivery Plan is still being developed and will be reported separately. Report P10

Who and where

  • Developers building new homes in the South East Devon partnership area, who will pay the revised per-dwelling SAMM contributions Report P32
  • The partner authorities (including East Devon District Council and Teignbridge) that collect and apportion developer contributions Report 1.1, 1.10
  • Natural England and other consultees, who have been given sight of the report Report P54
  • Ward councillors sitting on the South and East Devon Habitat Regulations Executive Committee

Timeline

  • 31/03/25: Cut-off date for contributions received and expenditure shown in Table 1 Report P19, P20
  • October 2025: Finance report presented to the Executive Committee and decisions taken Report P52
  • 2025-26: First year of the recommended SAMM expenditure, totalling £645,640 Report P42
  • 2026-27: Year two recommended SAMM expenditure, totalling £706,166 Report P42
  • 2027-28: Year three recommended SAMM expenditure, totalling £660,883 Report P42
  • 2028-29: Year four recommended SAMM expenditure, totalling £648,325 Report P42
  • 2029-30: Year five recommended SAMM expenditure, totalling £680,113, with projected closing balance of £1,909,428 Report P43, P45
  • Future meeting of the Executive Committee: New SANG Delivery Plan to be presented once developed Report P10

Plain English for the jargon

  • SAMM: Strategic Access Management and Monitoring: measures that manage visitor access to protected wildlife sites to reduce recreational impact.
  • SANG: Suitable Alternative Natural Greenspace: open space provided as an alternative recreational destination to draw visitors away from protected sites.
  • S106: Section 106 of the Town and Country Planning Act 1990: legal agreements used to secure developer contributions for site-specific mitigation.
  • CIL: Community Infrastructure Levy: a fixed charge that local authorities can levy on new development to fund infrastructure.
  • HELAA: Housing and Economic Land Availability Assessment: the joint method used by the partner authorities to forecast housing delivery rates.
  • HIF: Housing Infrastructure Fund grant from Homes England used for the Ridgetop Park SANG in SW Exeter.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17

Resolved

RESOLVED that the Executive Committee: 1. Notes the update on the overall financial position including contributions received, expenditure and anticipated contributions (from signed S106 and CIL ); 2. Notes the assessment of the partnership’s financial position, apportioning of those funds in line with the updated strategy and identification of the appropriate planning obligation contribution rates across the region; 3. Requests the partner authorities to revise planning obligations for habitat regulations mitigation contributions to match those shown in Table 2 of the report, index-linked on an annual basis.
Word for word from the decision East Devon published for this meeting. Source: democracy.eastdevon.gov.uk

Follow this further

Built from East Devon's papers

What the report saysPro

Report to South and East Devon Habitat Regulations Executive Committee

Recommendations

It is proposed that the Executive Committee:

1. Notes the update on the overall financial position including contributions received, expenditure and anticipated contributions (from signed S106 and CIL). 2. Notes the assessment of the partnership’s financial position, apportioning of those funds in line with the updated strategy and identification of the appropriate planning obligation contribution rates across the region. 3. Requests the partner authorities to revise planning obligations for habitat regulations mitigation contributions to match those shown in Table 2, index- linked on an annual basis.

Equalities impact: Low

Risk: High

This is an update, repeated annually, on the current financial position of developer contributions (both collected and anticipated) for Habitat Regulations mitigation across the three partner authorities. It is important that appropriate and sufficient funding is collected in order to ensure sustainable delivery of mitigation in the short, medium and long term.

Summary

1.1The purpose of this report is to update members of the Executive Committee on the overall financial position of developer contributions received by the partner authorities as mitigation payments towards measures identified in the South East Devon Wildlife – Joint Habitats Sites Mitigation Strategy1 (“the Strategy”).

1.2The report sets out details of the contributions received from inception to date and anticipated income from contributions where planning permission has been granted but the contribution has not yet been paid.

1.3With the adoption of the new Strategy, revised costs for the Strategic Access Management and Monitoring (SAMM) mitigation measures have been identified and the partnership’s financial position assessed. Adjustments to developer contributions are recommended (considering current reserves), and the tariffs should be reviewed annually to account for inflation, administrative costs, and any changes in costs or housing delivery.

1 Link to the document can be found on the homepage at www.southeastdevonwildlife.org.uk

Finance Report October 2025 1.4 Revised costs for Suitable Alternative Natural Greenspace (SANG) will be set out in the new SANG Delivery Plan, currently being developed by the partner authorities. The plan will be presented at a future meeting of the Executive Committee. As SANG delivery is funded through the Community Infrastructure Levy (CIL), the Delivery Plan will affect future SANG income forecasts. As the plan is not finalised, it is not yet possible to include SANG income in the forecast shown in Table 3 below.

1.5Updated housing forecasting/SAMM income has been made available from each partner authority and are reported below in Table 3. These projections have also been used to assist in outlining the indicative 5 year Delivery Plan, reported separately2.

1.6In order to maintain consistency as far as possible with the Housing and Economic Land Availability Assessment (HELAA) methodology of forecasting income, amounts expected from signed planning obligations are now included within the forecast figures.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Finance reportReport 262 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 10 attended
GJ
Councillor Geoff JungChair, present
RW
Councillor Ruth WilliamsCommittee Member, present
GT
Councillor Gary TaylorCommittee Member, present
SE
Sama EuridgeOfficer, apologies
CS
Claire SpenceOfficer, apologies
MD
Matthew DiamondOfficer, in attendance
NH
Neil HarrisOfficer, in attendance
RH
Rebecca HealOfficer, in attendance
DM
Debbie MeakinOfficer, in attendance
PO
Paul OsborneOfficer, in attendance

On this subject at East Devon

Search all
  1. Finance reportThis decision
  2. Finance reportNoted
  3. Finance Report: Agency and Consultant Expenditure for 2023/2024 and 2024/2025Agreed
  4. Finance reportDecided

More from East Devon South and East Devon Habitat Regulations Executive Committee

All decisions
MeetingDecisionOutcome
30 Oct 2025 2024-25 Annual Business Plan - Annual reportRESOLVED that the Executive Committee: Notes the progress made in delivering the 2024/25 annual business plan . Notes... Decided Open
30 Oct 2025 Habitat Mitigation Team updateRESOLVED that the Executive Committee note the update. Noted Open
30 Oct 2025 Communications reportRESOLVED that the Executive Committee note the results of the communications report for the period of September 2024 ... Noted Open
30 Oct 2025 2025-26 Annual Business Plan and 5 Year Delivery PlanRESOLVED that the Executive Committee: 1. Approves the 2025 – 26 Annual Business Plan (Appendix A in the report) and ... Approved Open
30 Oct 2025 Risk Register reportRESOLVED that the Executive Committee: 1. Notes the identification, categorisation and prioritisation of risks as rec... Decided Open