Elmbridge Borough Council
Cabinet, Wednesday 18 March 2026 at 7.00pm

Green Spaces Contract Extension

Decided Executive 1 paper

AI summaryElmbridge Cabinet approves two-year extension of green spaces contracts with Glendale and Safeplay to September 2029, with £120,650 annual extra budget for grounds maintenance funded from reserves.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedTwo years beyond original August 2027 end date
Money£120,650 per year extraFrom April 2026, funded from Working Balances Reserve in 2026/27
What happens nextFinal KPI terms to be agreedDelegated to Strategic Director and portfolio holder
Who it affectsGlendale and Safeplay contractsCovers parks, cemeteries and play area inspections

What was decided

Cabinet approved a two-year contract extension with Glendale for Lots 1 and 2 (green spaces and cemeteries) through to September 2029. Report P9

Cabinet approved a two-year contract extension with Safeplay for Lot 3 (play area inspections) through to September 2029. Report P10

Cabinet recommended to Council budget growth of £120,650 per year for grounds maintenance from April 2026 to September 2029, funded in 2026/27 from the Working Balances Reserve, and delegated authority to the Strategic Director Place and Community, in consultation with the Leisure, Culture and Commercial Strategy portfolio holder, to approve final Service Credit (default) mechanism details. Report P11, P12

Why

The extension is needed to ensure continuity of service beyond the vesting date of the new Unitary Authority and to give the new authority time to decide on future delivery, with the timeline aligning to grounds maintenance contract end dates at other councils in the new authority. Report P3, P49

Glendale's performance has been poor, with 87 rectifications and 31 defaults issued in 2024/25 and 86 rectifications and 5 defaults in 2025/26, and the current contract price is judged not to support the required level of quality, frequency or responsiveness. Report P18, P23

Other delivery options (working with a neighbour, in-house delivery, re-tendering) have been ruled out as impractical or too expensive in the time available before vesting. Report P47, P49

What happens next

Final details of KPI-based service credit (default) mechanism to be agreed, with KPIs covering bin and litter collection, grass cutting, hedge cutting and sport provision, and delegated to the Strategic Director Place and Community in consultation with the portfolio holder. Report P53, P54, P55, P56, P57, P58

Close monitoring of Glendale's performance will continue through the Green Spaces Monitoring Officer and the Ranger, with digitisation of grounds maintenance plans due to complete by November 2026. Report P26

A decision on the longer-term delivery of grounds maintenance will need to be in place by September 2028 to allow 12 months mobilisation to go live on 1 September 2029, for the new Unitary Council to take forward. Report P61

The money

  • £120,650p.a. Recommended budget growth for the Grounds Maintenance Contract from April 2026 to September 2029, funded in 2026/27 from the Working Balances Reserve Report P11, P62
  • £247,737 per year Increase to contract value proposed by Glendale across Lots 1 and 2 to reflect inflationary and delivery pressures and additional resources Report P33, P40

Options considered

  • Chosen: Extend the current contracts with Glendale and Safeplay to September 2029. Ensures continuity beyond Unitary vesting date, gives new authority time to decide future delivery, and reflects true cost of the service Report P3, P49
  • Rejected: Work with a neighbouring authority to take on grounds maintenance prior to LGR. Informal discussions found no neighbour has the capacity or machinery to take on Elmbridge grounds maintenance before Local Government Reorganisation Report P47
  • Rejected: Bring grounds maintenance in-house before vesting. Likely significantly more expensive, no accessible depot, and longer term option better suited to the new Unitary Council Report P47
  • Rejected: Procure a new external contractor. Would need about 12 months to procure and 12 months to mobilise, could not be completed before the new council is operational, and benchmarking suggests a similar price to the proposed extension Report P47

Implications

  • Financial: Additional contract costs of £120,650 per year for the Grounds Maintenance Contract from April 2026 to September 2029, funded in 2026/27 from the Working Balances Reserve. Report P62
  • Legal: The contract modification is considered under Regulation 72 of the Public Contract Regulations 2015, which allows changes for additional services up to 50% of the original contract value where a change of supplier cannot be made for economic or technical reasons. Report P38, P64
  • Risk: Failure to appoint a contractor would leave a gap in provision and a reputational and health and safety risk to users of green spaces; without the financial uplift, service quality issues and low satisfaction are likely to persist and the new authority will inherit a poorly performing service. Report P42, P66
  • Equalities: Equality implications are recorded as contained within the report. Report P65
  • Climate: The council will continue to work with the contractor to reduce carbon impact, including composting and introducing battery powered equipment as technology allows. Report P63
  • Staffing: The proposed uplift includes additional resources of 3000 hours of staff time (1.5 FTE) focusing on grass, horticulture, hedges, hard surface maintenance, leaf clearance and path sweeping, and additional pay support to align Glendale staff to the London Living Wage has already been provided. Report P26, P35

Who and where

  • Glendale Countryside Ltd, contractor for Lots 1 and 2 (green spaces and cemeteries) Report P4, P15, P33
  • Safeplay Ltd, contractor for Lot 3 (play area inspections) Report P4, P15, P32
  • Elmbridge residents and members who use parks, cemeteries and play areas Report P23, P42
  • The new East Surrey Unitary Council, which will inherit the contract and decide on longer-term delivery Report P3, P47, P49
  • The council's Green Spaces team, including a newly appointed Green Spaces Monitoring Officer and Green Spaces Ranger Report P26
  • Neighbouring authorities within the new Unitary Council whose grounds maintenance contracts end on a similar timeline Report P3

Timeline

  • April 2022: Contracts for Lots 1, 2 and 3 awarded Report P14
  • 1 September 2022: Contracts start Report P14
  • 1 April 2026: Proposed start of increased contract payments to Glendale Report P40
  • November 2026: Digitisation of grounds maintenance plans and data due to complete Report P26
  • April 2027: New Unitary Council vests Report P3, P47
  • 30 August 2027: Original 5-year contract term ends Report P2, P15
  • September 2028: Deadline for new Unitary Council to decide longer-term delivery model to allow 12 months mobilisation Report P61
  • 1 September 2029: Contract extension ends and any new arrangements go live Report P3, P61

Plain English for the jargon

  • LGR: Local Government Reorganisation, the creation of the new Unitary Council
  • KPI: Key Performance Indicator, used to measure contract delivery
  • FTE: Full Time Equivalent, a measure of staffing resource
  • Lot 1: Green Spaces ground maintenance contract
  • Lot 2: Cemeteries ground maintenance contract
  • Lot 3: Play Area Inspections contract
  • Rectification: A notice requiring the contractor to put right works not completed to the required standard
  • Default: A formal contractual failure notice issued for non-completion within contract terms
  • Service Credit (default) mechanism: A contractual deduction linked to failure to meet agreed performance levels
  • Vesting date: The date on which the new Unitary Council takes on responsibility for services
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item59/25

Resolved

View the decision text for item 59/25
Word for word from the decision Elmbridge published for this meeting. Source: mygov.elmbridge.gov.uk

Follow this further

Built from Elmbridge's papers

What the report saysPro

Report to Cabinet, 7 pages

Executive summary

Elmbridge Borough Council recognises the value of its green spaces to our communities and are committed to maintaining and improving our green spaces to ensure they meet the high standards rightly expected by our residents.

The contracts for the ground maintenance of the Council’s Green Spaces and Cemeteries (Lots 1 and 2) were awarded in 2022 to Glendale with the Play Area Inspections (Lot 3) awarded to Safeplay both on a 5-year contract with the option of a 2 year (1+1) extension. The original 5-year term comes to an end on 30 August 2027.

It is important to secure the extension to the Green Spaces contract to ensure a continuity of service beyond the vesting date of the new Unitary Authority but also reflect the true cost of maintaining the service. The new authority will need to make decisions on the future delivery of the service in the context of its new boundaries, but this will need some careful consideration and will take some time to evaluate and implement by the end of the extension in September 2029. This timeline also aligns to the grounds maintenance contract completion dates with some of the other authorities within the new Unitary Authority.

Both contractors have been written to, in order to extend the existing contracts. Safeplay Ltd (lot 3) have confirmed the extension under the current terms and conditions. Glendale Countryside Ltd (lots 1 and 2) have confirmed their willingness to extend the contract but due to commercial pressures have confirmed that there would need to be an increase in the contract value as set out in the report.

Glendale have set out the current inflationary and delivery pressures that have been impacting the delivery of the contract and set out improvements that could also be delivered from April 2026 including additional staffing resources across the contract. These improvements along with the breakdown of additional costs are set out in the body of the report.

It is proposed that the additional contract payments would be based on Key Performance Indicators (KPI`s) and the proportion of the contract specification that is delivered, with the final details to be agreed.

OFFICIAL OFFICIAL

Recommendation that:

1. Cabinet approves the contract extension with Glendale (Lots 1 and 2) for 2 years through to September 2029;

2. Cabinet approves the contract extension with Safeplay (Lot3) for 2 years through to September 2029;

3. Recommended to Council that budget growth of £120,650p.a. for the Grounds Maintenance Contract from April 2026 to September 2029 to be funded in 2026/27 from the Working Balances Reserve; and

4. Authority be delegated to the Strategic Director Place and Community, in consultation with the Portfolio Holder for Leisure, Culture and Commercial Strategy, to approve the final details of the Service Credit (default) mechanism.

Report

Background

2. The current contracts for maintenance of the Green Spaces (Lot 1), Cemeteries (Lot 2) and Play Area Inspections (Lot 3) were awarded in April 2022, to start on 1 September 2022.

3. The contracts for the management of the council's green spaces and cemeteries were awarded to Glendale Countryside Ltd with the play area inspections awarded to Safeplay Ltd both on a 5 year contract with the option of a 2 year (1+1) extension. The original 5 year term comes to an end on 30 August 2027.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Green Spaces Contract ExtensionReport 7 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Elmbridge

Search all
  1. Green Spaces Contract ExtensionThis decision
  2. Green Spaces PSPOs consultation outcomesDecided
  3. Green Spaces Income OpportunitiesDecided
  4. Green Spaces PSPO consultation outcomesDecided
  5. Green Spaces PSPO consultationDecided
  6. Green Spaces Contract AwardDecided

More from Elmbridge Cabinet

All decisions
MeetingDecisionOutcome
27 Oct 2026 Old Post Office EsherView the decision text for item 22/26 Decided Open
16 Sep 2026 Disposal of land in Oaken Lane, Claygate, EsherView the decision text for item 15/26 Decided Open
16 Sep 2026 Water Play Strategy UpdateView the decision text for item 16/26 Decided Open
16 Sep 2026 Elmbridge Local Plan 2039: Notice of commencement of plan-making and Local Plan timetableView the decision text for item 17/26 Decided Open
16 Sep 2026 2026/27 Revenue and Capital Budget Update - Quarter 1View the decision text for item 19/26 Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies