AI summaryEast Devon planning committee approves outline application for up to 2,640 sq m of employment floor space on a 0.77 ha site south of Hansford Way, Ottery St Mary, with B2 general industrial use dropped.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedOutline permission, all matters reserved
MoneyNot stated
What happens nextReserved matters within three yearsLayout, scale, appearance, access, landscaping
Who it affectsSite south of Hansford Way, Ottery St Mary. 0.77 ha, allocated for employment

What was decided

The committee approved the application in accordance with the officer recommendation, subject to conditions. Report P206

Permission is in outline only, with all detailed matters reserved, and is capped at up to 2,640 sq m of single storey employment floor space. Report P5, P114, P115, P116, P138, P141

The use mix was amended during the application to remove Class B2 (general industrial) and now comprises B8, E(c) and E(g) only. Report P114, P120, P152

Why

The site is a long-standing employment allocation in the adopted East Devon Local Plan and emerging draft plan, and the Economic Development Officer highlighted a serious district-wide shortfall in employment land, with unmet demand of 50.8 ha against 1.7 ha of supply. Report P6, P7, P113, P122, P126, P127, P45, P46, P47

Officers accepted the sequential test for flood risk because no lower-risk alternative sites are available in the town's built-up area, and the revised layout keeps buildings within flood zones 1 and 2 only, with detailed mitigation secured by conditions. Report P116, P161, P162, P163, P164, P165, P167, P186

Concerns about neighbour amenity, highways, ecology, drainage and design were judged capable of being dealt with at the reserved matters stage or through conditions, including restricted delivery hours for Class B8 uses. Report P8, P9, P133, P149, P150, P151, P154, P155, P193, P197

What happens next

Reserved matters applications must be made within three years, with development begun within two years of the last reserved matters approval. Report P208

Pre-commencement conditions require a Construction Management Plan, a Construction Ecological Management Plan, a 30-year Landscape and Ecology Management Plan, a drainage design, a lighting scheme, a noise assessment and a written scheme of archaeological investigation. Report P29, P58, P198, P210, P37, P38

Class B8 deliveries will be limited to 08:00 to 18:00 Monday to Friday and 08:00 to 13:00 on Saturdays; Class E deliveries to 07:00 to 23:00. Report P42, P149, P151

Options considered

  • Chosen: Approve with conditions in line with officer recommendation. Site is a long-standing employment allocation, no lower flood risk site is available, and impacts can be controlled by conditions. Report P206, P122, P164, P205
  • Rejected: Refuse or defer the application. Officers found the proposal acceptable in principle and on detailed matters subject to conditions, despite objections from the town council, a ward member, and third parties. Report P9, P133, P204, P205

Implications

  • Legal: Outline permission only; all layout, scale, appearance, access and landscaping details are reserved for later approval. Report P5, P115, P207
  • Financial: Potential to accommodate around 70 full-time equivalent jobs on a site flagged as part of a district-wide employment land shortfall. Report P45, P46, P47
  • Equalities: Proximity to a hospital, school and residential properties prompted conditions on noise, lighting, drainage and delivery hours. Report P2, P34, P42, P145, P150
  • Climate: Revised flood risk assessment includes climate change allowance, a 0.3 m freeboard and a refuge mezzanine in each unit; permeable SuDS surface water design and biodiversity-enhanced landscaping required. Report P167, P168, P171, P178, P196
  • Risk: Environment Agency and Lead Local Flood Authority require pre-commencement drainage details and ongoing management of flood zone 3 to prevent increased risk elsewhere. Report P29, P30, P186, P187, P193
  • Other: Ecologist flagged an adverse ecological impact from loss of neutral grassland and scrub because the application predates mandatory biodiversity net gain. Report P52, P56, P57

Who and where

  • Residents of Elliot Close and surrounding housing on Thorne Farm Way, including users of the nearby hospital and school Report P2, P110, P145
  • Ottery St Mary Town Council, which objected on grounds of appearance, flooding, hours, footpath 25, parking and inappropriate B2 use Report P12, P13
  • The ward member for Ottery St Mary, who objected on noise, ecology, parking, footpath and design grounds Report P14, P16, P20, P22, P23, P24
  • A second Ottery St Mary ward member, who supported the application subject to noise mitigation and protection of footpath 25 Report P25, P26, P27
  • 12 objectors and 1 supporter from the wider public Report P59, P60, P61, P62
  • Users of public footpath 25, which the application confirms will not be extinguished or diverted Report P111, P159
  • Existing businesses on the Finnimore Industrial Estate and future B8, E(c) and E(g) occupiers of the new floor space Report P2, P110, P114

Timeline

  • December 2022: Preliminary Ecological Appraisal of the site carried out. Report P18, 1.3
  • 10th June 2024: Drainage Strategy Plan referenced in flood risk consultation. Report P29
  • 10.09.24: Revised Flood Risk Assessment submitted by the applicant's agent. Report P49
  • October 2025: Ecological Impact Assessment submitted. Report P51, P58
  • Within three years of permission: Reserved matters application must be made. Report P208
  • Within two years of last reserved matters approval: Development must be begun. Report P208
  • 2026-03-24: East Devon Planning Committee approved the application with conditions.

Plain English for the jargon

  • Outline planning permission: Permission that establishes whether a development is acceptable in principle, with detailed matters such as layout, scale and appearance considered later.
  • Reserved matters: The detailed aspects of a development that an outline permission leaves to a later application, for example layout, scale, appearance, access and landscaping.
  • Sequential test: A test in national planning policy that requires development in higher flood risk areas to be steered first to sites with lower flood risk where possible.
  • Use Classes Order (UCO): The Town and Country Planning (Use Classes) Order, which groups land uses into classes such as B8 storage and distribution and E commercial, business and service.
  • Flood zones 1, 2 and 3: Government flood risk zones where zone 1 is low probability, zone 2 is medium probability and zone 3 is high probability of river or sea flooding.
  • SuDS: Sustainable Drainage Systems, drainage methods that manage surface water close to where it falls, for example through permeable surfaces or attenuation.
  • CEMP / CEcoMP: Construction Environmental or Ecological Management Plan, setting out how construction works will be controlled to limit harm to the environment, ecology and neighbours.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item93

Resolved

Approved with conditions in accordance with officer recommendation.
Word for word from the decision East Devon published for this meeting. Source: democracy.eastdevon.gov.uk

Follow this further

Built from East Devon's papers

What the report saysPro

Report to Planning Committee

Executive summary

This application is brought before the Committee owing, principally, to a difference of opinion between officers and one of the ward members. However, as the proposal falls within a 'Major' category of development, the conflict between the officer position and that of the town council also triggers a need for Committee referral.

The proposal seeks outline planning permission for the development of up to 2640 sq. m. of employment floor space on a currently vacant site, extending to around 0.77 ha in area, on the north side of Barrack Road. It is essentially bordered by the existing Finnimore Industrial Estate to the east whilst the community hospital and housing served by Thorne Farm Way are to the west and north, respectively. Hansford Way is a secondary route that connects Thorne Farm Way with the industrial estate to the north of the site.

The majority of the site lies within flood zone 2 with approximately half of the site area also within flood zone 3.

The scheme proposes a mix of uses that fall within Classes B8 (Storage or Distribution), E(c) (Financial, Professional and other Services appropriate for provision within a commercial, business or service locality) and E(g) (Office, Research and Light Industrial) as defined in Schedules 1 and 2 to the Town and Country Planning (Use Classes) Order (as amended) (UCO).

All detailed matters, comprising the layout, scale and appearance of development and means of access to, and landscaping of, the site are reserved for consideration at a later stage.

The site is, and has long been, designated as part of a larger Employment

23/2077/MOUT Allocation within the current adopted and predecessor local plans. As such, it is considered that the fundamental principle of the scheme, which would consist of traditional current and former B Class uses, would be acceptable.

The proposal is also thought to be acceptable having regard to all other contextual matters, such as its impact upon the character and appearance of the area, neighbour amenity impact, highways/traffic/parking, detailed flood risk mitigation matters, foul and surface water drainage disposal, ecology and archaeology.

Whilst a number of the concerns expressed by the town council, ward members, third parties and consultees in regard to the submitted site layout details are acknowledged, it should be emphasised that the current proposals are in outline alone with a maximum (as opposed to a fixed) level of floor space proposed. There would therefore be an opportunity at the reserved matters stage to assess the acceptability, or otherwise, of the details.

CONSULTATIONS

Local Consultations

Parish/Town Council A member of public spoke and acknowledged that the applicant had listened to some of the objections previously raised but that they still objected to the application, overall. A list of their objections were resummarised to the Committee.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
23/2077/MOUT (Major) OTTERY ST MARYReport 606 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 26 attended
BB
Councillor Brian BaileyCommittee Member, apologies
JB
Councillor Jessica BaileyGuest, in attendance
IB
Councillor Ian BarlowCommittee Member, present
NB
Nigel BarrettOfficer, in attendance
KB
Councillor Kim BloxhamCommittee Member, present
CB
Councillor Colin BrownCommittee Member, present
SC
Councillor Sarah ChamberlainCommittee Member, absent
MC
Councillor Maddy ChapmanCommittee Member, absent
BC
Councillor Bethany CollinsCommittee Member, present
RC
Councillor Roy CollinsGuest, in attendance
OD
Councillor Olly DaveyChair, present
AD
Andrew DigbyOfficer, in attendance

All 26 on the meeting page

On this subject at East Devon

Search all
  1. 23/2077/MOUT (Major) OTTERY ST MARYThis decision
  2. 26/0534/MOUT (Major) WHIMPLE & ROCKBEAREApproved
  3. 25/2397/MFUL (Major) & 25/2398/LBC EXMOUTH TOWNApproved
  4. 25/2468/MOUT (Major) OTTERY ST MARYRefused
  5. 25/0356/MOUT (Major) SIDMOUTH SIDFORDApproved
  6. 25/1060/MOUT (Major) FENITONApproved

More from East Devon Planning Committee

All decisions
MeetingDecisionOutcome
1 Sep 2026 25/2471/MRES (Major) CRANBROOKApproved with conditions in accordance with officer recommendation. Approved Open
1 Sep 2026 26/1143/PIP (Other) CLYST VALLEYThe Appropriate Assessment be adopted. 2. Permission in Principle be approved. Approved Open
1 Sep 2026 26/0854/FUL (Minor) BROADCLYSTApproved with conditions in accordance with officer recommendation. Approved Open
1 Sep 2026 26/0534/MOUT (Major) WHIMPLE & ROCKBEAREThe Appropriate Assessment be adopted. 2. Approved with conditions in accordance with officer recommendation subject ... Approved Open
1 Sep 2026 26/0535/MFUL (Major) WHIMPLE & ROCKBEAREThe Appropriate Assessment be adopted. 2. That the SANGS application be approved, subject to conditions and to the co... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies