Triton Knoll Offshore Wind Farm

Decided Planning 2 papers

Planning Committee decided this item on Thursday 19 April 2012. Below is the council's own wording, with the papers it was decided on.

Item161

Resolved

RESOLVED That no objection be rasied to the proposal but the effect on the seascape, effect on the landscape, cumulative impact, cabling route and effect of onshore and offshore wildlife be considered.
Word for word from the decision East Lindsey published for this meeting. Source: democracy.e-lindsey.gov.uk

Follow this further

Built from East Lindsey's papers

What the report saysPro

Report to Planning Committee, 30 pages

proposed Triton Knoll Offshore Wind Farm RWE npower renewables’ North Hoyle Offshore Wind Farm. This image is not intended to represent the size or scale of the Triton Knoll Offshore Wind Farm Limited

TRITON KNOLL OFFSHORE WIND FARM Environmental Statement Non-technical summary

January 2012

Document reference: 05/02 Pursuant to Reg 5(2)(a) Triton Knoll Offshore Wind Farm Limited

TRITON KNOLL OFFSHORE WIND FARM Environmental Statement Non-technical summary

January 2012 Revision A Status: Final Document reference: 05/02 Pursuant to Reg 5(2)(a)

Drafted by: RSK Environment Ltd

Approved by: Trevor Baker, Npower Renewables Ltd

Date of approval: 20th January 2012

RWE Npower Renewables Ltd

Auckland House, Lydiard Fields,

Great Western Way, Swindon, Wiltshire, SN5 8ZT Copyright (c) 2009 RWE npower renewables

All pre-existing rights reserved.

Liability In preparation of this document RWE npower renewables has made reasonable efforts to ensure that the content is accurate, up to date and complete for the purpose for which it was prepared. RWE npower renewables makes no warranty as to the accuracy or completeness of material supplied.

Other than any liability on RWE npower renewables detailed in the contracts between the parties for this work to the extent permissible by law, RWE npower renewables shall have no liability for any loss, damage, claim, expense, cost or other consequence arising as a result of use or reliance upon any information contained in or omitted from this document.

Any persons intending to use this document should satisfy themselves as to its applicability for their intended purpose.

Where appropriate, the user of this document has the obligation to employ safe working practices for any activities referred to and to adopt specific practices appropriate to local conditions. Triton Knoll Offshore Wind Farm Ltd Environmental Statement – Non-technical Summary

Contents 1 Introduction ...................................................................... 1 2 Introduction to RWE npower renewables......................... 1 3 The proposed development ............................................. 3 4 Anticipated benefits of the scheme .................................. 8 5 Selection of the TKOWF site............................................ 8 6 Renewable energy policy overview.................................. 8 7 Consenting process ......................................................... 9 8 Environmental impact assessment .................................. 9 9 Consultation................................................................... 11 10 Potential impacts on the physical environment .............. 11 11 Potential impacts on the biological environment ............ 13 12 Impacts on the human environment............................... 16 13 Inter-related impact assessment.................................... 24 14 Potential for cumulative impacts .................................... 24 15 Potential for transboundary impacts .............................. 24 16 Conclusions ................................................................... 25 17 Further information ........................................................ 25 Triton Knoll Offshore Wind Farm Ltd Environmental Statement – Non-technical Summary

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Special Item Attachment (2)Report 30 pages DownloadRead as text
PDF
Triton Knoll Offshore Wind Farm:Report 5 pages Download

At this meeting

Whole meeting

On this subject at East Lindsey

Search all
  1. Triton Knoll Offshore Wind FarmThis decision
  2. Triton KnollDecided
  3. Triton Knoll Offshore Wind Farm - Onshore Electricial SystemDecided
  4. Triton Knoll Wind Farm - Consultation on Potential On-Shore Cable Routes and Alternative Sites for Reactive CompoundDecided

More from East Lindsey Planning Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Tree Preservation Order: 137, Eastgate, Louth (105.36)That 137 Eastgate, Louth (105.36) Tree Preservation Order be confirmed (made permanent). Decided Open
2 Sep 2026 Tree Preservation Order: Land adjacent 116C Horncastle Road, Roughton Moor (215.31)That land adjacent to 116C Horncastle Road, Roughton Moor (215.31) Tree Preservation Order be confirmed (made permane... Decided Open
2 Sep 2026 00489/26/fulThat the application be approved. Approved Open
2 Jul 2026 03860/25/fulThat this Council resolve to grant planning permission with the application being referred to the Secretary of State ... Decided Open
20 May 2026 Election of ChairmanThat Councillor Stephen Eyre be elected Chairman of the Planning Committee for the Council year 2026/27. Decided Open