AI summaryEast Lindsey Executive Board approves adding £425,000 of unspent ELIF 1 funds to the £10m ELIF 2 programme, alongside proposed project spend across community, tourism, pride in place and business growth themes.
Written from the decision and the officer reportPDF Pro
OutcomeNotedNote ELIF 1 success and approve activities and spend
Money£10,425,000 total for ELIF 2£10m new plus £425,000 carried over from ELIF 1
What happens nextNot stated
Who it affectsNot stated
What was decided
The Board noted the success of the first £10m East Lindsey Investment Fund (ELIF 1) and approved adding the £425,000 unallocated sum to ELIF 2, giving ELIF 2 a total of £10,425,000. Report P3, 1.2, P70
The Board approved the proposed activities and expenditure for ELIF 2 set out in the report, covering community development, pride in East Lindsey grants, tourism and events, business support and growth, and support services. Report P3, 2.21
The Board delegated authority to the Executive Director of Economic Development and Service Director theme leads, in consultation with relevant portfolio holders, to approve the justification case for each project and spend. Report P3
Why
The proposals build on the success of ELIF 1 and align with the Sub-Regional Strategy for the South and East Lincolnshire Councils Partnership and the Council's Growth and Prosperity Plan. Report P4, P5
Doing nothing is not considered an option given the benefits delivered to communities and businesses through ELIF 1. Report P7, P8
What happens next
Each project, activity and grant scheme will require a justification case approved by the ELIF Programme Board, with a detailed prospectus produced for each grant scheme. Report 2.23
The ELIF Programme Board will monitor delivery, manage budgets, and escalate issues to the Major Projects Board, with the programme manager maintaining a risk register. Report P72, 2.23
The money
£425,000 Unallocated sum from ELIF 1 to be added to ELIF 2 Report 1.2, P70
£10,425,000 Total funding available for ELIF 2 (including £425,000 carried forward) Report P49, P70
£9,575,000 Total ELIF 1 allocation across themes Report 1.2, P69
£2,986,822 Total ELIF 1 spent as of 31 May 2026 Report P69
£1,569,387 Total ELIF 1 committed as of 31 May 2026 Report P69
£1,000,000 ELIF 2 community development projects (revenue) Report P34
£175,000 Sutton on Sea Colonnade phase II gap funding Report P41
£540,000 Lincs 2100 Partnership match funding and staffing for coastal flood defence business case Report P42
£1,000,000 Local Plan review including evidence base, consultation and staffing Report P43
£350,000 Skegness foreshore design, planning, surveys and landscaping Report P44
£1,500,000 Wolds visitor infrastructure capital investment (subject to business case) Report P45
£385,000 Delivery of emerging housing, employment or leisure sites (subject to business case) Report P46
£450,000 Extension of heritage grants schemes in Horncastle, Louth and Wragby Report P47
£275,000 Support services for communications, finance, procurement and legal Report P48
£1.2m ELIF 1 commitment to council-owned employment land in Louth to unlock 10 acres and around 200 jobs Report P29
Options considered
Chosen: Approve adding £425,000 unallocated from ELIF 1 to ELIF 2 and proceed with proposed activities and delegation. Builds on ELIF 1 success and supports Council priorities and Growth and Prosperity Plan Report P3, P5
Rejected: Do nothing. Not considered an option given the benefits delivered to communities and businesses Report P7, P8
Implications
Financial: ELIF 2 is proposed to be funded from the corporate priority reserve as set out in the budget setting report and financial strategy 2026-27 to 2030-31. Report P71
Risk: A risk register is maintained by the programme manager and highlight reports go to the Major Projects Board for risk management and strategic steer. Report P72
Legal: Any procurement contracts or grant agreements will be supported in compliance with the Council's contract management and financial procedure rules. Report P78
Equalities: No equality and diversity, human rights or safeguarding implications identified. Report P80, P81
Climate: No climate change and environment impact assessment implications identified. Report P84, P85
Staffing: Staffing resource requirements are considered as part of all proposals; no wider workforce capacity implications identified. Report P61, P63
Other: Programme is presented as having a positive reputational outlook for the Council. Report P75, P76
Who and where
Residents across East Lindsey, including rural, coastal and market town communities Report 2.1, 3.1
Local businesses and employers, including tourism, retail and market town traders Report 2.14, 2.16, 2.18
Parish and town councils in the district Report P35, P36
Community organisations, charities and voluntary sector groups Report P36, 2.10
Visitors to coastal and Wolds destinations Report 2.14, P45
Timeline
September 2024: Council approved £10m allocation for ELIF 1 Report P1, 1.1
March 2026: Council approved a further £10m for ELIF 2 as part of the budget setting report Report P1, 1.3
Autumn 2026: New parish councils grants scheme due to launch Report P35
Autumn 2026: Report expected to approve publication of a notice to commence the Local Plan Gateway 1 process Report P43
31 May 2026: ELIF 1 spend position recorded: £2,986,822 spent and £1,569,387 committed Report P68, P69
Plain English for the jargon
ELIF: East Lindsey Investment Fund, the Council's ringfenced investment programme
ELIF 1: First £10m round of the East Lindsey Investment Fund approved in September 2024
ELIF 2: Second £10m round of the East Lindsey Investment Fund approved in March 2026
SELCP: South and East Lincolnshire Councils Partnership
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5
Resolved
That the success of ELIF 1 as identified in this report be noted; 2. That approval be given to add the unallocated sum of £425,000 to ELIF 2; 3. That the proposed activities and expenditure as identified in this report be approved; 4. That delegation be granted to the Executive Director of Economic Development and Service Director theme leads in consultation with relevant portfolio holders to approve the justification case for each project and spend.
Word for word from the decision East Lindsey published for this meeting.Source: democracy.e-lindsey.gov.uk
The Executive Board approved the £10m East Lindsey Investment Fund (ELIF 1) in September 2024 to support the priorities of making our places welcoming, supporting events and attracting visitors, community development, and supporting business growth. Following the success of the first round, the Council approved the allocation of an additional £10m for ELIF 2 as part of the budget setting report in March 2026.
This report provides an update on the spend so far and highlights the significantly positive impact the use of this fund has had on our communities and businesses. It also identifies the next set of projects and initiatives to build on the success of ELIF1 and to address the gaps in funding need.
Recommendations
That the Executive Board, 1. Notes the success of ELIF 1 as identified in this report. 2. Approves to add the unallocated sum of £425,000 to ELIF 2. 3. Approves the proposed activities and expenditure as identified in this report. 4. Delegates authority to Executive Director of Economic Development and Service Director theme leads in consultation with relevant portfolio holders to approve the justification case for each project and spend.
Reasons for recommendations
The proposals are in accordance with the Council’s approval of the East Lindsey Investment Fund in September 2024 (ELIF 1) and March 2026 (ELIF 2).
The proposals set out in this report will build on the success of the work done so far and help deliver the priorities of the Sub-Regional Strategy for the South and East Lincolnshire Councils Partnership as well as the Growth and Prosperity Plan approved by the Council.
The approval of this report will continue to deliver the Council’s ambition to implement wide ranging benefits for the businesses and communities of East Lindsey.
Other Options Considered
Do nothing is not considered an option considering the benefits to our communities and businesses.
Background
1.1The Council approved £10m allocation for East Lindsey Investment Fund 1 in September 2024 and agreed to focus on four key priority themes: • Community Development • Pride in Place • Tourism and Events • Business Growth
1.2A total sum of £9,575,000 is allocated to projects that deliver these priorities with £3.00m spent, £1.60m committed, £5.00m allocated to schemes leaving £0.425m unallocated in the budget. A detailed update on spend is included in the financial implications section of this report and an update on the outcomes achieved is included in Section 2.
1.3In March 2026, the Council approved a further allocation of £10m for East Lindsey Investment Fund 2. This report identifies key areas of proposed spend.
2. Report
2.1Update on East Lindsey Investment Fund 1: 2.2 The ELIF 1 programme has demonstrated both breadth and depth of impact, with investment reaching coastal towns, market towns, and rural villages, ensuring benefits are visible across the majority of wards. Provided below is a summary of the projects supported under each theme, and the outputs and impact delivered through the investment to date.
2.3Pride in Place grants schemes
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2026/27 Quarter 1 Finance Update1) That the General Fund forecast revenue outturn position for 2026/27 being an underspend of £56k as detailed in Tab...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.