Resolved
View the decision text for item 16/15
Cabinet decided this item on Wednesday 8 July 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 16/15
This report advises the Council of the current position with regard to the Waterside Drive Sports Hub project which has been procured through the SCAPE framework agreement. It recommends that, subject to planning permission being obtained for the development and the costs of the scheme being verified by our Quantity Surveyors, Pick Everard, that we proceed with the construction of the Sports Hub.
Work will continue to “value engineer” savings for the scheme but at the same time ensure compliance with the Environment Agency (EA), Football Association (FA), UK Athletics and Sport England standards. The report further outlines the necessary professional fees which the Council will need to pay to achieve the construction of the scheme, along with relevant risk and contingency provisions which are normal for a project of this size.
The report highlights the current position with the clubs who will occupy the Sports Hub and a potential way forward for the facility to be managed. Once built, the key priority will be that the facility will be financially sustainable, will break even or generate funds to re-invest in the facility and, in doing so will not require a revenue subsidy from the Council.
RECOMMENDED: THAT
(A) CABINET AGREES, SUBJECT TO FULL PLANNING PERMISSION, TO PROCEED WITH THE REGENERATION PROJECT ON THE FORMER LANDFILL SITE AT WATERSIDE DRIVE TO CREATE AN ENHANCED SPORTS FACILITY FOR THE COMMUNITY AT A TOTAL PROJECT COST NOT EXCEEDING £17,895,963;
(B) THE CONSTRUCTION OF THE PROJECT WILL BE CARRIED OUT BY WILLMOTT DIXON WITH A CONTRACT VALUE OF £16,947,963;
(C) DELEGATED AUTHORITY BE GIVEN TO THE PORTFOLIO HOLDER FOR RESOURCES AND THE STRATEGIC DIRECTOR & DEPUTY CHIEF EXECUTIVE TO EXECUTE THE NEC BUILDING CONTRACT AT THE AGREED COST OF CONSTRUCTION; (Di) NOTE THAT, SUBJECT TO APPROVAL OF THE SALE, THE CAPITAL RECEIPT FROM THE DISPOSAL OF STOMPOND LANE WILL FUND THE DEVELOPMENT AT WATERSIDE DRIVE;
(Dii) THAT DELEGATED AUTHORITY BE GIVEN TO THE STRATEGIC DIRECTOR & DEPUTY CHIEF EXECUTIVE TO FUND THE RE- DEVELOPMENT FROM EXISTING CAPITAL FUNDING RESOURCES DURING 2015/16 AND 2016/17 WHICH MINIMISES THE IMPACT ON THE COUNCIL’S REVENUE ACCOUNT UNTIL THE CAPITAL RECEIPTS FROM STOMPOND LANE IS RECEIVED;
(Diii) AUTHORITY BE GIVEN TO UNDERTAKE SHORT-TERM BORROWING AS REQUIRED TO MANAGE THE CASH POSITION OF THE AUTHORITY DURING THE PERIOD OF RE-DEVELOPMENT UNTIL THE CAPITAL RECEIPT IS RECEIVED;
(E) A SUM OF £450,000 IS APPROVED AS PART OF THE TOTAL PROJECT COSTS OF WHICH £350,000 RELATES TO PROFESSIONAL FEES AND £100,000 FOR THE DELIVERY OF THE PLAY AREA AND FURNITURE FOR THE CLUBS;
(F) A SUM OF £500,000 BE SET ASIDE AS PART OF THE TOTAL PROJECT COSTS, AS CONTINGENCY FOR THE PROJECT TO COVER THE RISK ELEMENTS AS OUTLINED IN APPENDIX B;
(G) NOTES THAT, FOLLOWING A SUCCESSFUL CIL BID, (SUBJECT TO CABINET APPROVAL) A SECOND 3G PITCH BE CONSTRUCTED AS AN ADDITION TO THE MAIN CONTRACT;
(H) AGREES THE SUM OF £20,000 TO HOST WALTON CASUALS AT MERSTHAM FOOTBALL CLUB FOR NEXT SEASON DURING THE CONSRUCTION PROCESS, TO BE FUNDED FROM THE CORPORATE INITIATIVES REVENUE BUDGET;
(I) AGREES THE SCHEME KNOWN AS THE ELMBRIDGE SPORTS HUB BE OPTED FOR TAX.
REPORT:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Costs /15Appendix A | 1 pages | Download |
PDF |
Risk Register /15Appendix B | 1 pages | Download |
PDF |
Drawing /15Appendix C | 1 pages | Download |
PDF |
Sports Hub Waterside DriveReport | 12 pages | DownloadRead as text |
Follow Cabinet at Elmbridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Oct 2026 | Old Post Office EsherView the decision text for item 22/26 | Decided | Open |
| 16 Sep 2026 | Disposal of land in Oaken Lane, Claygate, EsherView the decision text for item 15/26 | Decided | Open |
| 16 Sep 2026 | Water Play Strategy UpdateView the decision text for item 16/26 | Decided | Open |
| 16 Sep 2026 | Elmbridge Local Plan 2039: Notice of commencement of plan-making and Local Plan timetableView the decision text for item 17/26 | Decided | Open |
| 16 Sep 2026 | 2026/27 Revenue and Capital Budget Update - Quarter 1View the decision text for item 19/26 | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.