CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
East Lindsey District Council
Executive Board, Tuesday 12 January 2010 at 10.00am

Capital Programme Update

Approved Executive 3 papers

Executive Board approved this item on Tuesday 12 January 2010. Below is the council's own wording, with the papers it was decided on.

Item70

Resolved

RESOLVED That the proposed changes to the Capital Programme, including the estimated unallocated capital resources at 31 March 2012 of £3.73m be approved. That the following changes to the Capital Programme be recommended to Council for approval: - 2009/10 2010/11 2011/12 TOTAL £’000 £’000 £'000 £’000 Current Capital Programme 15,620 2,741 1,332 19,693 Council 16 Dec 2009 Commitment to Invest 9,176 628 425 10,229 Contaminated Land investigation work 69 69 DEFRA Contaminated Land Capital Grant Income -69 -69 Rephase Kingfisher Caravan Park electrical upgrade work -125 125 0 Skegness Town Hall 206 206 Revised Commitment to Invest 9,051 959 425 10,435 Grant Aided Schemes 1,990 885 886 3,761 Frozen Schemes 4,454 1,228 21 5,703 Customer Access Services -200 -200 Revised Frozen Schemes 4,254 1,228 21 5,503 Revised Programme 15,295 3,072 1,332 19,699 A revised Capital Programme is shown at Appendix A to the report. Reason for decision To comply with the Council’s constitution, and to maintain an updated Capital Programme approved by Council.
Word for word from the decision East Lindsey published for this meeting. Source: democracy.e-lindsey.gov.uk

Follow this further

Built from East Lindsey's papers

What the report saysPro

Report to Executive Board, 3 pages

Capital Programme 2009 to 2012 Appendix A

Total Proposed 2009/10 2010/2011 2011/2012 Expenditure 2009/10 to 2011/12

Scheme Name £'000 £'000 £'000 £'000 Commitment to Invest Improve Economic Prosperity Buy Back Plots Fairfield Ind. Est 205 205 Ingoldmells Kingfisher Caravan Park 61 63 65 189 Ingoldmells Kingfisher Caravan Park Electrical Upgrade 125 125 250

Nurture Distinctive and Vibrant Communities Council Wide Footway Lighting 32 32 Flood Alleviation Drainage Works 29 29 CCTV Chapel St Leonards & Ingoldmells 9 9 E-Government (Strategy) - all projects 110 110 Skegness Town Hall - Customer Services work 206 206

Reduce Inequality to Improve Quality of Life New Build Depot Facility 860 860 Council Wide Disabled Access Works 9 9 Phase 2 Railway Walk 80 80 Less: LCC Funding -80 -80 The Strand 170 170

Housing Capital Programme - additional allocation 200 300 300 800 Housing Capital Programme - unallocated 10 10 HDP - Patten Avenue Wainfleet Phase 2 54 54 HDP - DV Unit Louth 33 33 HDP - Dymoke Drive Horncastle 25 25 HDP - Pooles Lane Spilsby 8 8 HDP - Ingoldmells Road Burgh Le Marsh 90 90 HDP - Church Lane Holton Le Clay 160 160 HDP - Locksley Way Somercotes 13 13 HDP - Carpenters Lodge, Wragby (private developer) 70 70 HDP - Claremont Road, Burgh Le Marsh (private developer) 0 0 HDP - Finsbury Street, Alford 7 7 HDP - Alexander Road, Mablethorpe ph 2 0 0 HDP - Maple Close, Mablethorpe 180 180 HDP - Anchor Inn, Alford 130 130 HDP - Hanby Lane, Alford 120 120 HDP - Old Boston Road, Coningsby 80 80 HDP - Riverhead, Louth 40 40 HDP - Thimbleby Hill, Horncastle 200 200

CapitalProgrammeUpdate12jan10AppA0.xls Page 1/3 31/12/09 Capital Programme 2009 to 2012 Appendix A

Total Proposed 2009/10 2010/2011 2011/2012 Expenditure 2009/10 to 2011/12

Scheme Name £'000 £'000 £'000 £'000 HDP - Lincoln Road, Skegness 75 75 HDP - Carpenters Lodge, Wragby (phase 2) 60 60 HDP - Sea Lane, Chapel St Leonards 220 220 HDP - Thames Street, Hogsthorpe 30 30 HDP - Barnes Road, Skegness 20 20 HDP - Staves Court, Tetney 90 90 HDP - Bells Yard, Horncastle 50 50 HDP - Church Road South, Skegness 90 90 HDP - Brackenborough Road (tenure change) 5 5

East Lindsey CLP Wood Lane (overspend on London Road £51k taken from contingency held within this budget) 5,049 5,049 Less: Funding East Lindsey CLP Wainfleet Rd 1,170 1,170 Less: Funding -952 -952 Meridian Leisure Centre - Gym Equipment 259 259

Hemingby Lane Land Reclamation 664 77 741 Less: Funding -664 -77 -741

Contaminated Land investigation work 69 69 Less: DEFRA Funding -69 -69

Other Schemes and Asset Maintenance Planned maintenance work - Capital nature 60 60 60 180

TOTAL FOR SCHEMES WITH COMMITMENT TO INVEST 9,051 959 425 10,435 GRANT AIDED SCHEMES

Nurture Distinctive and Vibrant Communities Council Wide Capital Grants Linked Grant Aid 32 25 25 82 Council Wide Capital Grants Local Initiatives 52 50 50 152

Reduce Inequality to Improve Quality of Life Disabled Facilities Grants 1,017 810 811 2,638

Council Wide Renovation Grants Decent Homes Grants - RHB 889 889

CapitalProgrammeUpdate12jan10AppA0.xls Page 2/3 31/12/09 Capital Programme 2009 to 2012 Appendix A

Total Proposed 2009/10 2010/2011 2011/2012 Expenditure 2009/10 to 2011/12

Scheme Name £'000 £'000 £'000 £'000 TOTAL FOR GRANT AIDED SCHEMES 1,990 885 886 3,761 SUB TOTAL APPROVED SCHEMES 11,040 1,844 1,311 14,195

FROZEN SCHEMES FROM COMMITMENT TO INVEST E-Government (Strategy) unapplied from ELDC Resource 50 50 Jubilee Park 1,448 1,448 Saltfleet Public Conveniences 34 34 Council Wide Pay and Display Machines and Car Park Barriers 43 21 21 85

TOTAL FROZEN SCHEMES FROM COMMITMENT TO INVEST 1,575 21 21 1,617

FROZEN SCHEMES FROM PRE-COMMITMENT TO INVEST Improve Economic Prosperity

CAZ Contribution 100 100 General ED Provision 1,938 1,207 3,145

Reduce Inequality to Improve Quality of Life

Disabled Access works - schemes on hold 161 161 Enhanced Leisure Facilities for Mablethorpe 250 250

Other Schemes and Asset Maintenance

Depot Facilities Mablethorpe 230 230

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Update 12jan10: AppAReport 3 pages DownloadRead as text
PDF
Capital Programme Update 12jan10: AppBReport 1 pages Download
PDF
Capital Programme Update:Report 6 pages Download

At this meeting

Whole meeting

On this subject at East Lindsey

Search all
  1. Capital Programme UpdateThis decision
  2. Annual Budget Report 2026/27, Medium Term Financial Strategy, Capital Programme and Capital Strategy Treasury Management Policy/Strategy, and Annual Delivery PlanApproved
  3. Annual Budget Report 2025/26, Medium Term Financial Strategy, Capital Programme and Capital Strategy, Treasury Management Policy/Strategy and Annual Delivery PlanNoted
  4. Annual Budget Report 24/25 Medium Term Financial Strategy, Capital Programme and Capital Strategy, Treasury Management Strategy and Annual Delivery PlanApproved
  5. Annual Budget Report 2023/24, Medium Term Financial Strategy, Capital Programme and Capital Strategy, Treasury Management Strategy, Pay Policy Statement and Annual Delivery PlanApproved
  6. Capital Programme Update: IT InvestmentApproved

More from East Lindsey Executive Board

All decisions
MeetingDecisionOutcome
23 Sep 2026 East Lindsey Investment Fund Update ReportThat the un-committed spend of ELIF 1 in para 2.3 and for ELIF 2 in para 2.5 be noted. 2. That the proposed activitie... Noted Open
23 Sep 2026 Acceptance of Ministry of Housing, Communities and Local Government (MHCLG) Playground Fund GrantThat the signed Memorandum of Understanding between East Lindsey District Council and MHCLG for the Playground Fund b... Noted Open
23 Sep 2026 Vehicle parking improvements to the Waste Depot, Fairfield Industrial Estate, LouthThat the addition of £500,000 to the 2026/27 Capital Programme to fund the improvements to vehicle parking provision ... Approved Open
23 Sep 2026 2026/27 Quarter 1 Finance Update1) That the General Fund forecast revenue outturn position for 2026/27 being an underspend of £56k as detailed in Tab... Noted Open
23 Sep 2026 Quarter 1 26/27 Performance and Risk ReportThat the performance and risk information contained within the report and appendices be noted. 2. That the risk appet... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies