Waterside Drive Sports Hub and Stompond Lane Development Update

Decided Executive 1 paper

Cabinet decided this item on Wednesday 14 September 2016. Below is the council's own wording, with the papers it was decided on.

Item25/16

Resolved

View the decision text for item 25/16
Word for word from the decision Elmbridge published for this meeting. Source: mygov.elmbridge.gov.uk

Follow this further

Built from Elmbridge's papers

What the report saysPro

Report to Cabinet, 5 pages

Executive summary

This report gives an update on where the Council is with regard to construction of the Waterside Drive Sports Hub. The report also advises on the current position with regard to the operation of the Sports Hub once built and informs the Council of the procurement process. The key priority remains that the facility will be financially sustainable and will break even or generate sufficient funds to re-invest in the facility and, in doing so, will require limited revenue subsidy from the Council.

The report further highlights the current position on the sale of Stompond Lane to developers London Square and the relevant timings.

RECOMMENDATION: THAT THE CABINET:

(A) NOTE THE UPDATE ON CONSTRUCTION OF THE SPORTS HUB AT WATERSIDE DRIVE; AND

(B) NOTE THE UPDATE ON THE SALE OF STOMPOND LANE.

REPORT:

1. Background Waterside Drive

Members will be aware that one of the Council’s flagship projects is to complete the contamination works and start construction of the Sports Hub on the former Landfill site at Waterside Drive. In July 2015, Council approved the construction of the Sports Hub which will create an enhanced sports facility for the Community and agreed that the capital receipt from the disposal of Stompond Lane would fund the Sports Hub development. It was also agreed that the Construction will be carried out by an organisation called Willmott Dixon.

In January 2016 full planning permission was granted to Willmott Dixon for the development of the Sports Hub which comprises a new football and athletics stadium with spectator seating and detached two storey building incorporating changing facilities, storage function and club rooms, floodlighting, additional football sports pitches, a new car park and access road, hard and soft landscaping, playground and a new electric sub-station.

2. Progress to Date

The building contract was signed between Willmott Dixon and Elmbridge Borough Council in March of this year and subsequently Willmott Dixon commenced work on site on 21 March 2016. The first stage of the programme was to undertake site set up and to demolish the existing buildings on site in order to facilitate the comprehensive development of the Sports Hub. The contract duration is 76 weeks and contract completion is expected to be in September 2017. At the time of writing there are no delays expected and we are on target to complete on the date advised above but this is strictly subject to matters outside of our control eg, weather, labour and materials market and deleterious objects found in the ground. Bi- weekly updates will keep members and the public informed of the progress.

Willmott Dixon have been on site for 21 weeks and the major first phase of the works is the grounds work element which will continue until end of the calendar year. In addition to the ground work the following tasks have already been or near to completion: -

 Installation of PRB (Permeable Reactive Barrier)  Installation of virtual curtain (to control any future gas emissions)  New entrance road created along with stabilisation  New foul and surface drainage  Completion of the piling to the pavilion  Completion of ground beam excavation

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Waterside Drive Sports Hub and Stompond Lane Development UpdateReport 5 pages DownloadRead as text

More from Elmbridge Cabinet

All decisions
MeetingDecisionOutcome
27 Oct 2026 Old Post Office EsherView the decision text for item 22/26 Decided Open
16 Sep 2026 Disposal of land in Oaken Lane, Claygate, EsherView the decision text for item 15/26 Decided Open
16 Sep 2026 Water Play Strategy UpdateView the decision text for item 16/26 Decided Open
16 Sep 2026 Elmbridge Local Plan 2039: Notice of commencement of plan-making and Local Plan timetableView the decision text for item 17/26 Decided Open
16 Sep 2026 2026/27 Revenue and Capital Budget Update - Quarter 1View the decision text for item 19/26 Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies