AI summaryEast Devon District Council Cabinet has agreed to replan Not Started Council Plan actions, embed InPhase reporting, and remove Service Objectives from the performance framework, after a Q1 review showed 96% reporting coverage.
What happens nextQ2 2026/27 review periodValidate plans and embed InPhase reporting
Who it affectsCouncil priorities and reportingHow performance against Council Plan actions is tracked
What was decided
Cabinet agreed to replan Not Started key actions and projects through the Q2 performance review, ensure a quarterly review of each Key Action, and maintain clear ELT visibility of delivery challenges and dependencies. Report 2.1, 2.3
Cabinet agreed to complete the Stage 2 Governance Pilot KPI review, rollout SMART KPIs with Service Leads, and embed InPhase reporting for system-led performance management. Report 2.4, 2.5
Cabinet agreed to remove Service Objectives from the performance framework to maintain strategic focus and avoid unnecessary operational complexity in ELT and Cabinet reporting. Report 2.6
Why
A strong early delivery baseline has been established, with 72% (33 of 46) Key Actions and 81% (26 of 32) projects in progress or completed, and 96% (153 of 160) metrics fully reported. Report 3.1, 3.3
Performance maturity is still developing, with incomplete Measures of Success and emerging KPIs limiting the depth of insight, and delivery pressures are evident across major programmes and dependencies, alongside the additional demands of Local Government Reorganisation. Report P31, 3.6
System and governance foundations are now in place, including successful adoption of Microsoft Lists, creating an opportunity to move towards management by exception and more targeted ELT oversight. Report 3.5, P31
What happens next
Q2 2026/27 will focus on validating Key Actions, Projects and Measures of Success, achieving full reporting coverage across all Directorates, and strengthening performance maturity through completion of SMART KPIs. Report P33, P34, 20.1
The council will embed consistent reporting standards with clear ownership, robust commentary and appropriate RAG application, supported by system-led reporting through InPhase. Report P34, 20.1
Q2 represents a transition from framework implementation to performance maturity and focused delivery oversight. Report P39
Options considered
Rejected: Continue with the existing delivery profile without replanning. Profile is ambitious and delivery confidence depends on improved prioritisation and sequencing Report P31
Rejected: Pause or stop some activities to free capacity for LGR and core services. No decision sought on this; would require a meticulous review and prioritisation exercise Report P32
Implications
Risk: Workload strain from continuing BAU, LGR demands and Council Plan projects may require pausing or stopping some activities to protect core services. Report P6, P32
Other: No financial, legal, equality, HR, community safety, climate change, health and safety, procurement, digital and data, or communications implications arise from this report. Report 6.1, 7.1, 9.1, 10.1, 11.1, 12.1, 13.1, 14.1, 17.1, 19.1, 8.1
Who and where
East Devon District Council staff and Service Leads using the new performance framework Report 2.5, 3.5, P8
Residents and businesses who receive council services Report P3, P6
Members of the Council's Executive Leadership Team and Cabinet Report 2.3, 2.6
Timeline
Q1 2026/27 (April to June 2026): Performance review period covering 46 Key Actions, 82 Measures of Success and 32 Projects Report P2, P15
16 June 2026: ELT Review held Report 18.1
Q2 2026/27: Next performance review period, focusing on validating plans, full reporting coverage and embedding InPhase Report P10, P33, 20.1
Plain English for the jargon
RAG: Status framework using Green (Complete), Amber (In Progress), Red (Late) and Black (Not Started)
BAU: Business As Usual, covering statutory and other core services
PMO: Project Management Office, planned for future implementation
InPhase: Performance management IT system used for system-based reporting
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item22
Resolved
RESOLVED that Cabinet agree the following: 1. Re-plan ‘Not Started’ key actions and projects through the Q2 performance review to ensure a realistic and deliverable Council Plan. 2. Ensure a quarterly review of each Key Action to ensure it remains achievable, deliverable and affordable. 3. Maintain clear visibility of delivery challenges, enabling focused ELT oversight of key issues and dependencies. 4. Complete Stage 2 Governance Pilot KPI review and rollout SMART KPIs with Service Leads. 5. Embed InPhase reporting, to support consistent, system-led performance management. 6. Remove Service Objectives from the performance framework, to maintain strategic focus and avoid unnecessary operational complexity in ELT and Cabinet reporting. REASON: The overall delivery position was positive, but the current profile appeared ambitious, with delivery confidence dependent on improved prioritisation and sequencing. Performance maturity was still developing, with incomplete Measures of Success and emerging KPIs limiting the depth of insight at this stage. Delivery pressures were evident across the portfolio, including major programmes and dependencies, alongside the additional demands of LGR. Adoption of Microsoft Lists demonstrated that simple, user-focused tools drive engagement, supporting timely data returns and improving reporting consistency. System and governance foundations were now in place, creating an opportunity to move towards management by exception and more targeted ELT oversight in Q2 2026/27.
Word for word from the decision East Devon published for this meeting.Source: democracy.eastdevon.gov.uk
This report provides an overview of the Council’s performance in relation to its Council Plan. It sets out the direction of travel for key strategic actions, measures of success, and projects for Q1 2026/27 (April to June 2026), covering Finance, Governance, Housing and Place. It also helps to identify the scale of activities within the Council Plan.
The Council Plan provides the framework and direction for the Council’s work in providing services to residents and businesses. The Council’s four key priorities are set out in the Plan, linked to specific strategies and service plans. Taken as a whole, the Council Plan includes 46 Key Actions, 82 Measures of Success and 32 Projects which are to be implemented over the lifespan of the Plan.
There are three key strands making up the Council’s workload across the period of the Council Plan:
▪ Business As Usual (BAU) activities which include statutory and other core services; ▪ Local Government Reorganisation (LGR); ▪ Projects and Corporate Plan Priorities.
Collectively, this represents a challenging workload to be delivered with limited resources. The impacts of continuing BAU activities, core services and committed projects alongside the additional demands of LGR presents a strain given the need to balance Council resources, appropriate risk management and mitigation, plus monitoring of performance. This strain likely means that the Council will need to pause or stop some activities to ensure it has sufficient capacity and capability to deliver core services and priority actions. This ‘stop/ go’ process could only take place following a meticulous review and prioritisation exercise and this report does not seek any decisions on priorities or which activities it may be necessary to stop. However, it is intended to raise awareness of the scale of requirements imposed on the Council in relation to its available resources.
The Council has now commenced the rollout of a Performance Management Framework across all Directorates allowing the assessment and monitoring of performance in relation to the Council Plan Key Actions, Measures of Success and Projects. The rollout has established a baseline position which will form the basis of monitoring and reporting at a corporate level. In due course this will be further strengthened by the planned implementation of a Project Management Office (PMO).
Initial engagement has been strong in several service areas, with partial reporting now in place across each Directorate. As expected at this early stage, coverage is not yet complete, and some areas are still establishing their reporting approach. However, progress to date has been significant and is a strong improvement over previous reporting periods.
This report provides a baseline position, with 96% (153 of 160) metrics fully reported, some metrics developing and others not yet reported.
A structured programme of onboarding and refinement is underway, with full coverage of Council Plan actions and measures of success expected during the Q2 2026/27 review period as the framework and supporting system is further embedded across all service areas.
Performance is assessed using a standard RAG framework:
▪ Green – Complete ▪ Amber – In Progress ▪ Red – Late ▪ Black – Not Started
Each update includes commentary from the responsible officer, setting out progress to date, context, and, where applicable, planned corrective action. This ensures that performance updates are supported by a clear narrative and actionable insight for 160 metrics.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.