Housing Delivery Scheme - Local Authority Housing Fund Round 4

Decided Executive 1 paper

AI summaryElmbridge Cabinet backed Local Authority Housing Fund Round 4, using £1.189m grant to buy four homes with no new council funding required.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedAcquire four homes: two for Afghan resettlement, two for temporary accommodation.
Money£1.189m grant, plus around £900,000 councilCouncil contribution covered by existing underspends, no new funding requested.
What happens nextAcquire four properties by end March 2027Through the council's existing property acquisition process.
Who it affectsAfghan resettlement and homeless householdsAnd Elmbridge's supply of in-borough temporary accommodation.

What was decided

The council agreed to participate in Round 4 of the Local Authority Housing Fund, accepting an indicative government grant of £1.189 million to deliver four properties in the borough. Report 2.1, 2.2

Two of the homes will provide temporary accommodation and two will be for Afghan resettlement, with the council expected to contribute around £900,000 of its own capital. Report 2.1, 2.2

The council's own contribution will come from an unspent Bridging Hotel balance of just under £1.9 million and from about £400,000 of an existing £1.4 million temporary accommodation budget, so no new funding is being sought. Report 3.1, 3.2, P17

Why

Three earlier LAHF rounds have delivered 31 properties in Elmbridge using £7.76 million of government funding and £8.5 million of council funds, with a further 10 under offer as of February 2026. Report 1.2, 1.3

The council wants to grow its in-borough temporary accommodation because 158 households were in temporary accommodation in quarter three of 2025/26, and to increase the affordable housing it owns. Report 2.3

Owning more temporary accommodation is expected to reduce reliance on costly privately-owned placements, which carry annualised net costs of £20,000 to £25,000 per placement to the council. Report P17, P19

What happens next

The council will enter a new memorandum of understanding with the Ministry of Housing, Communities and Local Government so the grant can be drawn down this financial year. Report 4.2, P21

The four homes will be bought and refurbished through the existing property acquisition process, with delivery required before the end of March 2027. Report 4.1, 4.2

The Afghan resettlement properties will be let first under the government's One Allocation Policy, then through the council's Allocations Policy; the temporary accommodation units will be let under the council's temporary accommodation protocol. Report 4.3, P22

The money

  • £1.189 million Indicative Round 4 government grant allocation for Elmbridge Report 2.1, P19
  • £520,000 Indicative grant share for two temporary accommodation properties Report 2.1
  • £669,000 Indicative grant share for two Afghan resettlement properties Report 2.1
  • around £900,000 Estimated council capital contribution to Round 4 Report 2.2
  • just under £1.9m Unspent Bridging Hotel funding earmarked for Afghan resettlement homes Report 3.1
  • £1.4 million Uncommitted balance in existing temporary accommodation capital budget Report 3.2
  • approximately £400,000 Council contribution to Round 4 temporary accommodation from existing budget Report 3.2
  • £7.76 million Total government funding received by Elmbridge under earlier LAHF rounds Report 1.2
  • £8.5 million Total council funds committed under earlier LAHF rounds Report 1.2
  • £16.3 million Combined LAHF funding (government plus council) in Elmbridge to date Report 1.3
  • £20,000 - £25,000 Annualised net cost per privately-owned temporary accommodation placement Report P17

Options considered

  • Chosen: Participate in LAHF Round 4. Accesses £1.189m external funding to grow temporary accommodation and affordable housing stock while the council's own contribution is covered by existing underspends. Report 2.1, 2.2, 3.1, 3.2, P17

Implications

  • Financial: No new capital funding is requested; the council's around £900,000 contribution is met from the Bridging Hotel underspend and existing temporary accommodation budget, and the grant means the council is not bearing the full cost. Report 2.2, 3.1, 3.2, P17, P19
  • Financial: Adding four council-owned homes is expected to ease revenue pressure from privately-owned temporary accommodation placements costing £20,000 to £25,000 a year each. Report P17, P19
  • Legal: A new memorandum of understanding with the Ministry of Housing, Communities and Local Government is required to draw down the grant. Report 4.2, P21
  • Equalities: The two Afghan resettlement homes will be restricted on first letting to households on the Afghan Resettlement Programme without settled accommodation, under the government's One Allocation Policy. Report 4.3, P22
  • Equalities: The two temporary accommodation properties will help meet the council's statutory homelessness duties and wider pressure, with no restrictions on letting. Report P23
  • Climate: Property choice and refurbishment will be shaped by the council's net zero by 2050 target and the new Decent Homes Standard, which requires social housing to reach EPC band C by 1 April 2030 unless exempt. Report P20
  • Risk: Anti-fraud, due diligence and conveyancing requirements from the prospectus are considered low risk because the council has already met them in earlier rounds. Report P24

Who and where

  • Households on the Afghan Resettlement Programme who have not received settled accommodation Report 2.1, P22
  • Households needing temporary accommodation in Elmbridge, including the 158 placed in Q3 2025/26 Report 2.3, P23
  • The council's housing, homelessness and asset base Report 2.3, 4.1, P19

Timeline

  • December 2022: Ministry of Housing, Communities and Local Government launched Round 1 of LAHF Report 1.1
  • June 2023: Round 2 of LAHF launched; council agreed participation in July 2023 Report 1.2, 3.1
  • March 2024: Round 3 of LAHF launched Report 1.2
  • February 2026: 31 properties acquired under LAHF in Elmbridge with 10 further under offer Report 1.3
  • Q3 2025/26: 158 households in temporary accommodation in Elmbridge Report 2.3
  • by the end of March 2027: Round 4 properties to be delivered Report 4.2
  • 1 April 2030: New and existing social housing expected to meet EPC band C under the new Decent Homes Standard Report P20
  • 2050: Council's net zero carbon target Report P20

Plain English for the jargon

  • LAHF: Local Authority Housing Fund, a government programme to help councils house Afghan and Ukrainian resettlement households and reduce homelessness.
  • MHCLG: Ministry of Housing, Communities and Local Government.
  • MoU: Memorandum of Understanding, a formal agreement to access the grant.
  • ARP: Afghan Resettlement Programme.
  • EPC: Energy Performance Certificate, rating a property's energy efficiency from A to G.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item57/25

Resolved

View the decision text for item 57/25
Word for word from the decision Elmbridge published for this meeting. Source: mygov.elmbridge.gov.uk

Follow this further

Built from Elmbridge's papers

What the report saysPro

Report to Cabinet, 4 pages

Background

1.1In December 2022 the Ministry of Housing, Communities and Local Government (MHCLG) launched the first round of the LAHF programme to support councils across England to provide housing to Afghan and Ukrainian households that were unable to find settled accommodation through the UK government resettlement schemes

1.2An additional two rounds of LAHF funding have been launched, round two in June 2023 with round three in March 2024. In total, Elmbridge has so far received £7.76 million from government funding to deliver additional housing. The council has committed £8.5 million of its own funds.

1.3The combined £16.3 million allocated under LAHF within Elmbridge has enabled the council, as of February 2026, to acquire 31 additional properties within the borough to provide long term accommodation to Afghan and Ukrainian households, as well as increasing our stock of in borough temporary accommodation. The council is currently under offer on 10 additional properties.

2 LAHF Round 4

2.1Under Round 4 of LAHF, Elmbridge has been given an indicative allocation of £1.189 million to deliver four properties. Two of these properties will be for temporary accommodation to help meet wider homelessness pressures, and the indicative grant allocation for temporary accommodation is £520,000 to acquire two properties. For the two Afghan resettlement properties we have an indicative allocation of £669,000 to provide one home with at least two bedrooms and a second homes, with at least four bedrooms.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Housing Delivery Scheme: Local Authority Housing Fund Round 4Report 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Elmbridge

Search all
  1. Housing Delivery Scheme - Local Authority Housing Fund Round 4This decision
  2. 2025 Housing Delivery Test Action PlanDecided
  3. Housing Delivery Test Action Plan 2024Decided
  4. Draft Housing Delivery Test Action PlanDecided
  5. Draft Housing Delivery Action PlanDecided
  6. Local Housing Company Delivery Models - UpdateDecided

More from Elmbridge Cabinet

All decisions
MeetingDecisionOutcome
27 Oct 2026 Old Post Office EsherView the decision text for item 22/26 Decided Open
16 Sep 2026 Disposal of land in Oaken Lane, Claygate, EsherView the decision text for item 15/26 Decided Open
16 Sep 2026 Water Play Strategy UpdateView the decision text for item 16/26 Decided Open
16 Sep 2026 Elmbridge Local Plan 2039: Notice of commencement of plan-making and Local Plan timetableView the decision text for item 17/26 Decided Open
16 Sep 2026 2026/27 Revenue and Capital Budget Update - Quarter 1View the decision text for item 19/26 Decided Open