Strategic Partnerships

Decided Executive 4 papers

AI summaryEast Surrey Shadow Authority Executive agreed in principle to progress initial statutory partnerships for Vesting Day, including the Community Safety Partnership for crime, disorder and anti social behaviour. [D][P5][P39][P42] Further statutory partnerships may be agreed in principle under delegation, with no direct financial implications. [D][P7][P58]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedInitial tranche, Community Safety model and delegation included [P5][P7][P38][P39]
MoneyNo direct financial implications [P58]Officer and councillor time is within existing roles [P62]
What happens nextDetailed partnership arrangements to follow [P78]Workstreams develop governance, operating and transitional arrangements [P78]
Who it affectsNot stated

What was decided

The Executive noted the programme wide approach, including that non statutory partnerships will usually continue with limited change unless a legal or operational reason requires otherwise. Report P3, P5, P34

It agreed in principle to progress the first tranche of statutory partnerships, endorsed the proposed Community Safety Partnership governance model, and supported consultation with Responsible Authorities and key partners. Report P5, P38, P39

The Executive delegated to the Head of Paid Service, in consultation with the relevant Portfolio Holder, authority to agree in principle on further statutory partnerships needed for safe and lawful operation from 1 April 2027, while substantive decisions remain subject to the applicable legal, constitutional and governance route. Report P7, P46

Why

Statutory partnerships must be established or otherwise provided for from Vesting Day, because not doing so would be unlawful. Report P11

Deferring would reduce the time available for governance, constitutional and transitional arrangements and could risk readiness for Vesting Day. Report P13

The principal risk is that required governance is not in place, potentially affecting statutory responsibilities and service continuity. Report P51, P53

What happens next

Relevant programme workstreams will develop detailed governance, operating and transitional arrangements for each first tranche partnership, informed by legal and governance advice, while the remaining partnerships come forward as their recommendations are ready. Report P43, P78

Further statutory partnerships needed for safe and legal operation will be considered under delegated authority, with any substantive decision remaining subject to the applicable legal, constitutional and governance route. Report P46, P79

Relevant themes will engage partner organisations, incorporate agreed arrangements into Vesting Day planning and relevant service blueprints, and continue non statutory partnership work with further Executive updates where needed. Report P49, P81, P82

Options considered

  • Rejected: Do not provide the statutory partnerships. Not doing so would be unlawful. Report P11
  • Rejected: Defer the required activities. This would reduce time for necessary arrangements and risk readiness for Vesting Day. Report P13
  • Chosen: Determine how each partnership is constituted and how the Council participates. The approach depends on each partnership's statutory basis, functions and governance requirements, with proposals set out in Appendix 1. Report P12
  • Chosen: Agree in principle to progress each partnership on the basis set out in Appendix 1. Detailed arrangements and further decisions follow the relevant legal, constitutional and governance route. Report P14

Implications

  • Financial: There are no direct financial implications of these recommendations, although officer and councillor time is required within existing roles and responsibilities. The Council faces significant budget pressure, reducing government funding and growing reliance on Council Tax. Report P58, P60, P62
  • Legal: Statutory partnerships must be established or otherwise provided for from Vesting Day, and agreement in principle does not replace further approval required, including inclusion within the constitution. Report P11, P44
  • Legal: The Shadow Authority's progression of partnership transfers falls within its obligations under the Surrey (Structural Changes) Order 2026. Report P64
  • Risk: Failure to put required governance arrangements in place could affect the Council's statutory responsibilities and service continuity. Report P51, P53
  • Risk: Changes to established arrangements could disrupt partnership working or place additional demands on partner organisations. Report P55
  • Staffing: There are no direct workforce implications, but any implications for roles, capacity and ways of working will be identified and managed as detailed arrangements develop. Report P67
  • Equalities: There are no direct equality and diversity implications. Report P74
  • Climate: There are no direct climate change or sustainability implications. Report P76

Who and where

  • East Surrey Council Report P64
  • Existing councils and their officers and councillors Report P16, P62
  • Partner organisations Report P49, P55
  • Responsible Authorities and key partners Report P39
  • Police, fire and rescue, health, probation and other responsible authorities Report P42
  • Service providers Report P16
  • Voluntary and community organisations Report P16
  • Residents and local businesses Report P16

Timeline

  • 1 April 2027: Statutory partnerships must be established or otherwise provided for and continue to operate lawfully. Report P2, P11
  • Following agreement in principle: Relevant workstreams develop detailed governance, operating and transitional arrangements. Report P78
  • Before Vesting Day: Further statutory partnerships needed for safe and legal operation may be progressed under delegation. Report P46, P79
  • October: Recommendations for two statutory partnerships from the Adults theme had already been received by the Shadow Executive. Report P36, P45

Plain English for the jargon

  • Vesting Day: The transition to unitary local government from 1 April 2027, when current District and Borough arrangements end. [P2][P32]
  • Strategic partnership: A formal forum, board, alliance or other arrangement where the Council and partners work together on strategic outcomes or oversee an area of work. [P20]
  • Statutory strategic partnership: A partnership required by legislation, which the Council must establish or participate in. [P21][P24]
  • Non statutory strategic partnership: A partnership not required by legislation, usually managed by a programme theme and expected to continue with limited change. [P3][P21][P34]
  • Community Safety Partnership: A statutory partnership through which the Council works with police, fire and rescue, health, probation and other responsible authorities to tackle crime, disorder and anti social behaviour. [P42]
  • Shadow Authority: The body with obligations under the Surrey (Structural Changes) Order 2026 to progress the transfer of strategic partnerships. [P64]
  • Transition, not transformation: The programme principle of minimal change, except where law requires change or no change would present significant service delivery risk. [P29][P31][P32]
  • Head of Paid Service: The officer delegated to agree in principle on further statutory partnerships, with the member for the relevant portfolio. [P7][P46]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item79/E

Resolved

View the decision text for item 79/E
Word for word from the decision Elmbridge published for this meeting. Source: mygov.elmbridge.gov.uk

Follow this further

Built from Elmbridge's papers

What the report saysPro

Report to East Surrey Shadow Authority Executive

Purpose of the report

This report sets out the programme-wide approach to managing strategic partnerships and seeks agreement to progress an initial tranche of essential statutory strategic partnerships that require governance and/or constitutional arrangements to be put in place for Vesting Day. Activities required in relation to the Community Safety Partnerships is being brought forward to this meeting for specific endorsement of its recommendation; more partnerships will follow as recommendations are ready.

Strategic partnerships play an important role in delivering essential public services across Surrey. As preparations continue for Vesting Day, arrangements must be made to ensure that essential partnerships continue to operate effectively and lawfully from 1 April 2027.

Other partnerships are being managed by the relevant programme workstreams, with the aim of limiting change unless there is a legal or operational reason to act differently.

Recommendations

It is recommended that the East Surrey Shadow Authority Executive resolves to:

1. Note the programme-wide principles and approach to managing strategic partnerships through local government reorganisation in Surrey, as set out in this report; 2. Agree to progress the statutory strategic partnerships identified in Appendix 1, including the specific recommendation regarding Community Safety Partnerships as set out in Appendix 2 and referenced in paragraph 19 this report; 3. Note that further work will be undertaken to develop the detailed governance, operating and transitional arrangements for each partnership, with any further decisions brought through the appropriate governance route; 4. Note that other, non-statutory strategic partnerships are being considered by each programme workstream, with the aim of limiting change at Vesting Day unless there is a legal or operational reason to the contrary;

OFFICIAL OFFICIAL

5. Delegate authority to the Head of Paid Service, in consultation with the relevant Portfolio Holder, to agree in principle the progression of any further statutory strategic partnerships identified as necessary for safe and legal service operation from 1 April 2027, and in accordance with the appropriate governance route.

Reason for recommendations

The recommendations will support the timely establishment of essential strategic partnerships for Vesting Day, while ensuring that the detailed arrangements and any further decisions follow the appropriate governance route.

The proposed delegation will allow any further statutory partnerships needed for safe and legal operation to be progressed in a timely way ahead of Vesting Day.

Options, including alternatives (if any):

The partnerships set out in Appendix 1 are statutory and must therefore be established or otherwise provided for from Vesting Day. Not doing so is unlawful and therefore not an option.

The relevant choice is in how each partnership should be constituted and/or how the Council should participate in it. This will depend on its statutory basis, functions and governance requirements. The proposed approach for each partnership is set out in Appendix 1.

Deferring the required activities is not recommended. This would reduce the time available to put the necessary governance, constitutional and transitional arrangements in place and could risk the Council’s readiness for Vesting Day.

The recommended option is to agree in principle to progress each partnership, on the basis proposed in Appendix 1, with the detailed arrangements and any further decisions progressed through the legal, constitutional and governance route identified for that partnership.

Summary

Local government reorganisation and strategic partnerships in Surrey

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Tranche 1 Statutory Strategic Partnerships /EAppendix 1 215 KB Download
PDF
Community Safety Governance Arrangements for East Surrey & West Surrey /EAppendix 2 187 KB Download
PDF
Completed LGR EIA screener tool /EAppendix 3 734 KB Download
PDF
Strategic PartnershipsReport 247 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 10 attended
ES
East Surrey Councillor Steve WottonLeader, expected
ES
East Surrey Councillor Kirsty HewensDeputy Leader, expected
ES
East Surrey Councillor Andy BurtonCommittee Member, expected
ES
East Surrey Councillor David BuxtonCommittee Member, expected
ES
East Surrey Councillor Julian FreemanCommittee Member, expected
ES
East Surrey Councillor Abhiram MageshCommittee Member, expected
ES
East Surrey Councillor Claire MalcomsonCommittee Member, expected
ES
East Surrey Councillor Andrew MatthewsCommittee Member, expected
ES
East Surrey Councillor Bradley NelsonCommittee Member, expected
ES
East Surrey Councillor Ashley TillingCommittee Member, expected

More from Elmbridge East Surrey Shadow Authority Executive

All decisions
MeetingDecisionOutcome
19 Nov 2026 Consenting to the Formation of a Foundation Strategic Authority for SurreyView the decision text for item 3. Decided Open
19 Nov 2026 Appointment of Electoral Appointee for East SurreyView the decision text for item 4. Decided Open
9 Nov 2026 Implementation Programme UpdateView the decision text for item 77/E Decided Open
9 Nov 2026 2026/27 Quarter 1 Budget Monitoring Report of Existing East Surrey CouncilsView the decision text for item 78/E Decided Open
9 Nov 2026 Equality Diversity and Inclusion ApproachView the decision text for item 80/E Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies