RESOLVED That the £43,000 not allocated to service budgets in 2010/11 be noted and hence is confirmed as a recurrent budget saving in the current and future years (scheme 7 in the Executive Board’s list of 19 savings schemes for 2011/12). That the Ambition Funding of £17,000 offered up by services against two projects as part of their service budget reductions be noted (these reductions having already been approved by Portfolio Holders) (Section A at Appendix A). These reductions will retain £30,500 of Ambition money within the services’ base budgets for these specific projects. That the budget transferred to Compass Point Business Services be noted (£11,500, Section B at Appendix A), which will form part of the base budget of the company and will be subject to review within the company’s own budget savings arrangement. That the recommendations from the Service and Financial Planning Group for the following be approved:- Further budgets to be removed (£28,000) (Section C at Appendix A) Those budgets recommended to be retained (£70,000) (Section D at Appendix A). That the schemes listed at Section E where further information is required before a decision can be made (£255,000) be noted. That the Ambition Plan budget of £45k used for various corporate subscriptions (Section F at Appendix A) be noted, and that this budget element forms part of a wider project reviewing all Council grants and subscriptions. Members will receive a future report with recommendations for budget reductions in this area. Reason for the decision - To enable the Council to review the arrangements for the ongoing funding of schemes originally allocated three years of Ambition Plan £500k base budget funding through to the end of 2010/11. Other options for consideration - Members can review all the schemes detailed at Appendix A and can make different recommendations to those proposed within this report.
Word for word from the decision East Lindsey published for this meeting.Source: democracy.e-lindsey.gov.uk
This report considers the current allocation of the £500k Ambition Funding allocated to base budgets in 2008/09 for various projects for a three year period, and requests Executive Board to review these allocations and make recommendations regarding the ongoing funding for these projects.
Recommendations: It is recommended that Executive Board:
1. Notes the £43,000 not allocated to service budgets in 2010/11 and hence confirm this as a recurrent budget saving in the current and future years (scheme 7 in the Executive Board’s list of 19 savings schemes for 2011/12). 2. Notes the Ambition Funding of £17,000 offered up by services against two projects as part of their service budget reductions (these reductions having already been approved by Portfolio Holders) (Section A at Appendix A). These reductions will retain £30,500 of Ambition money within the services’ base budgets for these specific projects. 3. Notes the budget transferred to Compass Point Business Services (£11,500, Section B at Appendix A), which will form part of the base budget of the company and will be subject to review within the company’s own budget savings arrangements. 4. Approves the recommendations from the Service and Financial Planning Group for: a. Further budgets to be removed (£28,000) (Section C at Appendix A) b. Those budgets recommended to be retained (£70,000) (Section D at Appendix A). 5. Notes the schemes listed at Section E where further information is required before a decision can be made (£255,000) and 6. Notes the Ambition Plan budget of £45k used for various corporate subscriptions (Section F at Appendix A), and that this budget element is part of a wider project reviewing all Council grants and subscriptions. Members will receive a future report with recommendations for budget reductions in this area. REASON: To enable the Council to review the arrangements for the ongoing funding of schemes originally allocated three years of Ambition Plan £500k base budget funding through to the end of 2010/11 This report has been prepared by:
The following policies form a context to this report:
NA
This report is not a key decision included in the Forward Plan.
LIST OF BACKGROUND PAPERS AS REQUIRED BY LAW (papers relied on to write the report but which are not published and do not contain exempt information)
1. NA
OTHER HELPFUL PAPERS (papers which the report author considers might be helpful – this might include published material)
1. Executive Board 17 June 2008 – Ambition Plans report
Local Government (Access to Information Act) 1985
Is the report Exempt –No
Please contact the person who has written this report or Phil Barnes Tel. No. 01507 601111 x 531 e-mail: [email removed], if you want more information about this report or the background papers. 1.0. INTRODUCTION 1.1 In 2008/2009 the council identified a pot of £500,000 which it allocated to new service projects and schemes. These various schemes were extracted from a long list of potential projects, and resources were allocated on the basis of the ability of those projects/schemes to deliver outcomes in line with the Council’s Corporate Strategy. The resources were committed over a three year period which finishes at the end of 2010/11 (30.03.11). 1.2 This report reviews the current position of those projects in receipt of this funding and makes various recommendations for the ongoing allocation to service base budgets
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2026/27 Quarter 1 Finance Update1) That the General Fund forecast revenue outturn position for 2026/27 being an underspend of £56k as detailed in Tab...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.