3/14/0771/FP – Resurface existing tennis courts to create 2 new floodlit 3rd generation (3G) five-a-side football pitches with specialist all weather "3G" artificial grass.

Decided Committee 2 papers

Development Management Committee decided this item on Wednesday 4 February 2015. Below is the council's own wording, with the papers it was decided on.

Item519

Resolved

RESOLVED – that in respect of application 3/14/0771/FP, planning permission be granted subject to the conditions detailed in the report now submitted.
Word for word from the decision East Hertfordshire published for this meeting. Source: democracy.eastherts.gov.uk

Follow this further

Built from East Hertfordshire's papers

What the report saysPro

Report to Development Management Committee

Recommendation

That planning permission be GRANTED subject to the following conditions:

1. Three Year Time Limit (1T121)

2. Approved plans (2E10) – insert; „Plan1 rev A; Plan 2 rev A; LIZ0144488 and the lighting specifications submitted on 23rd December 2015‟.

3. The floodlights hereby approved, shall not be operated between the hours of 22:00 hours and 07:30 hours.

Reason: In the interests of the protection of local amenities and the character of the Green Belt and surrounding wildlife and their habitats, in accordance with policies ENV1, ENV16 and ENV23 of the East Herts Local Plan.

4. Prior to the commencement of the development, full details of both hard and soft landscape proposals shall be submitted to and approved in writing by the Local Planning Authority. These details shall include, as appropriate: (a) Planting plans (b) Written specifications (including cultivation and other operations associated with plant and grass establishment) (c) Schedules of plants, noting species, planting sizes and proposed numbers/densities where appropriate (d) Implementation timetables. Thereafter the development shall proceed in accordance with the approved details.

Reason: To ensure the provision of amenity afforded by appropriate landscape design, in accordance with policies ENV1 and ENV11 of the East Herts Local Plan Second Review April 2007.

5. Landscape works implementation (4P135) 3/14/0771/FP

Directive: 1. Other legislation (01OL1) Summary of Reasons for Decision

East Herts Council has considered the applicant‟s proposal in a positive and proactive manner with regard to the policies of the Development Plan (Minerals Local Plan, Waste Core Strategy and Development Management Policies DPD 2012 and the ‟saved‟ policies of the East Herts Local Plan Second Review April 2007); the National Planning Policy Framework and in accordance with the Town and Country Planning (Development Management Procedure) (England) Order 2012 (as amended). The balance of the considerations having regard to those policies and the amendments made is that permission should be granted.

(3140771FP.MC)

Background

1.1The site is shown on the attached Ordnance Survey extract. It comprises a set of 3 tennis courts, enclosed in a chain link fence, on Hartham Common. The site is about 180 metres west of Hartham Leisure Centre on the banks of the River Beane and falls within the Metropolitan Green Belt.

1.2The proposal is for the re-surfacing of 2 of the 3 tennis courts to create two all-weather 3G football pitches. In addition, 4 floodlight columns of 10 metres in height are proposed to be erected at the corners of the new pitches.

1.3The application was submitted with a statement from the applicant indicating that the use of Hartham‟s tennis courts has been steadily declining over the last 5 years. However, there has been a growth in the use of the Common for football and the youth and adult clubs that use the Common and nearby Kingsmead find it difficult to train in the evenings and particularly through the winter months. The proposed pitches will provide all year round facilities for local clubs and will be available for any groups or teams to book.

2.0Site History

2.1This group of tennis courts has no relevant planning history. The group of six tennis courts to the east was granted permission in December 2004 for floodlighting on 12 metre columns (ref: 3/04/2237/FP). 3/14/0771/FP

3.0Consultation Responses

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
3/14/0771/FP: Resurface existing tennis courts to create 2 new floodlit 3rd generation (3G) five-a-side football pitches with specialist all weather "3G" artificial grass. 4no. 10 metre high floodlighting columns and 1 retained tennis court at Hartham Leisure Centre, Hartham Lane, Hertford, HertforReport 127 KB DownloadRead as text
PDF
3140771FP PlanReport 250 KB Download

At this meeting

Whole meeting

On this subject at East Hertfordshire

Search all
  1. 3/14/0771/FP – Resurface existing tennis courts to create 2 new floodlit 3rd generation (3G) five-a-side football pitches with specialist all weather "3G" artificial grass.This decision
  2. 3/12/0411/FP – Site improvements involving conversion of 67 existing pitches into hard standing, standardise 24 "L" shaped hard standings, resurface existing caravan storage area and resurface existing internal access road at The Camping anAgreed

More from East Hertfordshire Development Management Committee

All decisions
MeetingDecisionOutcome
12 Aug 2026 3/25/1986/FUL - Erection of 4 x industrial units (use classes E[g], B2 and B8) with associated parking and external works at Buntingford Business Park, Baldock Road, BuntingfordRESOLVED - in accordance with paragraph 6.5.6 of the constitution, Fergus Alexander be permitted to address the Commi... Decided Open
12 Aug 2026 Items for Reporting and NotingRESOLVED – that the following reports be noted: (A) Appeals against refusal of planning permission / non-determinatio... Noted Open
15 Jul 2026 Appointment of Vice-Chair for the 2026/27 civic yearRESOLVED – that Councillor J Thomas be appointed Vice-Chair of the Development Management Committee for the 2026/27 c... Decided Open
15 Jul 2026 Minutes - 15 April 2026RESOLVED – that the Minutes of the meeting held on 15 April 2026, be confirmed as a correct record and signed by the ... Decided Open
15 Apr 2026 Minutes - 11 March 2026RESOLVED – that the Minutes of the meeting held on 11 March 2026, be confirmed as a correct record and signed by the ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies