AI summaryCabinet supports re-establishing the Wellbeing Cranbrook programme, with two new community roles hosted by Cranbrook Town Council, funded by £138,519 through to March 2028.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedTwo new community roles to be hosted locally
Money£138,519Combined funding through to March 2028
What happens nextCivic agreement to be exploredFurther report to Cabinet planned
Who it affectsCranbrook residents and partnersTown, county council, NHS, trusts
What was decided
Cabinet supports re-establishing the Wellbeing Cranbrook programme to secure the benefits of the Sport England Place Partnership and promote physical activity. Report P4
Cabinet supports the creation of two roles, Community Wellbeing & Activity Organiser and Community Connector, to be hosted by Cranbrook Town Council. Report P4
Cabinet supports exploring a civic agreement with key partners to provide a framework for ongoing community development. Report P4, 2.2
Why
To reactivate the programme and realise the benefits of the Sport England Place Partnership, including promoting physical activity. Report P4
To establish strong social foundations for the Cranbrook new community alongside its ongoing physical development. Report P4
The previous Wellbeing Cranbrook programme ended in March 2025, leaving a gap in community cohesion and support for residents. Report P19
What happens next
The two roles will be funded through the earmarked reserve and the balance of the Move More Cranbrook budget, covering the period through to the end of March 2028. Report P4, P8, P28
The council will explore the development of a civic agreement with key partners; the legal team will review it. Report P4, P11
A further report to Cabinet will set out specific recommendations on funding and hosting, ensuring conditions attached to previous funding are complied with. Report P29, P30
The money
£138,519 Combined total for the two roles through to end of March 2028 Report P8, P28
£188,519 Subtotal before deducting outstanding invoice Report P9, P27
£45,000 Programme Management element Report P9, P27
£60,000 Connecting Communities element Report P9, P27
£76,974 Earmarked reserve from Cabinet decision of March 2024 Report P9, P27
£6,545 Staffing underspend from 2024/25 Report P9, P27
-£50,000 Outstanding invoice from 2024/25 deducted from total Report P9, P28
Options considered
Chosen: Fund via earmarked reserve plus balance of Move More Cranbrook budget. Presents a middle way, giving £138,519 through to end of March 2028 without new spending Report P8, P26, P28
Chosen: Host roles through Cranbrook Town Council. Rooted in the community, with potential for longer term security of employment Report P4, P26
Rejected: Do nothing on funding. Would mean taking back the residual funding as a budget saving and losing the roles Report P26
Rejected: Do more on funding by providing additional money. Risk of filling gaps left by other partners at detriment to wider service delivery Report P26
Rejected: Host roles through the District Council. Existing community development workers are focused on Council housing tenants, and Cranbrook has little Council housing Report P25, P26
Rejected: Host roles through the Ted Wragg Trust at the Cranbrook Education Campus. Willing to host, but no single preferred option among partners Report P20, P26
Rejected: Host roles through the EX5 Alive Hub. No certainty of funding beyond November; Hub is run as a community interest company Report P20, P26
Implications
Financial: No additional budget implications arise from these recommendations, as funding comes from existing reserve and Move More Cranbrook budget. Report P11
Financial: The District Council's financial decision making autonomy is expected to be limited at least a year before new unitary councils are constituted in April 2028. Report P24
Legal: The proposed civic agreement will be subject to review by the legal team, and any conditions attached to previous funding must be complied with. Report P11, P30
Equalities: Medium impact: community development must consider how to meet the needs of diverse groups with key characteristics. Report P7, P17
Climate: Low impact on climate change. Report P7, P17
Risk: Medium risk: there is no consensus among partners on a single preferred hosting option, which could affect long term community development. Report P7, P17, P26
Other: A bid for further National Lottery funding for the EX5 Alive Community Hub was unsuccessful, with no funding beyond November 2025 currently secured. Report P18, P24
Who and where
Residents of Cranbrook, a new community with a very young demographic profile Report P8, P19, P25
Cranbrook Town Council, which will host and line manage the Community Wellbeing & Activity Organiser role Report P4, P20
The NHS, particularly the Outer Exeter Primary Care Network, with ongoing discussions on funding the Community Connector role Report P20
Devon County Council, as the holder of statutory responsibility for community services delivery Report P25
The Ted Wragg Trust at the Cranbrook Education Campus, which offered to host the Activity Organiser role Report P20, P26
The EX5 Alive Hub, run as a community interest company, with no funding certainty beyond November 2025 Report P20, P24, P26
Sport England, as the Place Partnership runs until 2028 Report P8, P19
Timeline
March 2025: Wellbeing Cranbrook programme ended, leaving a gap in community cohesion and support Report P19
9 June 2025: Cranbrook Placemaking Group first considered how to progress the Wellbeing Cranbrook programme Report P18, P19
6 October 2025: Placemaking Group considered funding and hosting options for the new roles Report P12, P19
30 November 2025: Tax base confirmation date referenced in Town Council budget decision on a youth worker role Report P20
3 December 2025: Cabinet decision to support re-establishing the programme and the two new roles Report P2
End of March 2028: End point for the £138,519 funding package and for delivery against Sport England Place Partnership outcomes Report P8, P24, P28
April 2028: New unitary councils expected to be constituted, ending the current District Council structure Report P24
Plain English for the jargon
Sport England Place Partnership: Programme running until 2028 with Exeter, focused on increasing physical activity; the previous phase (Local Delivery Pilot) ran 2021 to 2025 and included the Wellbeing Cranbrook strand
Wellbeing Cranbrook: Community building and social prescribing strand of the Place Partnership, ended in March 2025, now proposed to be re-established
Move More Cranbrook: Funding stream within the Place Partnership covering Programme Management, Move More Cranbrook priorities, Connecting Communities and Cranbrook Active Travel
Civic agreement (civic collaboration): Framework bringing together diverse individuals, groups and organisations in a community to collectively identify issues, brainstorm solutions and implement actions
Cranbrook Placemaking Group: Group that considered reports in June and October 2025 and made recommendations to Cabinet on reinvigorating the programme
Primary Care Network (PCN): NHS grouping with a requirement related to social prescribing, relevant to the Community Connector role
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item124
Resolved
RESOLVED that Cabinet; 1. Supports re-establishing the programme. 2. Supports the creation of the Community Wellbeing & Activity Organiser and Community Connector roles and for these to be hosted by Cranbrook Town Council and funded through a combination of utilising the earmarked reserve and the balance of the Move More Cranbrook budget. 3. Supports exploring the development of a civic agreement with key partners to provide a framework to support ongoing community development REASON: To help to reactivate the programme to ensure that the benefits of being within the Sport England Place Partnership programme were realised including the promotion of physical activity. To ensure that strong social foundations were established for the Cranbrook new community alongside its ongoing physical development.
Word for word from the decision East Devon published for this meeting.Source: democracy.eastdevon.gov.uk
Date of Meeting 3 December 2025 Document classification: Part A Public Document Exemption applied: None Review date for release N/A
Wellbeing Cranbrook programme Report summary: The Cranbrook Placemaking Group has considered two reports on how best to reinvigorate the Wellbeing Cranbrook programme. This report follows up on the recommendations from the Group to Cabinet regarding the funding and hosting of key roles. The potential to develop a civic collaboration agreement is also put forward as a means to develop a framework to support the social development of Cranbrook over the longer term.
Is the proposed decision in accordance with: Budget Yes ☒ No ☐ Policy Framework Yes ☒ No ☐ Recommendation: That Cabinet; • Supports re-establishing the Wellbeing Cranbrook programme • Supports the creation of the Community Wellbeing & Activity Organiser and Community Connector roles and for these to be hosted by Cranbrook Town Council and funded through a combination of utilising the earmarked reserve and the balance of the Move More Cranbrook budget • Supports exploring the development of a civic agreement with key partners to provide a framework to support ongoing community development Reason for recommendation: To help to reactivate the Wellbeing Cranbrook programme to ensure that the benefits of being within the Sport England Place Partnership programme are realised including the promotion of physical activity. To ensure that strong social foundations are established for the Cranbrook new community alongside its ongoing physical development.
Portfolio(s) (check which apply): ☐ Assets and Economy ☐ Communications and Democracy ☐ Council, Corporate and External Engagement ☐ Culture, Leisure, Sport and Tourism ☐ Environment - Nature and Climate ☐ Environment - Operational ☐ Finance ☒ Place, Infrastructure and Strategic Planning ☒ Sustainable Homes and Communities
Equalities impact Medium Impact Medium Impact. The essence of community development is to support the establishment of strong and resilient communities. This necessarily needs to consider how best to meet the needs of diverse groups with key characteristics. Equalities Impact Assessment Climate change Low Impact Risk: Medium Risk; The recommendations in this report will enable two key roles to be hosted locally in Cranbrook through to April 2028. It is essential that there is a collective commitment to the wider social development of Cranbrook and the development of a civic agreement will help to establish a framework for this over the longer term. Links to background information (Public Pack)Agenda Document for Cranbrook Placemaking Group, 09/06/2025 09:30 item 10 Link to Council Plan Priorities (check which apply) ☒ A supported and engaged community ☐ Carbon neutrality and ecological recovery ☐ Resilient economy that supports local business ☒ Financially secure and improving quality of services
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.