Resolved
View the decision text for item 6/25
Cabinet decided this item on Monday 14 July 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 6/25
This report provides an update following the approval of the “Device as a Service (Laptops) for EBC” programme by Cabinet and Council in October 2024. The subsequent pilot and testing phases (see Table 1) have revealed important insights that necessitate a change in the approach, including the switch from remanufactured laptops to new laptops.
Delays to the original rollout due to the impact of user testing and the subsequent change in device specification, has meant that the original supplier quote is no longer valid. An initial enquiry has established that new devices can be purchased within the original budgeted project cost. To select a provider a procurement process in line with Contract Standing Orders will be undertaken.
Furthermore, due to Local Government Reorganisation (LGR), there is no longer a long-term requirement to provide laptops for Councillors, and along with other service changes, the number of laptop devices has reduced from 400 to approximately 338. While unit costs have increased with the switch to new devices, the total project cost of £490,000 remains within the Cabinet-approved budget of £98,000 per year over five years. Contingency has also been included to accommodate any additional device requirements if needed.
This change also supports a broader move toward a Modern Workplace programme, which addresses not just device refresh, but also improvements in application readiness, Wi-Fi, and the organisation’s hybrid working capability—particularly in the context of LGR.
Recommendation: That Cabinet recommends to Council:
(a) approval of the inclusion of the purchase in the capital programme at a cost of £490,000 to be funded by internal borrowing, rather than through recurring revenue as originally set out in the Cabinet-approved paper of September 2024. The revenue funding for the internal borrowing to be met from the existing £98,000 approved in September 2024.
Cabinet resolves to:
(a) delegate authority to the Strategic Director (Services) to award the contract.
OFFICIAL OFFICIAL
Report:
Following Cabinet and Council approval in September and October 2024 respectively, the Council began implementation of the Device as a Service model for the provision of employee laptops. The model, initially using remanufactured laptops, was selected for its cost-effectiveness and sustainability credentials.
To support the rollout, two testing phases were undertaken:
Phase 1: November 2024 involved pilot testing of remanufactured laptops. The goal was to assess their suitability for hybrid, office, and home working. However, feedback from participating employees indicated a poor user experience using the remanufactured devices in a Citrix environment.
Phase 2: April 2025 was launched in response to this feedback and involved testing new laptops. This phase aimed to compare the performance and user experience of the remanufactured laptops against new devices across different working settings— home, office, and hybrid. It also evaluated how both devices operated inside and outside of the Citrix environment.
The table below summarises both the key issues and positive feedback collated from both pilots:
Pilot 1 Pilot 2 Date: 23/09/24 to 25/10/24 Date: 14/04/25 to 9/05/25 Objectives: Objectives: To test hybrid/office/home working with To test hybrid/office/home working with remanufactured laptops new laptops
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Implementation Timeline Plan /25Appendix A | 1 pages | Download |
PDF |
Role Based devices /25Appendix B | 1 pages | Download |
PDF |
Device as a Service (Laptops): Update and Implementation DirectionReport | 6 pages | DownloadRead as text |
Follow Cabinet at Elmbridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Oct 2026 | Old Post Office EsherView the decision text for item 22/26 | Decided | Open |
| 16 Sep 2026 | Disposal of land in Oaken Lane, Claygate, EsherView the decision text for item 15/26 | Decided | Open |
| 16 Sep 2026 | Water Play Strategy UpdateView the decision text for item 16/26 | Decided | Open |
| 16 Sep 2026 | Elmbridge Local Plan 2039: Notice of commencement of plan-making and Local Plan timetableView the decision text for item 17/26 | Decided | Open |
| 16 Sep 2026 | 2026/27 Revenue and Capital Budget Update - Quarter 1View the decision text for item 19/26 | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.