East Surrey Shadow Authority Executive, Monday 20 July 2026 at 2.00pm

Implementation Programme Assurance Update

Decided Executive 3 papers

AI summaryEast Surrey Shadow Executive notes progress on local government reorganisation programme, with delivery confidence rated amber and £29.379m of implementation funding now approved.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedProgress, risks and funding position
Money£29.379m approvedTotal approved Implementation Fund to date
What happens nextContinue critical milestone deliveryStrengthened monitoring via Vesting Day Readiness Board
Who it affectsEast Surrey residents and councilPre vesting day transition programme

What was decided

The Shadow Executive noted progress against critical milestones and the overall programme assurance position. Report P4, P12

The Shadow Executive noted the current programme risk profile and emerging risks. Report P4, P35

The Shadow Executive noted the latest Implementation Fund position. Report P4, P37

Why

The Shadow Authority Constitution requires the Shadow Executive to oversee the transition programme and keep the Implementation Plan under review. Report P5, P51

Article 23 of the Surrey (Structural Changes) Order 2026 requires the East Shadow Authority to keep the Implementation Plan under review and revise it as necessary. Report P51

Overall delivery confidence is assessed as amber due to programme pace and complexity, emerging IT and Data cost pressures, and the need to finalise service configuration decisions. Report P31

What happens next

Continued delivery against critical milestones, with strengthened monitoring through the new Vesting Day Readiness Board and ongoing management of risks and financial pressures. Report P22, P62

The Implementation Programme Board will continue tight control of spend against the Implementation Fund, with regular reporting to the Shadow Executive. Report P44

From the following month, the Implementation Fund breakdown will include spend against the £0.900m provided to East Surrey by MHCLG. Report P44

The money

  • £1.2m Further Implementation Fund money committed for ERP system work since the previous meeting Report P37
  • 29.379 Total approved Implementation Fund funding (£m, as at June 2026) Report P40
  • 0.900 Funding provided to East Surrey by MHCLG, to be included in reporting from next month (£m) Report P44

Options considered

  • Chosen: Accept the recommendations to note progress, risks and the funding position. Required by the Constitution and by Article 23 of the Surrey (Structural Changes) Order 2026 to keep the Implementation Plan under review Report P5, P10, P51
  • Rejected: Not accept the recommendations. Could hinder the Shadow Executive in discharging its functions, risk inconsistency in reporting and reduce public confidence in the transition Report P10

Implications

  • Legal: Article 23 of the Surrey (Structural Changes) Order 2026 requires the East Shadow Authority to keep the Implementation Plan under review. Report P51
  • Risk: Overall delivery confidence is rated amber, with the Vesting Day Readiness Board now providing focused senior oversight to unblock delivery issues. Report P22, P31
  • Staffing: Workforce is a key dependency; the People, Workforce and Culture workstream is coordinating organisational design, consultation and employment compliance for Vesting Day readiness. Report P56
  • Equalities: No direct equality implications from the recommendations; Equality Impact Assessments will be undertaken where future decisions require. Report P58
  • Climate: No direct climate change and sustainability implications from the recommendations. Report P60

Who and where

  • East Surrey Council and its residents Report P2, P46
  • All Surrey Councils' Chief Executives, Commissioners and Interim Heads of Paid Service for East and West Surrey Report P32
  • Future unitary councils being established by Vesting Day Report P22

Timeline

  • January to February 2026: Initial funding of 10.226 (£m) agreed at Implementation Programme Board Report P40
  • March 2026: Additional approved funding of 10.763 (£m) Report P40
  • May 2026: Additional ERP funding of 1.200 (£m) approved Report P40
  • June 2026: Updated approved funding figure of 29.379 (£m) Report P40
  • 9 June 2026: Shadow Authority Executive agreed the approach to LGR programme monitoring and assurance Report P1
  • July 2026: Informal Executive briefing consultation held Report P33
  • Vesting Day: Target date for the new unitary councils to be established Report P12

Plain English for the jargon

  • LGR: Local Government Reorganisation
  • PMO: Programme Management Office
  • ERP: Enterprise Resource Planning system, an integrated software platform that brings together Finance, HR and Procurement functions
  • Section 24: A safeguard used during local government reorganisation to protect new councils from limiting decisions by predecessor councils
  • MHCLG: Ministry of Housing, Communities and Local Government
  • IPB: Implementation Programme Board
  • SRO: Senior Responsible Officer
  • RAG: Red, Amber, Green rating used to indicate progress status
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item18/E

Resolved

View the decision text for item 18/E
Word for word from the decision Elmbridge published for this meeting. Source: mygov.elmbridge.gov.uk

Follow this further

Built from Elmbridge's papers

What the report saysPro

Report to East Surrey Shadow Authority Executive, 8 pages

Purpose of the report

The East Surrey Shadow Authority Executive agreed an approach to Local Government Reorganisation (LGR) programme monitoring and assurance on 9 June 2026. This report sets out the latest position in line with that approach. Also included are updates on the top programme risks and the latest position related to the implementation fund.

The Shadow Executive is, jointly with the West Shadow Executive, responsible for keeping under review, and revising as necessary, the Implementation Plan for local government reorganisation in Surrey1 and managing the overall Transition Programme. Recommendations are made to the Shadow Executive for arrangements to support these functions.

Recommendations It is recommended that the Shadow Executive:

1. Notes progress against critical milestones and the overall programme assurance position 2. Notes the current programme risk profile and emerging risks 3. Notes the latest Implementation Fund position.

Reason for recommendations

1. Under the Shadow Authority’s Constitution, the Shadow Executive is responsible for overseeing and managing the transition programme, including maintaining the Implementation Plan and taking the key executive decisions needed to establish the new council. Agreeing the recommendations in this report will support the Shadow Executive to discharge these functions.

2. The Shadow Executive will receive regular programme updates providing assurance on overall delivery and highlighting areas requiring direction or decision.

1 Future Surrey - Implementation Plan -

https://www.surreylgrhub.gov.uk/downloads/file/18/implementation-plan-05-26

OFFICIAL OFFICIAL

Options, including alternatives (if any) 3. The Surrey (Structural Changes) Order 2026 (SCO) requires the Shadow Authority to keep the Implementation Plan under review and, as set out above, the Constitution confirms the role the Shadow Executive has in this. Whilst the Shadow Executive could choose not to accept the recommendations this could hinder their ability to discharge these functions and risks inconsistency in reporting and reduced public confidence in the transition process.

4. Overall, the programme continues to make progress against key milestones set out in the Implementation Plan; however, the pace and complexity of the programme and emerging cost pressures (particularly within the IT and data theme) are beginning to impact the risk profile and will require close management over the coming months.

Summary Programme Assurance and Critical Milestones 5. The programme remains broadly on track against its critical path to Vesting Day, with several key enabling milestones delivered since the previous meeting (as listed below). However, delivery confidence is increasingly dependent on maintaining pace across interdependent themes, particularly IT & data, workforce, and governance.

6. The Implementation Team has been working to finalise and track progress against critical milestones. Since the previous meeting of the Shadow Executive the milestones below have been completed:

Milestone 1. Section 242 enacted 2. Decisions for Fire and Pensions standalone arrangements from Government 3. Key Shadow Authority Committees established and meeting dates agreed 4. Proposed service configurations endorsed by the officer Implementation Programme Board for onward recommendation to Executive Members 5. Member briefings held to cover service configuration recommendations 6. Recruitment commenced for permanent Head of Paid service

7. As part of developing the list of critical milestones the Programme Management Office (PMO) has worked with all programme Themes to map out the critical path to Vesting Day, this can be located in Appendix 1 of this report. A critical

2 Section 24 is a safeguard used during local government reorganisation to help protect new

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Programme Progress & Assurance Update /EAppendix 1 7 pages Download
PDF
Risk Update /EAppendix 2 6 pages Download
PDF
Implementation Programme Assurance UpdateReport 8 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Elmbridge

Search all
  1. Implementation Programme Assurance UpdateThis decision
  2. Implementation Programme UpdateDecided
  3. Implementation Programme UpdateDecided
  4. Implementation Programme UpdateDecided

More from Elmbridge East Surrey Shadow Authority Executive

All decisions
MeetingDecisionOutcome
9 Nov 2026 Implementation Programme UpdateView the decision text for item 6. Decided Open
9 Nov 2026 2026/27 Quarter 1 Budget Monitoring Report of Existing East Surrey CouncilsView the decision text for item 7. Decided Open
9 Nov 2026 Strategic PartnershipsView the decision text for item 8. Decided Open
9 Nov 2026 Equality Diversity and Inclusion ApproachView the decision text for item 9. Decided Open