Elmbridge Borough Council
Cabinet, Monday 13 July 2026 at 7.00pm

2026-27 Strategic Community Infrastructure Levy (CIL) - Strategic Priority Programme (SPP)

Decided Executive 2 papers

AI summaryElmbridge Cabinet to agree 2026/27 Strategic Priority Programme list of infrastructure projects, with £6,342,000 currently in the SPP fund and £6,793,000 in indicative project asks.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedStrategic infrastructure projects for 2026/27 to be agreed
Money£6,342,000 in SPP fundIndicative project asks total £6,793,000; rises 30 June 2026
What happens nextFunding applications open Summer 2026SCILWG to consider in Autumn 2026, then Cabinet
Who it affectsStrategic infrastructure providers in ElmbridgeIncluding Surrey Police, NHS, schools, Surrey County Council

What was decided

Cabinet is asked to agree the infrastructure projects recommended by the Strategic CIL Working Group for inclusion on the 2026/27 Strategic Priority Programme List. Report P4, P5, 1.5

Inclusion on the list does not guarantee funding: providers must still submit detailed applications for Cabinet to decide on actual awards. Report P2, 1.9, 2.2

Five named projects need further information from applicants before funding decisions can be made. Report 2.3, P30, P31, P33, P34, P35, P36

Why

CIL Regulations and the Council's adopted process require 80% of CIL receipts to fund strategic borough-wide infrastructure on the SPP list, and SCILWG met on 1 June 2026 to review submitted projects. Report 1.1, 1.2, P7, P10

The Working Group assessed each project against strategic CIL eligibility and the Planning Act 2008 definition of infrastructure, aiming to support the Council's vision of a sustainable, thriving Elmbridge and to mitigate development impacts. Report 1.3, P16, 1.4, 1.6

What happens next

Projects on the SPP List will be invited to apply for CIL funding in Summer 2026; SCILWG will consider applications in Autumn 2026 and pass recommendations to Cabinet for decision. Report 3.1, 2.1

Applicants for five projects must supply extra information on contracts, consultation, budgets, costs, or facility details before funding can be considered. Report 2.3, P30, P31, P33, P34, P35, P36

Projects extending beyond 1 April 2027 (vesting day for the new East Surrey Authority) are listed in Appendix 3 for information, to support the new authority. Report P3, 1.10, P48

The money

  • £6,342,000 SPP fund balance as of 31 March 2026 Report P2, 2.2, P39
  • £6,793,000 Indicative total value of projects recommended for SPP List inclusion in 2026/27 Report P2, 2.2, P39

Options considered

  • Chosen: Agree the projects recommended by SCILWG for inclusion on the 2026/27 SPP List. Recommended in the report; aligns with CIL Regulations and supports strategic infrastructure needs. Report P4, P5, 1.5

Implications

  • Financial: Indicative project asks of £6,793,000 exceed the £6,342,000 currently in the SPP fund; only the amount available can be allocated, and the fund is expected to rise after 30 June 2026. Report P2, 2.2, P39
  • Legal: Funding priority decisions must conform with the Planning Act 2008 and the CIL Regulations 2010 (as amended). Report P41, 1.3, P16
  • Other: Environmental, equality, risk and community safety implications are recorded as none for this report. Report P40, P42, P43, P44

Who and where

  • Strategic infrastructure providers in Elmbridge, including Surrey Police, the NHS, Chatterbus, Surrey County Council, and EBC project teams Report 1.7, 1.8, P22
  • Residents of Walton-on-Thames and Cobham, where additional SEN school places are proposed Report 1.7, P22
  • Users of Lower Green play facilities, Esher Station, Oxshott Surgery, Cobham Community Swimming Pool, and LCWIP cycling and walking routes Report 1.6, 1.7, P30, P31, P33, P34, P35, P36
  • The new East Surrey Authority (from 1 April 2027), which will inherit longer-term projects listed in Appendix 3 Report P3, 1.10, P48

Timeline

  • 31 March 2026: SPP fund balance stood at £6,342,000 Report P2, 2.2
  • 1 June 2026: Strategic CIL Working Group met and recommended projects for the SPP list Report P1, 1.2, P48
  • 30 June 2026: Additional CIL receipts expected to be allocated, increasing the SPP fund Report P2, 2.2, P39
  • 13 July 2026: Cabinet meeting considers the 2026/27 SPP list recommendation Report P4, P5
  • Summer 2026: Projects on the SPP list invited to submit CIL funding applications Report 3.1, 2.1
  • Autumn 2026: SCILWG to consider applications and recommend awards to Cabinet Report 3.1, 2.1
  • 1 April 2027: Vesting day for the new East Surrey Authority; longer-term SPP projects transfer for reference Report P3, 1.10, P48

Plain English for the jargon

  • CIL: Community Infrastructure Levy, a charge that local authorities can levy on new development to fund infrastructure.
  • SPP: Strategic Priority Programme, the list of strategic borough-wide infrastructure projects eligible for CIL funding.
  • SCILWG: Strategic Community Infrastructure Levy Working Group, which reviews and recommends SPP projects.
  • SANG: Suitable Alternative Natural Greenspace, funded from CIL before the SPP allocation.
  • LCWIP: Local Cycling and Walking Infrastructure Programme.
  • SEN: Special Educational Needs.
  • Vesting day: 1 April 2027, the date the new East Surrey Authority comes into being.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8/26

Resolved

View the decision text for item 8/26
Word for word from the decision Elmbridge published for this meeting. Source: mygov.elmbridge.gov.uk

Follow this further

Built from Elmbridge's papers

What the report saysPro

Report to Cabinet, 5 pages

Executive summary

This report sets out the infrastructure projects to be considered for inclusion on the Strategic Priority Programme (SPP) List for the municipal year 2026/27 as recommended by the Strategic Community Infrastructure Levy (CIL) Working Group (SCILWG) following their meeting on 1 June 2026.

As of 31 March 2026, the SPP fund held a balance of £6,342,000. This balance is expected to increase following the allocation of additional funding at the end of the next quarter, on 30 June 2026. The SCILWG has recommended a number of projects for inclusion on the SPP list that are expected to commence during 2026/27, with a total indicative value of £6,793,000. The SCILWG recognises that inclusion on the SPP list does not guarantee that funding will be allocated to a project.

Additional projects with a medium to long term timeline that extend beyond vesting day (01 April 2027) of the new East Surrey Authority have also been included on the SPP list in Appendix 3. These have been included for information purposes and to support the new authority.

Recommended: that

(a) Cabinet consider and agree the infrastructure projects recommended for inclusion on the Strategic Priority Programme (SPP) List for the municipal year.

Report:

1. The Strategic Priority Programme 2026-27

1.1In accordance with the CIL Regulations and the Council’s adopted process (February 2020 & July 2023) for administering CIL monies, 80% of the total

OFFICIAL OFFICIAL

amount collected goes towards funding strategic borough-wide infrastructure that has been included on the Council’s SPP.

 5% to the Borough Council for administration costs; and  15% neighbourhood portion to the Local Spending Boards (and in the case of Claygate, to the Parish Council) for local projects to support current growth.

The remaining CIL receipts are then allocated (post allocation to SANG) as:

 15% of CIL is ringfenced for the implementation of joint EBC & SCC public realm and active travel projects.  73% of CIL is allocated through the SPP created by the SCILWG and approved by Cabinet for strategic borough-wide infrastructure that will be required to bring forward development and enable future growth; and  12% of CIL is ringfenced for maintenance purposes as agreed and approved through the capital application programme, by Cabinet and Council.

1.2At their meeting on 1 June 2026, the SCILWG considered projects submitted by strategic infrastructure providers for inclusion on the SPP. See Appendix 1 for the minutes of this meeting.

1.3When discussing each project and recommending funding priorities, the SCILWG considered whether the schemes are eligible for strategic CIL funding and whether they are infrastructure as defined by the Planning Act 2008. Section 216 (2) of the Act defines ‘infrastructure’ to include:

(a) roads and other transport facilities, (b) flood defences, (c) schools and other educational facilities, (d) medical facilities, (e) sporting and recreational facilities, and (f) open spaces.

1.4The SCILWG also noted that any funded projects through strategic CIL funds should assist in meeting the infrastructure needs created by new development to support and enable future growth of the borough.

1.5Those projects recommended to Cabinet by the SCILWG for inclusion on the SPP List are set out in Appendix 2.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2026-27 Strategic Community Infrastructure Levy (CIL): Strategic Priority Programme (SPP)Report 5 pages DownloadRead as text
PDF
Minutes SCILWG 01.06.26 /26Appendix 1 4 pages Download

At this meeting

Whole meeting

On this subject at Elmbridge

Search all
  1. 2026-27 Strategic Community Infrastructure Levy (CIL) - Strategic Priority Programme (SPP)This decision
  2. 2025/26 Strategic Community Infrastructure Levy (CIL) Strategic Priority Programme applicationsDecided
  3. 2025/26 Strategic Community Infrastructure Levy (CIL) Strategic Priority Programme applicationsDecided
  4. 2025-26 Strategic Community Infrastructure Levy (CIL) - Strategic Priority Programme (SPP)Decided
  5. Risk Management Strategy & Strategic Risk Register and the RMP report on Community Support ServicesDecided
  6. 2024/25 Strategic Community Infrastructure Levy (CIL) Strategic Priority Programme applicationsDecided

More from Elmbridge Cabinet

All decisions
MeetingDecisionOutcome
27 Oct 2026 Old Post Office EsherView the decision text for item 22/26 Decided Open
16 Sep 2026 Disposal of land in Oaken Lane, Claygate, EsherView the decision text for item 15/26 Decided Open
16 Sep 2026 Water Play Strategy UpdateView the decision text for item 16/26 Decided Open
16 Sep 2026 Elmbridge Local Plan 2039: Notice of commencement of plan-making and Local Plan timetableView the decision text for item 17/26 Decided Open
16 Sep 2026 2026/27 Revenue and Capital Budget Update - Quarter 1View the decision text for item 19/26 Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies