Resolved
View the decision text for item 11/25
Cabinet decided this item on Monday 14 July 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 11/25
This report sets out the infrastructure projects to be considered for inclusion on the Strategic Priority Programme (SPP) List for the municipal year 2025/26 as recommended by the Strategic Community Infrastructure Levy (CIL) Working Group (SCILWG) following their meeting on 3 June 2025.
There is currently £11,347,000 available in the SPP fund and the SCILWG have recommended for inclusion on the SPP list projects with an imminent timeline for 2025/26 and 2026/27, totalling £8,233,000. The SCILWG is mindful that inclusion on the SPP list does not guarantee funding.
There are further projects that have been included on the SPP list with a due date beyond 2027. This is beyond the current timeframes for Local Government Reorganisation (LGR); however these projects are included for information and continuity.
Recommended: that
(a) Cabinet consider and agree the infrastructure projects recommended for inclusion on the Strategic Priority Programme (SPP) List for the municipal year.
Report:
1. The Strategic Priority Programme 2025-26
1.1In accordance with the CIL Regulations and the Council’s adopted process (February 2020 & July 2023) for administering CIL monies, 80% of the total amount collected goes towards funding strategic borough-wide infrastructure that has been included on the Council’s SPP. 5% to the Borough Council for administration costs; and 15% neighbourhood portion to the Local Spending Boards (and in the case of Claygate, to the Parish Council) for local projects to support current growth.
The remaining CIL receipts are then allocated (post allocation to SANG) as:
15% of CIL is ringfenced for the implementation of joint EBC & SCC public realm and active travel projects. 73% of CIL is allocated through the SPP created by the SCILWG and approved by Cabinet for strategic borough-wide infrastructure that will be required to bring forward development and enable future growth; and 12% of CIL is ringfenced for maintenance purposes as agreed and approved through the capital application programme, Cabinet and Council.
1.2At their meeting on 3 June 2025, the SCILWG considered projects submitted by strategic infrastructure providers for inclusion on the SPP. See Appendix 1 for the minutes of this meeting.
1.3When discussing each project and recommending funding priorities, the SCILWG considered whether the schemes are eligible for strategic CIL funding and whether they are infrastructure as defined by the Planning Act 2008. Section 216 (2) of the Act defines ‘infrastructure’ to include:
(a) roads and other transport facilities, (b) flood defences, (c) schools and other educational facilities, (d) medical facilities, (e) sporting and recreational facilities, and (f) open spaces.
1.4The SCILWG also noted that any funded projects through strategic CIL funds should assist in meeting the infrastructure needs created by new development to support and enable future growth of the borough.
1.5Those projects recommended to Cabinet by the SCILWG for inclusion on the SPP List are set out in Appendix 2. These focus on EBC projects that align with the council’s Vision and the current Local Plan. Also identified are joint EBC and SCC projects that form part of the Council’s and County Council’s shared place-making and active travel ambitions.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2025-26 Strategic Community Infrastructure Levy (CIL): Strategic Priority Programme (SPP)Report | 4 pages | DownloadRead as text |
PDF |
Minutes: SCILWG: 030625 /25Appendix 1 | 4 pages | Download |
Follow Cabinet at Elmbridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Oct 2026 | Old Post Office EsherView the decision text for item 22/26 | Decided | Open |
| 16 Sep 2026 | Disposal of land in Oaken Lane, Claygate, EsherView the decision text for item 15/26 | Decided | Open |
| 16 Sep 2026 | Water Play Strategy UpdateView the decision text for item 16/26 | Decided | Open |
| 16 Sep 2026 | Elmbridge Local Plan 2039: Notice of commencement of plan-making and Local Plan timetableView the decision text for item 17/26 | Decided | Open |
| 16 Sep 2026 | 2026/27 Revenue and Capital Budget Update - Quarter 1View the decision text for item 19/26 | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.