RESOLVED That support be given to implement the final part (Stage 2) of the Legbourne Road Flood Relief Scheme to a maximum of £90K as allocated within the Capital Programme. Reason for the decision - To allow completion of the project to protect in excess of 40 residential properties from flooding during periods of heavy rainfall. Other options for consideration- None.
Word for word from the decision East Lindsey published for this meeting.Source: democracy.e-lindsey.gov.uk
On 15th December 2010, Full Council considered the availability of capital resources for the final part (Stage 2) of the Legbourne Road Flood Relief Scheme within the Capital Programme. This scheme is designed to significantly reduce the likelihood of flooding of residential properties in the Legbourne Road/Kenwick Road area of Louth during periods of heavy rainfall.
Recommendations
That support is given by the Executive Board to implement the final part (Stage 2) of the Legbourne Road Flood Relief Scheme to a maximum of £90K as allocated within the Capital Programme.
REASON: To allow completion of the project to protect in excess of 40 residential properties from flooding during periods of heavy rainfall.
Stuart Davy – Strategic Director The following policies form a context to this report:
Not applicable.
This report is not a key decision included in the Forward Plan. LIST OF BACKGROUND PAPERS AS REQUIRED BY LAW (papers relied on to write the report but which are not published and do not contain exempt information)
1. Not applicable.
OTHER HELPFUL PAPERS (papers which the report author considers might be helpful – this might include published material)
1. Report to Portfolio Holder – Amenities: ‘Draft Discussion Document: The 2007 Flood Response and the Challenges Ahead’ dated 22nd April 2010.
Local Government (Access to Information Act) 1985
Is the report Exempt –No
Please contact the person who has written this report or Stuart Davy, Strategic Director Tel. No. (01507) 601111 Ext. 310 e-mail: [email protected], if you want more information about this report or the background papers.
1.0INTRODUCTION 1.1. The severe flooding during the summer of 2007 seriously affected the Kenwick Road /Legbourne Road areas of Louth. In excess of 40 residential properties were flooded, many internally. This included several in the adjoining Albany Road area. As a consequence, research into the flooding history and formulation of a permanent solution to the problems have been undertaken by the Land Drainage Officer in the Regulatory Services business unit, working with the Environment Agency and Lincolnshire County Council Highways Division through the local Inter-Agency Flood Forum. A flood relief scheme for this area has been developed, Stage 1 of which was completed during 2008. It has been identified that the works needed to complete the land drainage improvements, thereby protecting the previously affected properties from future flooding, amounts to an estimated £75K. Easements and compensation to the landowner will amount to an additional £15K. The total funding required to complete the scheme amounts to £90K.
1.2The solution being applied involves the construction of new dykes and culverts to divert surface water from the Kenwick Hill area to join the Stewton Beck at a point further down its course, well away from residential developments (see Appendix D).
2.0BACKGROUND 2.1. Prior to, during and after the floods of 2007, the Kenwick Road /Legbourne Road junction of Louth has been a problem area for flooding of residential properties. The presence of nearby outdated and inadequate surface water drainage arrangements can result in a high volume of water running off the surrounding agricultural land during heavy rainfall, overtopping dykes and flowing down the road to the junction with Legbourne Road (see map - Appendix A).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2026/27 Quarter 1 Finance Update1) That the General Fund forecast revenue outturn position for 2026/27 being an underspend of £56k as detailed in Tab...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.