East Lindsey District Council Internal Audit Annual Report 2013/14
Distribution List Emma Bee Internal Audit Manager
______________________________________________________________ 1 CONTENTS
Para No Purpose of Annual Report 1
Our opinion on the internal control environment 2-6
How we came to our opinion. 7 - 11
Delivery of internal audit plan 2013/14 12
Counter Fraud 13
Restrictions on scope 14
Other areas of audit activity 15
Effectiveness of Internal Audit 16
Quality Assurance 17 - 20
Appendix 1 – Internal Audit Assurances Given 2013/14 Appendix 2 – Outstanding Recommendations at 31st March 2014
______________________________________________________________ 2 Purpose of Annual Report
1 The Annual Internal Audit Report of East Lindsey District Council aims to present a summary of the audit work undertaken over the past year. In particular:
§ Include an opinion on the overall adequacy of and effectiveness of the internal control system and the extent to which the Council can rely on it; § Inform how the plan was discharged and of overall outcomes of the work undertaken; § Draw attention to any issues particularly relevant to the Annual Governance Statement.
Our Opinion
2 We have taken account of structures and processes, which have been put in place to ensure that the Council promotes good governance in the way it operates.
3 The Audit and Governance Committee helps ensure that these arrangements are working effectively. They regularly review the governance framework and consider draft and final versions of the Annual Governance Statement.
4 From the work we have undertaken during the year our opinion on the effectiveness of East Lindsey District Council’s arrangements for governance, risk management and control arrangements are as follows:
Red Amber Green1
Performing Well Governance
Risk Management Performing Adequately - some improvements required
Internal Performing Adequately - some Control improvements required
Financial Control Performing Well
1 Red Inadequate Performance. Critical action required by management throughout the Council.
Amber Performing Adequately Some improvement required to manage a high risk in a specific business area and medium risks across the Council.
Green Performing well. No concerns that significantly affect the governance framework and successful delivery of the Council priorities.
______________________________________________________________ 3 5 Our work provides an important assurance element to support the External Auditor’s opinion on the Council’s Statement of Accounts.
6 Whilst we are satisfied that the overall standard of internal control for the financial year ending 31st March 2014 is ‘performing adequately’ - our work did identify some areas of improvement.
How we came to our opinion
7 We took account of the outcome of our internal audit work during the year. Our work identified a number of areas where our assurance opinion on the activity identified some concerns on service delivery arrangements, management of risks, and operation of controls. These are:
Embassy Theatre
We have worked closely during the year with the interim Theatre Manager to address significant control and governance weaknesses at the Embassy Theatre in addition to a separate review of the Embassy Lottery Scheme. We made a number of recommendations to improve the effectiveness of the control environment. We are continuing to monitor progress at the Theatre and will conduct a further review in 2014/15.
Procurement
We found that there were cases where the Council was not fully complying with Contracts Procedure Rules in respect of obtaining the required number of quotations and exception reporting and in one instance was not compliant with OJEU (Official Journal of the European Union) regulations.
8 We suggest the Council should consider including the Embassy Theatre in the Annual Governance Statement 2014.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
East Lindsey District Council Internal Audit Annual Report 2013/14:Report | 9 pages | DownloadRead as text |
Follow Audit and Governance Committee at East Lindsey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | 2026/27 Q1 Treasury UpdateThat the report be noted. | Noted | Open |
| 9 Sep 2026 | Q1 Risk report 2026/27That the Q1 Risk Report - 2026/27 Report be noted. | Noted | Open |
| 9 Sep 2026 | Local Code of Corporate GovernanceThat the updated Local Code of Corporate Governance be approved. | Approved | Open |
| 9 Sep 2026 | Audit & Governance Committee Annual Report 2025/26That the Audit and Governance Committee's Annual Report 2025/26 be approved and presented to Full Council in October ... | Approved | Open |
| 9 Sep 2026 | Annual Governance Statement 2025/26That the draft Annual Governance Statement 2025/26 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.