Planning application 3/24/0294/OUT Land north of Hare Street Road, Buntingford

Agreed Committee 3 papers

Development Management Committee agreed this item on Wednesday 22 January 2025. Below is the council's own wording, with the papers it was decided on.

Item298

Resolved

RESOLVED – that in accordance with paragraph 6.5.5 in Section 6 (Regulatory Committees) of the constitution, the committee agreed to depart from the speaking arrangements of the Development Management Committee, to allow public speakers to address the committee for 6 minutes in respect of application 3/24/0294/OUT. The Head of Planning and Building Control recommended that in respect of application 3/24/0294/OUT, planning permission be granted subject to the conditions set out at the end of the report, and subject to the completion of a Section 106 legal agreement. The Principal Planning Officer highlighted the location of the site and said that application 3/24/0294/OUT was a hybrid planning application with part of the proposals submitted in full details. He set out in detail the key issues for Members to consider. As part of this summary, Members were presented with a series of plans, visuals, and detailed elevation drawings. The Principal Planning Officer detailed the planning history of the site and summarised the late representations received since the publication of the report. Members were advised that legal advice given to Officers was that the application should be reported back to Committee to allow further discussion and for some greater clarity on the elements of the proposal that members at the previous committee considered unacceptable and, in particular, in respect of the policies to be referenced and reasoning for any refusal in relation to the harms that had been identified at the previous meeting of the Committee on 13 November 2024. The Principal Planning Officer also explained that since the previous meeting there were a number of material planning considerations which needed to be reported as these may have a material bearing on the determination of the planning application. The officer explained that the publication of the revised NPPF in the middle of December had resulted in a significant change to national planning policy in terms of housing. He referred to a new standard mandatory method for calculating housing need which had resulted in an increase in yearly housing number that East Herts was required to deliver in order to achieve a 5-year ... view the full minutes text for item 298.
Word for word from the decision East Hertfordshire published for this meeting. Source: democracy.eastherts.gov.uk

Follow this further

Built from East Hertfordshire's papers

What the report saysPro

Report to Development Management Committee

Development Management Committee: 13 November 2024 Additional Representations Summary

East Herts Council: Development Management Committee Date: 13 November 2024 Summary of additional representations received after completion of reports submitted to the committee, but received by 5pm on the date of the meeting.

Agenda No Summary of representations Officer comments

5a Comment received from CPRE (Hertfordshire) Officers position with regard to the 5YHLS, 3/24/0294/OU raising objections to the application which are the relevance of the appeal decision on land T – Land north summarised as follows: east of the A10, Buntingford, and the of Hare Street planning balance with regard the benefits / Road, • The Hare Street Road application and its harms of the proposals are as set out in the Buntingford context are very different from the Vistry committee report. application, and this appeal decision does not represent a precedent for determination For the reasons outlined in the committee of the current application. report Officers do not agree with the • 5-year housing land supply shortfall is weighting attributed by CPRE to the relatively small and will be met by other planning considerations discussed in their windfall sites. As such this issue would not comments. outweigh adverse impacts of encroachment beyond the settlement boundary. Other concerns raised with regard to the • Encroachment beyond the settlement location of the medical centre, loss of boundary is clearly a material consideration agricultural land and concerns over drainage Development Management Committee: 13 November 2024 Additional Representations Summary

as the proposals would be contrary to policy are also addressed within the committee GBR2. report. • Landscape impacts and intrusion upon the Ribb Valley setting are greater at this site in comparison with the Vistry application, resulting in moderate adverse harm in the longer term, which cannot be fully mitigated. • Loss of Best Most Versatile agricultural land. • The medical centre should be located in an alternative location better served by public transport. • Significant concerns with regard to sewerage / drainage

5a A Further comment has been received from Government guidance to Local Planning 3/24/0294/OU Sawbridgeworth Swifts Group that condition 40 Authorities is that use of pre- T – Land north (biodiversity enhancements) should be amended commencement conditions should be of Hare Street to require submission of details of swift boxes minimised and only required if necessary. Road, prior to commencement to ensure they can be The current wording of condition 40 requires Buntingford integrated into the development. submission of details ‘prior to occupation’ which would allow for a range of construction works to take place before the condition should be discharged but would still allow for detailed to be secured of Development Management Committee: 13 November 2024 Additional Representations Summary

integrated biodiversity features. As such changing the trigger point to ‘prior to commencement’ is not considered justified.

Table of errata and updates to reports submitted to Committee.

Agenda No Paragraph Updates No

5a 6.7 Paragraph 6.7 amended as follows due to error: 3/24/0294/OU “Application can be determined with no Ecology Objections. BNG information is T – Land north sufficient for determination, showing a 13.02% Hedgerow Net Gain which of Hare Street exceeds requirements and there is no reason to believe that the Biodiversity Net Road, Gain Condition will not be met”. Buntingford

5a 9.36 Paragraph 9.36 amended as follows due to error: Development Management Committee: 13 November 2024 Additional Representations Summary

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
0294: Land North of Hare Street Road, Buntingford: Late Reps and Updates.docxReport 109 KB DownloadRead as text
PDF
3-24-0294-OUT: Land North of Hare Street Road, Buntingford.docxReport 3.5 MB Download
PDF
Planning application 3/24/0294/OUT Land north of Hare Street Road, BuntingfordReport 243 KB Download

At this meeting

Whole meeting
297Minutes - 4 December 2024Decided
298Planning application 3/24/0294/OUT Land north of Hare Street Road, BuntingfordThis decision
299Items for Reporting and NotingNoted

On this subject at East Hertfordshire

Search all
  1. Planning application 3/24/0294/OUT Land north of Hare Street Road, BuntingfordThis decision
  2. Planning Applications for Consideration by the CommitteeAgreed
  3. Planning Applications for Consideration by the CommitteeAgreed
  4. Planning Applications and Unauthorised Development for Consideration by the CommitteeDecided
  5. 3/15/0300/OUT – Hybrid planning application comprising demolition of former depot and development of Phases 1 – 4 of a mixed use scheme comprising 316 dwellings of mixed size and tenure with ancillary parking, public open space and landscapDecided
  6. 3/14/0094/OP – Outline planning application for a development of up to 10 dwellings with all matters reserved except highway access onto Green End (B1368) on Land East of Green End Farm, Green End, Braughing, SG11 2PG for The Fairfield PartnershipRefused

More from East Hertfordshire Development Management Committee

All decisions
MeetingDecisionOutcome
12 Aug 2026 3/25/1986/FUL - Erection of 4 x industrial units (use classes E[g], B2 and B8) with associated parking and external works at Buntingford Business Park, Baldock Road, BuntingfordRESOLVED - in accordance with paragraph 6.5.6 of the constitution, Fergus Alexander be permitted to address the Commi... Decided Open
12 Aug 2026 Items for Reporting and NotingRESOLVED – that the following reports be noted: (A) Appeals against refusal of planning permission / non-determinatio... Noted Open
15 Jul 2026 Appointment of Vice-Chair for the 2026/27 civic yearRESOLVED – that Councillor J Thomas be appointed Vice-Chair of the Development Management Committee for the 2026/27 c... Decided Open
15 Jul 2026 Minutes - 15 April 2026RESOLVED – that the Minutes of the meeting held on 15 April 2026, be confirmed as a correct record and signed by the ... Decided Open
15 Apr 2026 Minutes - 11 March 2026RESOLVED – that the Minutes of the meeting held on 11 March 2026, be confirmed as a correct record and signed by the ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies