That the Local Impact Assessment and the written evidence and submissions to the Panel Hearing to be held at a date to be determined be prepared on the basis that: a) The landfall site, the route for the underground cable and the cable itself are unlikely to cause significant harm and as such no objections are raised in principle (NB see c, d and e below); b) Concerns are expressed regarding the siting and resulting landscape impact of the intermediate electrical compound at Marsh Lane, Orby and feel that further justification and analysis is required by the applicants; c) Reassurance and guarantees are required to ensure that neither the construction works nor the programme for those works will interfere with and as a result harm neither the attractiveness of Anderby Creek and the Lincolnshire Coastal Country Park as tourist destinations nor the free flow of traffic to and from the coast, particularly during the holiday season upon which the economy of the coastal communities are dependent; d) Reassurance is required regarding mitigation and remediation for the areas affected by the Coastal Grazing Marshes scheme; e) Reassurance and guarantees are required regarding preparation, protection, care and respect when working in the vicinity of the Sibsey Northlands Lancaster Memorial which not only commemorates those who lost their lives but is also a ‘war grave’;
Word for word from the decision East Lindsey published for this meeting.Source: democracy.e-lindsey.gov.uk
This report constitutes the Council’s formal response to the Triton Knoll on- shore electrical system consultation and will constitute the basis for the Council’s written submissions to the Panel Hearing.
Recommendations
That East Lindsey District Council prepare both the Local Impact Assessment and the written evidence and submissions, to the Panel Hearing to be held at a date to be determined, on the basis that;
a) The landfall site, the route for the underground cable and the cable itself are unlikely to cause significant harm and as such no objections are raised in principle (NB see c, d and e below). b) Concerns are expressed regarding the siting and resulting landscape impact of the intermediate electrical compound at Marsh Lane, Orby and feel that further justification and analysis is required by the applicants. REASON: In the interests of the valued landscapes of East Lindsey c) Reassurance and guarantees are required to ensure that neither the construction works nor the programme for those works will interfere with and as a result harm neither the attractiveness of Anderby Creek and the Lincolnshire Coastal Country Park as tourist destinations nor the free flow of traffic to and from the coast, particularly during the holiday season upon which the economy of the coastal communities are dependent. REASON: In the interests of the economy of the district and the amenity of residents and visitors d) Reassurance is required regarding mitigation and remediation for the areas affected by the Coastal Grazing Marshes scheme EAST LINDSEY DISTRICT COUNCIL REPORT
e) Reassurance and guarantees are required regarding preparation, protection, care and respect when working in the vicinity of the Sibsey Northlands Lancaster Memorial which not only commemorates those who lost their lives but is also a ‘war grave’.
This report has been prepared by:
David Loveday (DL) and Chris Panton (CP) - Tel: 01507 613158 e-mail: [email protected]
This report was prepared after consultation between: DL and CP.
This report is number 1 in a series of 1.
This report has been signed off by:
Alison Penn
The following policies form a context to this report:
The National Planning Policy Framework
This report is not a key decision included in the Forward Plan.
LIST OF BACKGROUND PAPERS AS REQUIRED BY LAW (papers relied on to write the report which are published but do not contain exempt information)
1. Messrs RWE have produced a raft of papers relating to the on-shore electrical system. These have been made available to the public in the planning reception area and are on the web via the Planning Inspectorate’s infrastructure site. OTHER HELPFUL PAPERS
(papers which the report author considers might be helpful – this might include published material)
1. Environmental Impact Regulations 2. Report to Executive Board November 2014
Local Government (Access to Information Act) 1985
Is the report Exempt – No
Please contact the person who has written this report CP or DL Tel. No. 613146 e-mail: [email protected] or chris.panton@e- lindsey.gov.uk if you want more information about this report or the background papers.
1.0INTRODUCTION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2026/27 Quarter 1 Finance Update1) That the General Fund forecast revenue outturn position for 2026/27 being an underspend of £56k as detailed in Tab...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.