CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Elmbridge Borough Council
East Surrey Shadow Authority Executive, Tuesday 13 October 2026 at 2.00pm

Implementation Programme Update

Decided Executive 3 papers

AI summaryEast Surrey Shadow Executive notes LGR programme progress, with overall and Children's Theme RAG ratings moved to red following the Surrey SEND inspection; £32.558m Implementation Fund committed.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedProgramme and Children's Theme now red
Money£32.558m committed to datePlus £0.900m MHCLG grant, £0.176m uncommitted
What happens nextRecovery plan and November updateSEND inspection impact review concludes
Who it affectsTransition to new East Surrey CouncilVesting Day readiness and IT&D delivery

What was decided

The Shadow Executive noted continued progress against critical milestones, with 61 of 182 milestones completed since the previous meeting. Report P4, P26, P27, P28, P29, P31, P32, P33, P34, P35

The Shadow Executive noted the movement of the overall programme RAG rating and the Children's Theme RAG rating to red, driven by the Surrey Local Area Partnership SEND inspection running from week commencing 21 September until Friday 9 October 2026. Report P5, P17, P18, P20, P22, P23

The Shadow Executive noted the current programme risk profile, including a new System Readiness risk, and the latest Implementation Fund position of £32.558m committed. Report P6, P7, P52, P56, P59

Why

The Shadow Executive is responsible under the Shadow Authority's Constitution and Article 23 of the Surrey (Structural Changes) Order 2026 for keeping the Implementation Plan under review and managing the transition programme. Report P11, P82

The SEND inspection is diverting staff capacity away from LGR activity, affecting IT&D testing, Section 16 and Inter Authority Agreement work, workforce disaggregation and other readiness tasks, with a thematic review under way to assess impacts and identify rephasing or resource redeployment. Report P17, P18, P22, P24

Programme risks around Shadow Executive decision-making capacity, programme capacity and the newly escalated System Readiness risk remain high scoring; mitigations are in place and Children's Theme Partnerships risk has closed. Report P52, P53, P54

What happens next

Thematic review of SEND inspection impact to conclude, with a recovery plan developed and implemented. Report P91

Continued delivery against critical milestones, with ongoing monitoring through the Vesting Day Readiness Board and active management of risks and financial pressures. Report P92, P93, P94, P95

Further updates to future Shadow Executive meetings, with the next Implementation Programme Update Report due to the November Executive meeting. Report P24, P96

The money

  • £32.558m Total committed Implementation Fund funding across all themes and categories Report P56, P59
  • £0.012m Additional commitments since the September Shadow Executive meeting Report P56
  • £0.900m MHCLG grant allocation to East Surrey Council Report P56, P70, P72
  • £0.176m Uncommitted balance of the £0.900m MHCLG grant Report P72, P75
  • £0.018m Overspend on members' laptops and Microsoft licences against grant budget Report P73
  • £2.2m Severance costs profiled for March 2027 within the forecast Report P66

Options considered

  • Chosen: Note the four recommendations on progress, RAG movement, risks and funding. Supports the Shadow Executive's statutory duty to keep the Implementation Plan under review and maintain oversight of the transition programme Report P11, P14, P82
  • Rejected: Reject or not accept the recommendations. Could hinder the Shadow Executive's ability to discharge its functions and risk inconsistency in reporting and reduced public confidence Report P14

Implications

  • Risk: Overall programme delivery confidence moved to red; Children's Theme red due to SEND inspection impact; System Readiness risk newly escalated; decision-making and programme capacity remain highest-scoring risks. Report P5, P17, P23, P52
  • Financial: Total Implementation Fund committed stands at £32.558m; headroom is expected to remain but further cost pressures, especially in IT and Data, are likely and will be kept under close review. Report P56, P59, P68, P69
  • Financial: East Surrey Council will operate in a very challenging financial environment; decisions by predecessor and shadow authorities must ensure expenditure does not exceed resources available. Report P76, P77
  • Legal: Article 23 of the Surrey (Structural Changes) Order 2026 requires the East Shadow Authority to keep the Implementation Plan under review; this report supports that duty. Report P82, P83
  • Staffing: Transition programme is highly dependent on workforce capacity and specialist skills; no direct staffing implications from the recommendations themselves, but resource pressures continue to be actively monitored. Report P84, P85
  • Equalities: No direct equality implications from the recommendations; Equality Impact Assessments will be undertaken where future decisions require. Report P86, P87
  • Climate: No direct climate change or sustainability implications from the recommendations. Report P88, P89

Who and where

  • East Surrey Shadow Executive and Members Report P11, P48
  • Implementation Team, Surrey Councils' Chief Executives and theme sponsors Report P47, P97
  • Workforce across predecessor and shadow councils involved in LGR delivery Report P85
  • Children's Theme staff and partners, due to SEND inspection diversion Report P17, P18, P22
  • Future residents and service users of the new East Surrey Council Report P76, P83

Timeline

  • 9 June 2026: East Surrey Shadow Executive agreed the LGR programme monitoring and assurance approach Report P1
  • 30 September 2026: Vesting Day Readiness Board agreed the move of programme RAG from amber to red Report P23
  • 1 October 2026: Shadow Executive Members briefed on RAG changes at Informal Executive meetings Report P23, P48
  • Week commencing 21 September until Friday 9 October 2026: Surrey Local Area Partnership SEND inspection period Report P20
  • November 2026: Next Implementation Programme Update Report due to the Executive meeting Report P24
  • March 2027: Severance costs of £2.2m profiled in the forecast Report P66

Plain English for the jargon

  • LGR: Local Government Reorganisation, the restructuring of councils in Surrey into new unitary authorities
  • RAG rating: Red, Amber, Green assurance rating used to indicate programme delivery confidence
  • SEND: Special Educational Needs and Disabilities
  • SCO: Surrey (Structural Changes) Order 2026, the legal order setting up the new councils
  • Vesting Day: The date on which the new councils come into legal existence and take on their powers
  • PMO: Programme Management Office, the team that tracks progress against milestones and risks
  • SRO: Senior Responsible Officer, the senior officer accountable for the programme
  • MHCLG: Ministry of Housing, Communities and Local Government
  • IT&D: Information Technology and Data, a key workstream for systems readiness
  • Section 16: Statutory transfer scheme under the Local Government Act, setting out how property, rights and liabilities transfer to the new councils
  • Inter Authority Agreement: Agreement between the new and continuing councils governing shared services or transitions
  • Foundation Strategic Authority: The proposed strategic authority for Surrey, subject to consultation
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item60/E

Resolved

View the decision text for item 60/E
Word for word from the decision Elmbridge published for this meeting. Source: mygov.elmbridge.gov.uk

Follow this further

Built from Elmbridge's papers

What the report saysPro

Report to East Surrey Shadow Authority Executive

Purpose of the report

The East Surrey Shadow Authority Executive agreed an approach to Local Government Reorganisation (LGR) programme monitoring and assurance on 9 June 2026. This report sets out the latest position in line with that approach. Also included are the updates on programme risks against critical milestones, top programme risks and the latest position related to the implementation fund.

The Shadow Executive is, jointly with the West Shadow Executive, responsible for keeping under review, and revising as necessary, the Implementation Plan for local government reorganisation in Surrey1 and managing the overall Transition Programme. Recommendations are made to the Shadow Executive for arrangements to support these functions.

Recommendations

It is recommended that the East Surrey Shadow Executive resolves to:

1. Note continued progress against critical milestones;

2. Note the movement of the programme assurance position (RAG rating) and the Children’s Theme RAG rating to red due to the impact of the Surrey Local Area Partnership SEND Inspection;

3. Note the current programme risk profile and highest scoring risks; and

4. Note the latest Implementation Fund position.

Reason for recommendations

1 Future Surrey - Implementation Plan -

https://www.surreylgrhub.gov.uk/downloads/file/18/implementation-plan-05-26

OFFICIAL OFFICIAL

1. Under the Shadow Authority’s Constitution, the Shadow Executive is responsible for overseeing and managing the transition programme, including maintaining the Implementation Plan and taking the key executive decisions needed to establish the new council. Agreeing the recommendations in this report will support the Shadow Executive to discharge these functions.

2. The Shadow Executive will receive regular programme updates providing assurance on overall delivery and highlighting areas requiring direction or decision.

Options, including alternatives (if any)

3. The Surrey (Structural Changes) Order 2026 (SCO) requires the Shadow Authority to keep the Implementation Plan under review and, as set out above, the Constitution confirms the role the Shadow Executive has in this. Whilst the Shadow Executive could choose not to accept the recommendations this could hinder their ability to discharge these functions and risks inconsistency in reporting and reduced public confidence in the transition process.

4. Overall, the programme continues to make progress against key milestones set out in the Implementation Plan; however, the pace and complexity of the programme, reflected in the high number of decisions required to be taken at pace, together with recently announced Surrey Local Area Partnership SEND inspection, are impacting the risk profile and will require close management over the coming months.

Summary

Progress and Programme Assurance

5. Due to the timing of the Surrey Local Area Partnership SEND inspection2 having implications for staff capacity, which needs to be focussed on the inspection and any resulting follow up work, LGR programme activity will be impacted, resulting in delays to delivery of activities and potentially milestones. As a result, the Children’s Theme RAG rating has moved from amber to red.

6. A new programme-level issue has been created and assessed at the highest level. The full implications are still being assessed by the Implementation Team, but the anticipated impacts will be wider than just the Children’s theme, as activity

2 Ofsted and the Care Quality Commission (CQC) are carrying out a Special Educational Needs and

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Programme Progress & Assurance Update /EAppendix 1 2 MB Download
PDF
Risk Update /EAppendix 2 393 KB Download
PDF
Implementation Programme UpdateReport 914 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 10 attended
ES
East Surrey Councillor Steve WottonLeader, expected
ES
East Surrey Councillor Kirsty HewensDeputy Leader, expected
ES
East Surrey Councillor Andy BurtonCommittee Member, expected
ES
East Surrey Councillor David BuxtonCommittee Member, expected
ES
East Surrey Councillor Julian FreemanCommittee Member, expected
ES
East Surrey Councillor Abhiram MageshCommittee Member, expected
ES
East Surrey Councillor Claire MalcomsonCommittee Member, expected
ES
East Surrey Councillor Andrew MatthewsCommittee Member, expected
ES
East Surrey Councillor Bradley NelsonCommittee Member, expected
ES
East Surrey Councillor Ashley TillingCommittee Member, expected

On this subject at Elmbridge

Search all
  1. Implementation Programme UpdateThis decision
  2. Implementation Programme UpdateDecided
  3. Implementation Programme UpdateDecided
  4. Implementation Programme Assurance UpdateDecided

More from Elmbridge East Surrey Shadow Authority Executive

All decisions
MeetingDecisionOutcome
9 Nov 2026 Implementation Programme UpdateView the decision text for item 6. Decided Open
9 Nov 2026 2026/27 Quarter 1 Budget Monitoring Report of Existing East Surrey CouncilsView the decision text for item 7. Decided Open
9 Nov 2026 Strategic PartnershipsView the decision text for item 8. Decided Open
9 Nov 2026 Equality Diversity and Inclusion ApproachView the decision text for item 9. Decided Open
9 Nov 2026 Performance Management ApproachView the decision text for item 10. Decided Open