RESOLVED – that in respect of application 3/11/0370/FP, planning permission be granted subject to the conditions detailed in the report now submitted.
Development Management Committee decided this item on Wednesday 20 June 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – that in respect of application 3/11/0370/FP, planning permission be granted subject to the conditions detailed in the report now submitted.
That planning permission be GRANTED subject to the following conditions:
1. Approved plans (2E10) – ‘p01 a ; p02 b; JBA 10/142-01 Q and JBA 10/142-TS02 D’
2. The landscape details as shown on drawing numbers JBA 10/142-01 Q, JBA 10/142-TS02 D and within the Hedge Management Plan dated August 2011 shall be implemented in accordance with those details within 3 months of the date of this permission.
Reason: To ensure the provision of amenity afforded by appropriate landscape design, in accordance with policy ENV2 of the East Herts Local Plan Second Review April 2007.
Summary of Reasons for Decision
The proposal has been considered with regard to the policies of the Development Plan (East of England Plan May 2008, Hertfordshire County Structure Plan, Minerals Local Plan, Waste Local Plan and the saved policies of the East Herts Local Plan Second Review April 2007 and in particular policies OSV1, ENV1, ENV2, ENV5, ENV6, BH5, IMP1 and TR7) and the National Planning Policy Framework. The balance of the considerations having regard to those policies and the planning permission that was granted for 17 dwellings under lpa reference 3/09/1370/FP is that permission should be granted.
(037011FP.MP)
1.1The application site is shown on the attached OS extract. 3/11/0370/FP
1.2This application was previously considered by Members at the 25 May 2011 Committee meeting and again at the 09 November 2011 meeting. A copy of that report is attached as Appendix A to this report. The application seeks permission to amend the original planning permission for 17 dwellings on the site, granted under reference: 3/09/1370/FP, by the separation of a pair of semi detached houses on the development and the provision in their place of two detached houses. Further alterations are proposed to provide additional space in the roof of the two dwellings for additional bedrooms.
1.3At the November 2011 meeting Members resolved to grant planning permission for the development, subject to the signing of a S106 legal agreement. This agreement has now been signed and Officers are therefore in a position to issue the decision previously agreed by Members. However, in the intervening period, the development has been commenced and indeed is nearing completion. It has therefore been necessary to review the set of conditions that had previously been agreed by the committee and, as a result, Officers have recommended a revised list as set out at the head of this report.
2.0Considerations:
2.1The resolution by Members to grant permission on 09 November 2011 was subject to a number of conditions, some of which required details to be submitted prior to the commencement of the development. However, as the development of the wider site has progressed, and these dwellings are nearing completion, many of these conditions are no longer required.
2.2For example, it is unnecessary now to attach planning conditions requiring the submission of details relating to materials of construction, protection of trees and landscape features and other conditions relating to construction works as these elements have already been satisfactorily achieved and therefore such conditions would serve no useful purpose.
2.3It is, however, necessary and reasonable to attach a planning condition relating to the approved plans and it is also necessary and reasonable to require the provision of previously approved landscape details. These remaining conditions are therefore recommended at the head of this report.
3.0Conclusion:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
3/11/0370/FP: Separation of plots 7 and 8 (retrospective) shown as a pair of semi-detached dwellings on the approved scheme under ref 3/09/1370/FP to provide 2 no detached dwellings, Alterations and extensions to enable use of roof spaces for additional accommodation to include 2 no additional bedrReport | 27 KB | DownloadRead as text |
PDF |
3110370FP PlanReport | 128 KB | Download |
PDF |
,Gravelly LaneAppendix A | 331 KB | Download |
Follow Development Management Committee at East Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Aug 2026 | 3/25/1986/FUL - Erection of 4 x industrial units (use classes E[g], B2 and B8) with associated parking and external works at Buntingford Business Park, Baldock Road, BuntingfordRESOLVED - in accordance with paragraph 6.5.6 of the constitution, Fergus Alexander be permitted to address the Commi... | Decided | Open |
| 12 Aug 2026 | Items for Reporting and NotingRESOLVED – that the following reports be noted: (A) Appeals against refusal of planning permission / non-determinatio... | Noted | Open |
| 15 Jul 2026 | Appointment of Vice-Chair for the 2026/27 civic yearRESOLVED – that Councillor J Thomas be appointed Vice-Chair of the Development Management Committee for the 2026/27 c... | Decided | Open |
| 15 Jul 2026 | Minutes - 15 April 2026RESOLVED – that the Minutes of the meeting held on 15 April 2026, be confirmed as a correct record and signed by the ... | Decided | Open |
| 15 Apr 2026 | Minutes - 11 March 2026RESOLVED – that the Minutes of the meeting held on 11 March 2026, be confirmed as a correct record and signed by the ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.