RESOLVED That it be noted that Lincolnshire County Council was currently progressing their respective approvals and were keen for an early decision. That the proposed letting to Lincolnshire County Council as part of the joint use and occupation of the building be approved. That the Capital request to facilitate delivery of the project be approved. That the Embassy Theatre venue be made available on a free of charge basis to Skegness Town Council for the purposes of their Annual General Meeting if required. Note: The Capital input would be necessary to progress with joint occupation as ground floor alterations were necessary to accommodate all parties planned usage. There was currently no provision in the Capital Programme for ... view the full minutes text for item 69.
Word for word from the decision East Lindsey published for this meeting.Source: democracy.e-lindsey.gov.uk
EAST LINDSEY DISTRICT COUNCIL REPORT COMMITTEE: EXECUTIVE BOARD
DATE: 12 JANUARY 2010
SUBJECT: SKEGNESS TOWN HALL
PORTFOLIO HOLDER COUNCILLOR DAVIE
Ward(s) affected: SKEGNESS WARDS
Brief description of report content and the decision being asked for:
Summary: This report considers the progress on a partnership proposal for the joint utilisation of Skegness Town Hall between the District and County Councils and the resultant capital funding required to redesign and refurbish the accommodation for joint occupation to include a multi use Council Chamber/Marriage Room. A previous report was considered by Management Team on 28th July 2008, 4th May 2009 and again on 16th October 2009, the background information within those reports remains relevant.
It should be noted that the capital expenditure in the recommendation below consists of two distinct elements i.e. 1) the sum of £128,900 (subject to tender) being the District Council’s contribution to the ground floor alterations to facilitate the partnership occupation of the building and 2) a further £ 76,732 (subject to tender) required to allow for works to the vacant first floor office space. This second element will provide the opportunity for provision of “touchdown” working facilities to the benefit of all service departments of East Lindsey District Council and will ensure that all floors of the building are updated and fit for purpose.
Recommendations: 1.1. That Executive Board note that the County Council are currently progressing their respective approvals and are keen for an early decision.
1.2That Executive Board approve the proposed letting to Lincolnshire County Council as part of the joint use and occupation of the building.
E:\moderngov\data\published\Intranet\C00000124\M00003663\AI00007482\SkegnessTownHall0.doc 1.3. That Executive Board approve the Capital request to facilitate delivery of the project. Capital input will be necessary to progress with joint occupation as ground floor alterations are necessary to accommodate all parties planned usage. There is currently no provision in the Capital Programme for this specific work. However, within the capital programme approved on 29th July 2009, there is £200k in the frozen element of the pre-commitment section of the capital programme, which is allocated against unspecified Customer Access Services. REASON: To provide enhanced Customer Service Facilities for East Lindsey District Council residents meeting recommendations from the Use of Resources Assessment and outcomes from Lincolnshire Shared Services / The New Ways of Working Project.
This report has been prepared by: David Short Tel: 01507 601111 – Extension 390 e-mail: [email protected]
This report was prepared after consultation with:
Asset Management Group of 29th April 2009 considered a further draft of this report and it should be noted that the Portfolio Holder, Councillor Davie, supported both elements of the proposed scheme (as costed). Management Team of 4th May 2009 were also in support and requested that the matter be progressed to the Executive Board after further Town Council consultation.
A further meeting was held between the Business Manager and the Clerk to Skegness Town Council on 16th September 2009. The matter was then raised with their members on two occasions although we are advised it was not as a formally minuted agenda item. The Clerks’ initial feedback was that members were generally in support provided the I.T. display equipment was adequate in a re-provided chamber and that sufficient members of the public could be accommodated in the layout options as and when required.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2026/27 Quarter 1 Finance Update1) That the General Fund forecast revenue outturn position for 2026/27 being an underspend of £56k as detailed in Tab...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.